TB/T 10824-2024 railway tunnel excavation quota: clearance-section step selection and the pricing caliber for overbreak and reserved deformation allowance (Railway works budget quota, Volume 3: tunnel works)
The mining-method excavation quotas of TB/T 10824-2024 "Railway works budget quota, Volume 3: tunnel works" step by clearance section area (minimum clearance cross-section above rail level, taken from the design), all intervals left-closed right-open — a section exactly on a step boundary (42/76/92 m2) takes the next step up. Excavation quantities are computed per the design excavation sections of each surrounding-rock class, including design-allowed overbreak and the reserved deformation allowance (included and priced); construction error and indiscriminate overbreak beyond that envelope are not priced. The quota consumptions are compiled for smooth controlled blasting of rock and exclude design-allowed overbreak and reserved deformation.
Applicable Codes
- TB/T 10824-2024 · Budget Quota of Railway Engineering (Volume 3: Tunnel Works)
Topic Positioning
Two practical questions on the mining-method tunnel excavation quotas of TB/T 10824-2024 Volume 3: which step applies when the section sits between steps (or exactly on a boundary), and whether design-allowed overbreak, the reserved deformation allowance and construction error are priced in the excavation quantities. For compiling estimates and budgets, BOQ rate build-up and final account review of new and rebuilt railway tunnels.
Core Conclusions
- The step parameter is the "clearance section area" — the minimum clearance cross-section above rail level (volume note 6), taken from the design, not the excavation section and not the as-excavated profile.
- Steps by method (m2):
- Pneumatic-mechanical drill-and-blast: 31<=clearance<42; 42<=clearance<76; 76<=clearance<92; 92<=clearance<105, compiled separately;
- Hydraulic jumbo drill-and-blast: 42<=clearance<76; 76<=clearance<=105, compiled separately;
- Mechanical breaking: no clearance distinction;
- Mucking quotas (main tunnel rail-bound/trackless, used with the excavation quotas): no rock-class distinction, loose-volume factors already comprehended; compiled by work-zone length <=500 m plus per additional 500 m, used in overlay; mucking via rail incline or shaft per shaft length <=100 m plus per additional 100 m (including all transloading work at shaft bottom and portal); mucking via incline belt conveyor per incline angle <=15 degrees and length <=500 m plus per additional 500 m.
- Boundary rule: except the last hydraulic-jumbo step, all intervals are left-closed right-open (lower bound included, upper excluded). A section exactly equal to a boundary (S=42, 76, 92 m2) does not belong to the lower step having that value as its upper bound — take the next step up; the last hydraulic-jumbo step 76<=S<=105 m2 is closed. Above 105 m2 there is no higher step — borrow from other quotas per a dedicated project execution plan (construction methodology and site organization) or analyze separately.
- Quantity rule (Chapter 1 Section 1 "5. quantity rules", item 1, as written): "Excavation quantities of the tunnel body, attached chambers, and structures are all computed per the design excavation sections of each surrounding-rock class, including design-allowed overbreak and the reserved deformation allowance." Accordingly, design-allowed overbreak and the reserved deformation allowance enter the excavation quantities and are priced normally; construction error and indiscriminate overbreak beyond the "design section + allowed overbreak + reserved deformation" envelope have no quantity basis and are not priced.
- Consumption-side caliber (Chapter 1 Section 1 note 2, as written): "The drill-and-blast excavation quotas are compiled for smooth controlled blasting of rock and exclude design-allowed overbreak and reserved deformation factors" — overbreak and reserved deformation are not in the consumptions but enter via the quantities (the backfill quantities of shotcrete/lining must be checked separately against the quantity rules of the support and lining chapters); the same note records a blast vibration velocity of 3-9 cm/s within 50 m of tunnel blasting influence.
- Work-zone length (the key parameter for quota overlay, volume note 7): the maximum single-heading construction length from the main tunnel portal or auxiliary adit portal to the division point of the independent work zone, per the project execution plan (construction methodology and site organization); without auxiliary adits, a tunnel <=1000 m is one independent work zone (zone length = tunnel length); >1000 m, the entry and exit zones are computed separately (each bearing half the tunnel length absent separate design); with auxiliary adits, for the independent main-tunnel section constructed via parallel adit/cross adit/incline/shaft, zone length = passage length + the independent main-tunnel section it serves, the parallel adit adding one cross-passage length, the incline adding the shaft-bottom yard length, the shaft adding the shaft-collar ring-gallery length.
Applicable Boundaries
- Applies only to new and rebuilt railway tunnels; mining-method tunnels step by clearance section, TBM and shield tunnels by cutterhead diameter, auxiliary adits by excavation section area — this card's step table does not apply to TBM/shield or auxiliary adits.
- The volume is compiled for normal conditions, reasonable duration and balanced organization; it excludes efficiency-loss factors of high-risk or geologically complex tunnels, which require separate analysis under a dedicated project execution plan (construction methodology and site organization).
- The volume excludes open-cut tunnel foundations, in-tunnel pile foundations, shield-shaft diaphragm walls, shaft-structure concrete, operational ventilation and lighting, fire protection, etc. — borrowed from the relevant railway quotas.
- The excavation quotas exclude natural water inflow pumping; where inflow affects normal construction, analyze per a dedicated dewatering design.
- Stepping follows the design clearance section, regardless of actual excavated dimensions; overbreak/underbreak disputes return to the "design section + allowed overbreak + reserved deformation" envelope.
Further Reading
See TB/T 10824-2024 "Railway works budget quota, Volume 3: tunnel works": volume notes (general notes 1-9 and chapter notes), Chapter 1 Section 1 excavation and Section 2 mucking notes; for the inclusion calibers of design-allowed overbreak / reserved deformation backfill in shotcrete and lining, check the quantity rules of the support and lining chapters. For the general principle see the card "quantities are computed per design dimensions (measure from the drawings)".