Thermal insulation quantity calculation rules: part-by-part measurement for roofs, walls, ceilings, columns and beams, and floors (GB/T 50854-2024 Appendix K)

Thermal insulation quantities are mainly calculated by area (sqm) per design-drawn dimensions, with holes uniformly subject to the single-hole 0.3 sqm threshold: walls deduct door/window openings but merge their side faces; ceilings merge the developed area of connected beams, and column capitals merge into the ceiling; exterior walls by the centerline length of the insulation layer, interior walls by net length; pool walls are listed as walls, pool bottoms as floors. BOQ quantities are by area — thickness only enters the item characteristics for pricing brackets and is not multiplied into the quantity.

Applicable Codes

  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. K
  • GB/T 50353-2013 建筑工程建筑面积计算规范 第3.0.24条
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
  • DB11/T 638-2016 房屋修缮工程工程量计算规范 Table A.9.2

Topic Positioning

Part-by-part measurement rules for thermal insulation of the building envelope (GB/T 50854-2024 Appendix K and industry/local quota calibers).

Core Conclusions

Thermal insulation quantities are calculated by area (sqm) per design-drawn dimensions, with holes uniformly subject to the single-hole 0.3 sqm threshold. Roofs deduct holes > 0.3 sqm; walls deduct door/window openings and beams/holes > 0.3 sqm, with opening side faces, attached columns, beam ends, and tie beams merged into the wall; ceilings deduct columns, pilasters, and holes > 0.3 sqm, merge the developed area of connected beams, and merge column capitals into the ceiling; columns and beams by the developed length of the insulation-layer centerline x height/length; floors deduct columns, pilasters, and holes > 0.3 sqm; for pools and tanks, pool walls are listed as wall insulation and pool bottoms as floor insulation. Exterior walls by the centerline length of the insulation layer, interior walls by net length. Vent pipes by m, vent holes by piece. BOQ quantities are by area — thickness only enters item description for pricing brackets and is not multiplied into the quantity.

Applicable Boundaries

Applies to envelope thermal insulation of buildings; pipe and duct insulation belongs to another system (GB/T 50856-2024 Appendix M). Exterior-wall external insulation counting into the gross floor area (GFA) (GB/T 50353-2013 Clause 3.0.24) is a GFA caliber — do not mix it with BOQ measurement. Local quota rules are of the same origin; details follow the current local quota.

Further Reading

GB/T 50854-2024 Appendix K Table K.1.1; GB/T 50353-2013 Clause 3.0.24; DB11/T 638-2016 Table A.9.2; TB/T 10831-2024 Volume 10 volume notes, thermal insulation part.