Determining where removable (demountable) insulation structures apply and their construction requirements: metal insulation boxes at frequently serviced positions such as valves, flanges, strainers, manholes and inspection ports, monolithic insulation permissible on straight runs; bolt-removal clearances and acceptance requirements included
Valves, flanges, strainers, manholes, inspection ports, monitoring points, maintenance positions and other frequently dismantled and serviced locations shall (or should) use removable insulation structures, preferably metal insulation boxes in two parts joined by snap fasteners; straight runs and other long-service locations without maintenance needs need not consider removability, and monolithic renders and wrappings are used there. At insulation breaks at flanges, clearance for bolt removal shall be left: for equipment flanges, 3 times the nut thickness on both sides; for pipe flanges, 3 times the nut thickness on the nut side and the bolt length plus 25mm on the other side.
Applicable Codes
- GB 50126-2008 工业设备及管道绝热工程施工规范 第5.11.1、5.11.2、5.11.4、5.11.7、5.11.8条
- GB 50264-2013 工业设备及管道绝热工程设计规范 第6.2.2条
- GB 50645-2011 石油化工绝热工程施工质量验收规范 第5.3.10、5.3.11条
- GB 50041-2008 锅炉房设计规范 第14.1.8条
- GB 50873-2013 化学工业给水排水管道设计规范 第8.2.4条
- GB 50391-2014 油田注水工程设计规范 第9.5.9条
- GB/T 51310-2018 地下铁道工程施工标准 第21.6.3条
- DB11/T 1974-2022 既有居住区综合管廊工程施工技术规程 第6.4.4条
- GB/T 11790-1996 设备及管道保冷技术通则 第6.3.2.3款
Topic positioning
This card answers 'which positions must or should use removable insulation structures (metal insulation boxes), and which may use monolithic renders and wrappings', plus the construction forms of removable boxes, bolt-removal clearances and workmanship acceptance points. A dual-use card for design decisions and construction details, for confirming insulation practices, drawing reviews and insulation acceptance.
Core conclusions
1) General determination: insulation structures need not consider removability, but frequently serviced positions should use removable insulation structures. GB 50264-2013 clause 6.2.2, verbatim: 'Insulation structures need not consider removability, but positions requiring frequent maintenance should use removable insulation structures.'
2) Where 'shall' applies to serviced positions (GB 50126-2008)
- Clause 5.11.1, verbatim: 'Insulation at inspection ports, monitoring points and maintenance positions on equipment or piping shall use removable structures.' Commentary: removable structures, also called demountable insulation structures, are widely used at positions needing frequent maintenance, convenient inspection, or monitoring and testing in production, because such positions are irregular in shape and can be dismantled and refitted; special positions on equipment and piping mainly include flanged valves, pipe creep-measurement points, flow measurement devices, and manhole doors, access doors and expansion joints of tanks and vessels.
- Clause 5.11.2, verbatim: 'For cold insulation at flanges, valves, manholes, handholes and fittings on equipment or piping that are frequently dismantled and serviced, where the medium temperature is low or hard or semi-hard materials are used, the inner cold-insulation layer should be fixed and the outer protective covering should be removable' (with figure 5.11.2-1 valve cold-insulation metal box and figure 5.11.2-2 flange cold-insulation metal box; the build-up is covering - vapour barrier - cold-insulation layer, plus condensate drain pipes and soft material). The commentary notes: GB/T 11790-1996 General principles for cold insulation of equipment and pipes, clause 6.3.2.3, states that cold-insulation structures generally do not consider removability, hence where the medium temperature is low or hard or semi-hard materials are used, the cold-insulation layer should be fixed (integral with the body) and only the outer covering removable.
3) The wording 'must be individually removable' ('shall' in some sectors / local codes)
- GB/T 51310-2018 Standard for construction of underground railway works, clause 21.6.3: 'The insulation at pipe valves, strainers and flanges shall be individually removable.' Commentary: individual removability aids maintenance.
- DB11/T 1974-2022 Technical specification for utility tunnel works in existing residential areas, clause 6.4.4: 'The insulation structure at pipe valves, strainers and flanges shall be individually removable.'
- GB 50873-2013 Code for design of water supply and drainage piping in chemical industry, clause 8.2.4: 'Flanged joints at valves and instruments should use removable insulation.'
- GB 50041-2008 Code for design of boiler rooms, clause 14.1.8: 'Valves and attachments and other equipment and pipes requiring frequent maintenance should use preformed insulation structures easy to dismantle and refit.' Commentary: removable structures ease valve maintenance and allow the insulation to be reused.
- GB 50391-2014 Code for design of oilfield water injection, clause 9.5.9: 'Insulated flanges, valves and manholes requiring dismantling for service may be made as metal or non-metal box insulation structures.'
