TB/T 10825-2024 track quota: single-turnout laying items stepped by straight-through speed (<=120/<=160/<=250) — selection rules and the sleeper-rail-number breakdown within each step

Single-turnout laying quotas step by the turnout's design (permitted) straight-through speed (<=120, <=160, <=250 km/h, etc.); the step follows the turnout product's design speed class (fixed by model/drawing number), not the line's operating speed; heavy-haul freight railways are the exception — per Chapter 2 note 10, "not limited by straight-through speed; select by design rail weight". Within a step, items subdivide layer by layer: sleeper type -> rail type -> turnout number, each number with its own item, base price, and unit (set). The laying quotas exclude turnout and turnout-sleeper materials — pair with the turnout-material quotas of the same speed step.

Applicable Codes

  • TB/T 10825-2024 铁路工程预算定额 Vol. 4 轨道工程 Ch. 2 铺道岔及钢轨伸缩调节器
  • TB/T 3042-2016 铁路道岔型号编制方法

Topic Positioning

The selection rules for single-turnout laying items in Chapter 2 "laying turnouts and rail expansion joints" of TB/T 10825-2024 Volume 4: how the straight-through speed step is chosen, by what dimensions items subdivide within a step, how laying and material quotas pair, and the heavy-haul exception.

Core Conclusions

  1. Step basis: items step by "straight-through speed" (<=120, <=160, <=250 km/h, etc.), taking the turnout product's own design (permitted) straight-through speed class, fixed by the turnout model/drawing number — turnout models are coded per TB/T 3042-2016 "Coding method for railway turnout models", embedding straight/side speed parameters; not by how fast trains actually run. E.g., a 60 kg turnout with 200 km/h permitted straight-through speed takes the <=250 step, not <=160.
  2. Heavy-haul exception (Chapter 2 note 10 as written): "For quotas differentiated by straight-through speed, when used on heavy-haul freight railways they are not limited by straight-through speed; select by design rail weight." — for heavy-haul budgets select by 50/60 kg rail weight, not speed.
  3. Within-step subdivision: each step subdivides "sleeper type -> rail type -> turnout number", each number an independent item, base price, and unit "set":
    • <=120 km/h step GY-253~GY-262 (10 items): concrete turnout sleepers (50 kg No.9/No.12, 60 kg No.9/No.12) + timber sleepers (50 kg No.9/No.12/No.18, 60 kg No.9/No.12/No.18);
    • <=160 km/h step GY-263~GY-267 (5 items): 60 kg rail No.9/No.12/No.18, sleeper types listed separately;
    • <=250 km/h step GY-268~GY-276 (9 items): ballastless turnouts (assembly rough adjustment: embedded long-sleeper No.12/No.18, turnout-slab No.18; fine adjustment No.12/No.18) + ballasted turnouts (pre-assembly and rough adjustment No.12/No.18; fine adjustment No.12/No.18), subdivided by track structure + process + number; no timber sleepers.
  4. Pairing and limits (Chapter 2 notes): (1) laying quotas exclude turnout and sleeper materials — pair with the matching material quotas; turnout-material quotas already include fastenings and non-metallic parts (e.g., rubber pads). (2) Laying excludes switch-stand installation — non-interlocked turnouts pair with the switch-stand installation quota. (3) Laying excludes welding inside and outside the turnout, stress dispersion and locking, and switch-machine installation; ballastless-turnout quotas exclude the cast-in-place concrete and rebar under the turnout. (4) Turnout loading and transport materials include turnout rails, fastenings, sleepers, and switch machines. (5) Temporary track (turnout) laying/removal items are for transitional works per the project execution plan. (6) The loaded-car rolling quota applies only to main-line turnouts on ballasted heavy-haul railways. (7) Combined turnouts combine the single-turnout and double-slip turnout items.
  5. Locating order: design straight-through speed step -> sleeper type (high-speed steps: ballastless/ballasted) -> rail type (50/60 kg) -> number (9/12/18 etc.) — four steps to a unique item; the laying item and the turnout-material item must take the same speed step.

Applicable Boundaries

  • For compiling turnout-laying budgets of mixed passenger-freight and high-speed railways under TB/T 10825-2024 Volume 4.
  • Not applicable: heavy-haul freight turnouts (select by rail weight, no speed limit); non-interlocked turnouts (add switch stands); transitional works (temporary track items); loaded-car rolling limited to main-line ballasted heavy-haul turnouts.
  • Ballastless turnout laying requires separate booking of the concrete, rebar, welding, stress dispersion and locking, and switch machines under and around the turnout.
  • This card details the <=120/<=160/<=250 steps; higher steps (e.g., <=350) exist — compile per the official quota text.
  • Caution: within <=160, GY-265~267 are labeled concrete turnout sleepers in the database, but by price magnitude and number progression they should be timber sleepers (suspected OCR mislabeling) — verify names against the official text.

Further Reading

  • TB/T 10825-2024 Volume 4, Chapter 2 notes (10 clauses); Section 1 turnout laying, 1. single turnouts: (1) straight-through speed <=120 km/h (GY-253~GY-262), (2) <=160 km/h (GY-263~GY-267), (3) <=250 km/h (GY-268~GY-276).
  • Turnout model coding: TB/T 3042-2016 "Coding method for railway turnout models" (models embed straight/side speed parameters).
  • Pair with the "turnout materials" items of the same chapter (fastenings, non-metallic parts included), taking the same speed step.