Quantity calculation and quota application for metal protective cladding (aluminium sheet, galvanised iron sheet) over pipe insulation
Metal cladding over pipe insulation is measured in developed cladding area m2, not by pipe length or insulation volume; calculated by the GB/T 50856-2024 Appendix M Table M.11.10 notes item 6 formulas (insulation V = pi x (D + 1.03d) x 1.03d x L; vapour barrier / cladding S = pi x (D + 2.1d) x L, D being pipe outside diameter, d insulation thickness, L pipe extended length); apply the metal cladding items of the painting, anti-corrosion and insulation chapter, banded by material (galvanised thin steel sheet, aluminium alloy sheet etc.) and thickness, pipes and equipment listed separately, seaming and lap wastage already in the material consumptions; pipes over 720 mm diameter are treated as equipment; flange and valve insulation box cladding is calculated separately per Table M.11.10-1.
Applicable Codes
- GB/T 50856-2024 · Standard for measurement of general mechanical, electrical, plumbing and fire services App. M Table M.8.1、Table M.11.10、Table M.11.10-1、Table M.11.10-2
- TB/T 10833-2024 · Budget Quota of Railway Engineering (Volume 12: Locomotive and Rolling Stock Machinery Works) 册说明四、工程量计算规则第1~6条
- GB 50264-2013《工业设备及管道绝热工程设计规范》第5.7.3条
- GB 50126-2008《工业设备及管道绝热工程施工规范》第7.1.1条
- CJJ 28-2014 · Code for Construction and Acceptance of Urban Heating Network Works 第7.3.4条
- DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) App. D Table D.4.59-2(D4-10-222 铝板、D4-10-225 镀锌铁皮)
Scope of the question
The measurement basis and quota item application for metal protective cladding in pipe insulation works - aluminium alloy sheet / aluminium sheet, galvanised thin steel sheet / galvanised iron sheet, colour-coated sheet, thin stainless sheet - together with material selection and workmanship requirements.
Core conclusions
1. Measurement: metal cladding by area in m2, not pipe length, not insulation volume. Metal cladding is the cladding layer under GB/T 50856-2024 Measurement Standard for General Installation Works, Appendix M Table M.8.1 insulation works (code 031208), measured in m2 on the developed (external surface) area; the vapour barrier likewise in m2, the insulation layer in m3.
2. Area formulas (Table M.11.10 notes item 6): among the formulas for insulation, vapour barrier and cladding of vessel shells or pipes, insulation volume V = pi x (D + 1.03d) x 1.03d x L; vapour barrier / cladding area uses the same form with adjustment factor 2.1, i.e. S = pi x (D + 2.1d) x L, where D = diameter (pipe outside diameter), d = insulation thickness, L = vessel shell or pipe length; 1.03 and 2.1 are adjustment factors.
3. Railway quota cross-check (TB/T 10833-2024 Railway Works Budget Quota Manual, Volume 12 Locomotive and Rolling Stock Machinery Works, volume notes Section 4 quantity rules, item 6), source: cladding quantities are calculated in m2 on the design cladding area. Single-layer cladding is the outer-surface perimeter of the protected pipe times its installed length; for multi-layer cladding, the single-layer area is multiplied by the number of layers.
4. No deductions: pipe installation length is the design centre-line length, without deducting valves, flanges and fittings; at bends it is taken to the centre-line intersections (TB/T 10833-2024 volume notes item 1); painting and anti-corrosion quantities follow the design area, ignoring the ridged areas of fittings, flanges and valves (item 4 of the same volume) - metal cladding likewise takes the net developed outer-surface area.
5. Valve and flange insulation boxes separately: flange and valve insulation box cladding is calculated separately per Table M.11.10-1 (unit m2), the insulation layer per Table M.11.10-2 (unit m3), not merged into the pipe cladding area.
6. Large-diameter conversion: GB 50264-2013 Code for Design of Insulation Works of Industrial Equipment and Pipes, Article 5.7.3 note (1): pipes over 720 mm in diameter have their insulation and cladding treated as equipment - i.e. apply the equipment items, not the pipe items.
7. Quota application principle: metal cladding is listed separately from the insulation layer and vapour barrier, applying the metal cladding items under vapour barrier and cladding in the painting, anti-corrosion and insulation chapter; banded by material (galvanised thin steel sheet, aluminium alloy sheet, colour-coated sheet, thin stainless sheet) and thickness, pipes and equipment listed separately; unit m2 (quotas mostly per 10 m2); quantities are net area, seaming and lap wastage of the metal sheet already in the material consumptions, no extra lap area added.
