Railway 2024 budget quotas — optical/cable trench dig-and-fill pricing: communication TY (trench-km), signaling XY (hm), power DY (hm) — per-discipline measurement and item application
In the railway 2024 quotas (TB/T 1082x-2024), optical/cable trench "dig-and-fill" falls in three discipline volumes: communication Volume 5 TB/T 10826-2024 (TY-9~TY-20, unit "trench-km"); signaling Volume 6 TB/T 10827-2024 (XY-1~XY-31, unit hm, stepped by cable count 1-5/6-10/11-20); power Volume 8 TB/T 10829-2024 (DY-309~DY-321, unit hm). Items = ground class (ordinary/hard soil, soft/sub-hard/hard rock; signaling adds paddy field) x trench depth, dig and fill combined in one item; no volume has frozen-soil items — per Volume 11 TB/T 10832-2024 notes, "frozen-soil excavation may follow the soft-rock items"; communication compiled for 2 cables, +13% consumptions per extra cable; power is loose backfill — compaction via DY-322.
Applicable Codes
- TB/T 10826-2024 铁路工程预算定额 Vol. 5 通信工程
- TB/T 10827-2024 铁路工程预算定额 Vol. 6 信号工程
- TB/T 10829-2024 铁路工程预算定额 Vol. 8 电力工程
- TB/T 10832-2024 铁路工程预算定额 Vol. 11 给水排水工程
Topic Positioning
The pricing rules for optical/cable trench "dig-and-fill" in the railway 2024 budget quotas (TB/T 1082x-2024): which volume per discipline, the units, item stepping (ground x depth; signaling adds cable count), and easily missed add-ons (frozen soil, compaction, cable-count increments). For pricing by applying quota line items and measurement of communication/signaling/power cable trenches in railway works.
Core Conclusions
- Volume per discipline (prefix fixes the discipline; units and consumption levels differ — no cross-volume use):
- Optical-cable and long-distance/regional cable trenches -> Volume 5 communication TB/T 10826-2024, "digging and filling optical (copper) cable trenches" TY-9~TY-20, unit "trench-km";
- Signal cable trenches -> Volume 6 signaling TB/T 10827-2024, "digging and filling cable trenches" XY-1~XY-31, unit hm (hundred metres);
- Power cable trenches -> Volume 8 power TB/T 10829-2024, "digging and filling cable trenches" DY-309~DY-321, unit hm.
Dig and fill combined in one item, not split. Work contents are all "line-marking, trench and joint-pit excavation, backfill (clearing)": communication includes "backfill, tamping, clearing"; signaling "backfill, clearing"; power "clearing, loose fill" (no tamping).
Item logic = ground class x depth:
- Soil trenches: ordinary soil, hard soil (signaling adds a "paddy field" class, depth 1.5 m);
- Rock trenches: soft, sub-hard, hard rock. The power volume's rock items are expressly "non-blast excavation" (DY-317~DY-321; manual soil trenches DY-309~316); the communication volume's rock items price pneumatic excavation;
- Depth steps differ by volume (soil 0.8/1.0/1.2/1.5 m; rock 0.6/0.8/1.3 m) — take the nearest step to the actual depth;
- Signaling additionally steps by cable count: 1-5, 6-10, 11-20 cables — select directly, no conversion.
Frozen soil: no volume has frozen-soil items. The system rule is in Volume 11 water supply and drainage (TB/T 10832-2024) Chapter 2 notes: "Frozen-soil excavation may follow the soft-rock excavation quotas." Apply the soft-rock items — not the soil items.
Communication cable-count increment (TB/T 10826-2024 Chapter 1 note 2 as written): "The 'digging and filling optical (copper) cable trenches' quotas are compiled for laying 2 cables. For each additional cable, consumptions increase by 13% on the corresponding item." No reduction for a single cable.
Power compaction separate: DY-309~321 are "loose fill" without tamping; where the design requires tamping, add DY-322 "cable trench (pit) compaction" (unit 10 m3); communication items already include tamping; signaling content is backfill + clearing.
Companions and measurement: communication has TY-8 "ballast protection and clearing in shoulder sections" (unit trench-km); "pavement cutting and reinstatement" is measured by area = designed trench length x (top width + 0.1 m) (Chapter 1 note 4); communication "duct-trench pumping" is per "section" — between two manholes.
Applicable Boundaries
- Only railway works (TB/T 1082x-2024); urban-road, highway, and power-sector trenches have their own quotas — do not mix.
- Optical (communication), signal, and power cable trenches must use TY/XY/DY respectively — no cross-volume use (units and consumption levels differ).
- Ground classes per each volume's notes and classification basis; judge the actual geology before applying.
- Rock items are compiled for non-blast (pneumatic) excavation and exclude blasting; where blasting is actually used, do not force the non-blast items — handle separately per the rules.
- No base prices listed: base-period prices require price adjustment for fluctuation at the compilation-period price level.
- Haulage rules (loader within 20 m, truck increments within 10 km, etc.) are in Volume 1 subgrade — not developed here.
Further Reading
- TB/T 10826-2024 Volume 5: Chapter 1 Section 1 (TY-8~TY-20), Chapter 1 notes 2-7 (13% increment, sheeting and pumping, pavement-cut area formula, duct-trench pumping).
- TB/T 10827-2024 Volume 6: Chapter 1 Section 1 (XY-1~XY-31, unit hm, steps by count 1-5/6-10/11-20 across ordinary/hard/paddy/soft/sub-hard/hard rock x depth).
- TB/T 10829-2024 Volume 8: Chapter 2 Section 2 (DY-309~DY-322; manual soil, non-blast rock; compaction DY-322 unit 10 m3).
- TB/T 10832-2024 Volume 11: Chapter 2 notes (frozen soil follows soft rock; manual excavation compiled for weak inflow — pumping machinery booked separately; cofferdams and wellpoint dewatering per Volume 2 TB/T 10823-2024).
Keywords
- 挖填电缆沟
- 光缆沟
- railway works budget quota manual (China Railway)
- 沟公里
- 冻土开挖
- TB/T 10826
- TB/T 10827
- TB/T 10829