4) Where monolithic (non-removable) structures fit: straight runs and long-service positions. GB 50264-2013 clause 6.2.2 permits integral insulation structures, and the acceptance check scope is correspondingly limited - GB 50645-2011 clause 5.3.11 commentary, verbatim: 'This clause differs most from clause 5.3.10 in the removability of the structure... but in process checks the scope is limited to removable positions such as inspection ports, monitoring points and maintenance positions; for valves and flanges in long-term service there is no need to check under this clause.' That is: straight runs and long-service valves and flanges without maintenance needs may use monolithic coverings (asbestos-cement render and the like) and wrappings (glass cloth / plastic film wrapping, mastic finishes), measured under covering items by the outer area of the insulation layer.
5) Construction requirements for removable boxes
- Clause 5.11.7, verbatim: 'Removable insulation structures should be a two-part metal insulation box combination, sized to suit the actual item, with the two parts preferably joined by snap fasteners.' Commentary: metal insulation boxes may be fixed by insert-strip connection, steel-band binding, snap fasteners or self-tapping screws; snap fasteners ease dismantling; where space allows, especially for thermal insulation, a two-part metal box combination sized to the item avoids material waste.
- Clause 5.11.8, verbatim: 'Pipe-flange metal insulation boxes should be made as two semi-circles; pipe-valve metal insulation boxes should be in upper-half plus lower-semicircle form, extending up to the gland seal and down to the lowest point of the valve body. When cold-insulation metal boxes are installed, the box shall lap onto the cold-insulation layer at both ends.' Commentary: the valve box covers up to the gland and down to the body bottom to cut heat loss; the end laps make the vapour barrier of the removable structure continuous with the main barrier, improving vapour tightness and cold retention; thermal-insulation boxes may lap over the outer covering.
- Clause 5.11.4, verbatim (bolt-removal clearance): 'The insulation structure at insulation breaks at flanges of equipment or piping shall leave clearance for bolt removal. For equipment flanges, 3 times the nut thickness shall be left on both sides; for pipe flanges, 3 times the nut thickness on the nut side and the bolt length plus 25mm on the other.' Commentary: ample clearance eases replacement of parts and protects the insulation at both ends.
6) Acceptance points (GB 50645-2011 clause 5.3.11, verbatim): 'For insulation works at removable positions on equipment and piping - inspection ports, monitoring points, maintenance positions and the like - beyond complying with clause 5.3.10 of this code, the following shall also be met: 1 there shall be separation between the insulated body and the insulation material; 2 the insulation layer shall be packed dense and easy to remove; where locking devices exist they shall be secure and easy to open. Inspection: visual and measured checks.' The checks target removability (reuse) and protection of the insulated body - a clause specific to removable positions.
7) Pricing interface: removable positions cost three parts - insulation layer volume (m3, valve / flange insulation items), metal covering (insulation box fabrication and installation, by drawn surface area m2), and vapour barrier / covering (m2); monolithic positions are priced under render or wrapping covering items, with no box item.
Applicability boundaries
GB 50126-2008 governs insulation works for industrial equipment and piping: 'shall' for inspection ports, monitoring points and maintenance positions; 'should' for cold insulation at flanges, valves, manholes, handholes and fittings frequently dismantled (and only where the medium temperature is low or hard / semi-hard materials are used). Cold insulation generally does not consider integral removability (GB/T 11790-1996 clause 6.3.2.3) - do not make the cold-insulation layer removable under GB 50264-2013 clause 6.2.2 at the cost of vapour-barrier continuity: only the outer covering should be removable, lapping onto the cold-insulation layer at both ends. The clause 5.3.11 check scope of GB 50645-2011 stops at removable positions and shall not extend to long-service valves and flanges. Removability is a design and workmanship decision and does not change measurement rules; units and item criteria follow the applicable quantity take-off and consumption standards. Permanent, non-reusable preformed insulation is outside this card's removable scope.
Further reading
GB 50126-2008 Code for construction of industrial equipment and piping insulation, clauses 5.11.1, 5.11.2, 5.11.4, 5.11.7, 5.11.8 and their commentaries (figures 5.11.2-1 valve cold-insulation metal box, 5.11.2-2 flange cold-insulation metal box); GB 50264-2013 Code for design of industrial equipment and piping insulation, clause 6.2.2; GB 50645-2011 Code for acceptance of petrochemical insulation construction quality, clauses 5.3.10 and 5.3.11 and commentaries; GB 50041-2008 Code for design of boiler rooms, clause 14.1.8; GB 50873-2013 Code for design of chemical industry water supply and drainage piping, clause 8.2.4; GB 50391-2014 Code for design of oilfield water injection, clause 9.5.9; GB/T 51310-2018 Standard for construction of underground railway works, clause 21.6.3; DB11/T 1974-2022 Technical specification for utility tunnel works in existing residential areas, clause 6.4.4; GB/T 11790-1996 General principles for cold insulation of equipment and pipes, clause 6.3.2.3.
Keywords
- 可拆卸式绝热结构
- 活动式绝热结构
- 金属绝热盒
- 保温盒
- 阀门法兰绝热
- 螺栓拆卸距离
- 经常检修部位
- 绝热层验收