8. Local consumption example (DB11/T 2382-2024 Construction Consumption Standard, Appendix D municipal works, Table D.4.59-2 cladding):
- D4-10-222 cladding, aluminium sheet (m2): labour comprehensive class-2 1.5510 workdays; materials aluminium sheet 2.0000 kg, curing agent 0.0180 kg, coal-tar epoxy 0.1100 kg, primer 0.2500 kg, nylon abrasive disc d100 1.5%; plant other plant 2%.
- D4-10-225 cladding, galvanised iron sheet (m2): labour comprehensive class-2 0.2910 workdays; materials galvanised iron sheet 1.2500 m2 (including 25% wastage, i.e. seaming and laps included), nylon abrasive disc d100 1.5%; plant beading machine 0.0130 machine-shifts, another working machine 0.0120 machine-shifts, other plant 2%. Work content: material working, binding, installation, coating etc.
9. Material selection (where the design is silent): GB 50126-2008 Code for Construction of Insulation Works of Industrial Equipment and Pipes, Article 7.1.1: metal cladding materials should preferably be thin aluminium alloy sheet, colour-coated sheet, galvanised thin steel sheet, thin stainless sheet etc. (an amended article deleting the painted plain thin steel sheet content of the former code). CJJ 28-2014 Code for Construction and Acceptance of Urban Heat-Supply Network Works, Article 7.3.4: metal cladding materials shall satisfy the design; where the design is silent, galvanised thin steel sheet or aluminium alloy sheet is preferred.
10. Cladding workmanship (CJJ 28-2014 Article 7.3.4):
- Before installation, two semicircular beads shall be rolled on both edges of each sheet; for vessel insulation, two crossed stiffening ribs may be rolled on the diagonal of each sheet.
- On horizontal pipes the sheet may be rolled directly over the insulation and installed upslope in the pipe's direction of fall; the circumferential semicircular beads of adjacent sheets shall overlap, and sheet joints shall sit below the pipe.
- Laps shall be riveted at spacings not exceeding 200 mm.
- Cladding shall allow for thermal expansion of equipment and pipes in operation.
- In condensing or damp environments, the cladding shall be filled with sealant or wrapped with sealing tape at the joints.
- No walking on the cladding or stacking of goods on it.
Applicability limits
- Applies to quantity and pricing of thin metal cladding over industrial and civil pipes and equipment insulation, in aluminium alloy sheet (aluminium sheet), galvanised thin steel sheet (galvanised iron sheet), colour-coated sheet or thin stainless sheet.
- Not applicable / charged separately: non-metal cladding (glass cloth, bitumen felt, wire mesh, trowelled coats) under its own codes / items; flange and valve insulation box cladding per Table M.11.10-1; rust removal and painting before insulation itemised under Appendix M.1 painting works (Table M.8.1 notes item 14).
- Layered work: where the design requires insulation layers laid in sequence, state it (Table M.8.1 notes item 5); quantities are calculated layer by layer, applying the items of the required thicknesses.
- Quota item numbers are regional / industry-specific (the example above is Beijing municipal D4-10-222/225; installation works see their vapour barrier and cladding tables split pipes vs equipment); the governing items are those of the project's locality and executed quota; consumptions are versioned data, not to be applied across versions.
Further reading
GB/T 50856-2024 Measurement Standard for General Installation Works, Appendix M Table M.8.1 (insulation works 031208, notes items 1-14: vessel forms, layers, objects, structural forms, layered-work notation, the vessel / pipe insulation, vapour barrier and cladding formulas with the 1.03 and 2.1 factors, the composite value D' for traced pipes, the dished-end formula, the flange and valve insulation box tables); Table M.11.10-1 (flange and valve insulation box cladding, m2) and Table M.11.10-2 (flange insulation box insulation layer, m3); TB/T 10833-2024 Railway Works Budget Quota Manual, Volume 12, volume notes Section 4 items 1-6; GB 50264-2013 Code for Design of Insulation Works of Industrial Equipment and Pipes, Article 5.7.3 (pipes over 720 mm treated as equipment); GB 50126-2008 Code for Construction of Insulation Works of Industrial Equipment and Pipes, Chapter 7, Article 7.1.1; CJJ 28-2014 Code for Construction and Acceptance of Urban Heat-Supply Network Works, Article 7.3.4; DB11/T 2382-2024 Construction Consumption Standard, Appendix D Table D.4.59-2 cladding (D4-10-222 aluminium sheet, D4-10-225 galvanised iron sheet).
Keywords
- 金属保护层
- 管道保温 保护层
- 铝皮 镀锌铁皮 保护层
- 保护层工程量计算
- 保护层定额子目
- 绝热工程 031208
- D4-10-222
- D4-10-225