TB/T 10822-2024 subgrade earthworks: excavator self-dig-self-dump vs excavator loading + dump-truck haul — haul-distance boundaries (20 m / 1 km / 10 km x 0.85)
One criterion: does the excavated soil enter the truck-haulage stage? Soil cast in place within the excavator's working radius -> book "excavator self-dig-self-dump" (LY-1~3, work content "position, dig, dump", no haul); soil requiring dump-truck transfer -> split into "excavator loading" (LY-4~15, by bucket capacity 0.6~2.5 m3 + soil class) + "dump-truck soil haul" (LY-20~25, 8/15/25 t, base item for haul <=1 km plus (actual haul - 1) km of "incremental 1 km" items). Distance boundaries per the chapter notes: loader haul of loose soil applies only within 20 m (beyond that, use dump trucks); truck incremental-haul items apply only within 10 km (the part beyond 10 km x 0.85). The split combination costs roughly 2.8x self-dig-self-dump at base-period prices — book according to the real soil-allocation flow.
Applicable Codes
- TB/T 10822-2024 · Budget Quota of Railway Engineering (Volume 1: Subgrade Works) Ch. 1 路基土石方(分章说明第(一)~(三)条;第一节 土方挖运 LY-1~3、LY-4~15、LY-20~25)
Topic Positioning
The rules for choosing among the soil excavation-haul quota line items in Chapter 1 "subgrade earthworks" of the railway works budget quota manual, Volume 1 Subgrade Works (TB/T 10822-2024): when to book "excavator self-dig-self-dump" (LY-1~3), when to split into "excavator loading (LY-4~15) + dump-truck soil haul (LY-20~25)", and the haul-distance boundary references (20 m / 1 km / 10 km and the 0.85 reduction factor).
Core Conclusions
The single core criterion: does the excavated soil enter the "haulage stage" (dump-truck transfer)?
- Work contents of the three quota families (quota text, which decides how to book):
- Excavator self-dig-self-dump (LY-1~3, <=1.0 m3): work content "position, dig, dump" — dig and dump in place, no haul;
- Excavator loading (LY-4~15, <=0.6/<=1.0/<=2.0/<=2.5 m3, each split into loose/ordinary/hard soil): work content "position, excavate, load" — dig and load, no haul;
- Dump-truck soil haul (LY-20~25, 8 t/15 t/25 t): work content "1. haul <=1 km, including waiting, loading assistance, haul, dump, empty return; 2. incremental 1 km, including haul, empty return" — haulage only.
- Book "self-dig-self-dump" when: the soil is not loaded for off-site haulage and the excavator casts it directly to the dump point — spoil cast beside cuts, short-distance casting in cut-fill balance, on-site stockpiling during grading, and cases where the project execution plan (construction methodology and site organization) expressly states "no rehandling of cut".
- Split into "loading + haul" when: the excavated soil must be transferred by dump truck — whatever the distance, once the transfer point lies beyond the excavator's direct casting range, split into two bookings: excavator loading (selected by bucket capacity + soil class) + dump-truck soil haul (haul = <=1 km base item + (actual haul - 1) km of "incremental 1 km" items). Typical cases: spoil hauled to the disposal site, borrow hauled from borrow pits, longitudinal haul of cut to distant fill sections.
- Haul-distance boundaries (three provisions of the Chapter 1 notes, as written):
- 20 m: "loader loading and hauling of loose soil applies only to the loading, hauling and dumping of loose soil within 20 m; beyond 20 m, dump-truck haulage shall be used" — the only express machine-haul distance boundary in this chapter; although written for loaders, it reflects the compilation logic: within 20 m, load-and-haul can be done in one operation (no split); beyond that, dump trucks must be used. The excavator's actual casting radius is smaller (in practice generally <=10-15 m); apply the split boundary by asking "does it exceed the excavator's working radius?", with 20 m as the conservative upper bound.
- 1 km starting point: dump-truck soil haul takes "haul <=1 km" as the base item; once on trucks, everything within 1 km carries the same price — there is no split discount for a few hundred metres.
- 10 km reduction: "earthworks haulage already allows for road factors (access roads and traffic interference); in earthworks, truck incremental-haul items apply only to haulage within 10 km, and the part beyond 10 km is multiplied by a factor of 0.85" — this is a price-adjustment factor, not a split-booking issue.
- Cost comparison (base-period price basis, to guard against both over- and under-booking): for ordinary soil, excavator <=1.0 m3, per 100 m3, the split combination (loading + truck haul <=1 km) is of the order of 2.8x self-dig-self-dump — do not split across the board to inflate cost, nor book everything as self-dig-self-dump and omit haulage charges; book according to the real destinations in the soil-allocation table of the project execution plan (construction methodology and site organization).
- Easily missed points: cut quantities are measured in natural in-situ (undisturbed) volume (chapter measurement rules); where cut is used as fill, the fill items of this chapter must be booked separately, not just excavation and haul; where spoil requires spreading and compaction, the Section 4 items "site clearing, spoil (rock) spreading and compaction" are added on top of excavation and haul.
Applicable Boundaries
- Applies only to Section 1 "soil excavation and haul" of Chapter 1, Volume 1 Subgrade Works, of the railway works budget quota manual TB/T 10822-2024; for rock excavation and haul (deep-hole/shallow-hole/smooth pre-split/static blasting/controlled blasting classes A/B/C), see the companion card for the same chapter; these rules do not apply.
- The quota sets no hard upper haul distance for "excavator self-dig-self-dump"; the 20 m figure is a reference from the loader clause, not a direct excavator rule — the actual split boundary follows the soil-allocation scheme in the project execution plan (construction methodology and site organization).
- Loader loading and hauling applies only within 20 m and only to loose soil; beyond 20 m, dump-truck haulage shall be used.
- Base prices are quota base-period prices; actual cost is further adjusted for price differences and fee charges under the compilation measures such as TB 10801-2024.
Further Reading
- Quota text: TB/T 10822-2024 Volume 1 Subgrade Works, Chapter 1 "subgrade earthworks": chapter notes (1)-(3) (excavation also covers cut slope trimming and bottom cleaning and borrow-pit finishing; the loader 20 m limit; truck incremental haul within 10 km, the part beyond 10 km x 0.85); Section 1 "soil excavation and haul": I. excavator self-dig-self-dump LY-1~3; II. excavator loading LY-4~15; VI. dump-truck soil haul LY-20~25 (<=1 km base item and incremental-1 km items).
- Companion cards: application of rock controlled-blasting classes A/B/C in the same chapter; earthworks volume conversion factors and spoil disposal estimation (natural in-situ basis); the "three-way comparison method" for quota-application audits; the overall framework for budget compilation and review.
Keywords
- TB/T 10822-2024
- railway works budget quota manual (China Railway)
- subgrade earthworks (earth and rock)
- 挖掘机自挖自卸
- 挖掘机装车
- 自卸汽车运土
- pricing by applying quota line items
- 运距
- 路基工程