TB/T 10825-2024 track quota: CWR track laying and rail-material transport compiled at "rail length <=500 m" — laying longer rail strings (unit sections) applies directly, no conversion, no extra booking

Under the railway 2024 quotas (TB/T 10825-2024 Volume 4 track works), long-rail laying for CWR (GY-9~11, GY-24~30) and rail-material transport (GY-31~36) are all compiled at "rail length <=500 m"; units are track-km laid / 1 km of rail material, consumptions amortized per kilometre — "<=500 m" is a compilation basis, not a ceiling. Laying long rails beyond 500 m on site (design unit sections preferably 1000-2000 m, TB 10015-2012 Clause 4.5.1) applies directly, with no conversion factor and no "excess booked separately" clause; rail-string joints use the on-site rail welding quota separately; closure sawing and rail drilling per Chapter 6. Wherever the volume requires adjustment it lists a factor (grade >20 permille x1.5, tunnel >1 km x1.25, both x1.75, etc.); no factor means apply directly.

Applicable Codes

  • TB/T 10825-2024 铁路工程预算定额 Vol. 4 轨道工程 Ch. 1铺轨 册说明及第二节无缝线路
  • TB 10015-2012 铁路无缝线路设计规范 第4.5节 长轨条布置
  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额 第2.4节 价外运杂费
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.4.4条

Topic Positioning

The applicable caliber of the "rail length <=500 m" laying/transport quotas for continuous welded rail (CWR) under the railway 2024 system: how to apply them when the site lays rails longer than 500 m (design unit sections) — the answer: apply directly, no conversion, no extra booking — plus the companion bookings (on-site welding, sawing and drilling, freight outside price).

Core Conclusions

1. Apply directly — no conversion, no extra booking. (1) The quota units are rail-length-independent: long-rail laying items (GY-9 ballastless fastening spread, pre-installation and oiling; GY-10 ballastless long-rail laying; GY-11 ballastless-ballasted transition laying; GY-24 ballasted single-sleeper-method laying; GY-26~28 ballasted relay method for 50/60/75 kg rail) are all in "track-km laid"; rail-material transport items (GY-31~32 ballastless 500 m long-rail loading + 1 km transport; GY-33~34 ballasted single-sleeper loading + 1 km transport; GY-35~36 ballasted relay loading/unloading + 1 km transport) are all in "1 km of rail material". The labor, laying-machine trains, and long-rail flatcar shifts per track-km do not change with the single-rail length being 500 m or longer — there is no object to convert or book separately. (2) "<=500 m" is a compilation-basis statement (matching 500 m long-rail laying trains and transport cars), not an applicability ceiling. The chapter notes (20 clauses of Chapter 1 "track laying") contain no "rail >500 m adjust/book separately" clause; wherever adjustment is required a factor is listed: rail-laying quotas apply only to grades below 20 permille and tunnels under 1 km — above 20 permille multiply labor and plant by 1.5; tunnels over 1 km by 1.25; both by 1.75; yard welding of long rail compiled for 100 m fixed-length rails — welding 25 m fixed-length rails multiplies labor and plant by 0.55; on-site welding inside turnouts by 1.1. Clause 10 states "the rail-material transport quotas are compiled for double-locomotive haul, comprehensively covering all grade factors; locomotive consumptions must not be adjusted for grade". By the quota-usage rules, no stated adjustment means apply directly (consistent with the red line that consumptions may not be adjusted except where expressly permitted).

2. Conceptual distinction: the quota's "500 m" is the single long rail; the long strings laid on site are welded. The quota's "rail length <=500 m" is the single long rail — the ex-works length welded at the welding base from 100 m fixed-length rails (the yard long-rail welding quota counts per "10 joints"); the site's "laying beyond 500 m" is the design rail string (unit section): per TB 10015-2012 "Code for design of railway continuous welded rail", Clause 4.5.1, section unit sections are preferably 1000-2000 m, minimum not less than 200 m, the strings being joined rail by rail by on-site welding after laying. The objects of the laying and transport quotas are always 500 m single rails; the design string length does not affect these two quotas.

3. Companion bookings (note when pricing as separate BOQ items). (1) Rail-string joints: book the "on-site rail welding" quota per joint count (including rail consumed making type-test specimens; other type-test costs sit in the testing fee); (2) closure-gap sawing and rail drilling: not in the laying quota — compute per design quantities with the Chapter 6 sawing and drilling quotas (chapter note 3); (3) freight outside price (welding base -> laying base — a different thing from the quota's rail-material transport): per TB 10811-2024 Section 2.4, for train-freight composite coefficients the "500 m long rail" carries K1=K2=1.43 (100 m fixed-length 1.80; <=25 m rail 1.08); rails beyond 500 m have no separate class — still booked as "500 m long rail"; train/truck handling per Table 2.4.4 rail-class rates (loading 60%, unloading 40%); long-rail supply-related costs are analyzed and booked per the compilation measures.

Applicable Boundaries

  • Applies to TB/T 10825-2024 Volume 4, Chapter 1 Section 2 CWR "long-rail laying (rail length <=500 m)" and "rail-material transport (rail length <=500 m)" items (GY-9~11, GY-24~36).
  • Not applicable to jointed-track laying: the jointed-track material quota's 0.1% rail waste applies to the main line only; for station tracks and new terminal marshalling yards, add 0.1% and 0.2% respectively via the station-track rail-waste quotas.
  • Rail laying applies only below 20 permille grades and under 1 km tunnels; beyond, adjust by the factors above; rail-material transport on in-service lines must not use the transport quotas — compute as freight (chapter note 12).
  • Ballastless-track laying must be used with the ballastless fastening spread/pre-installation/oiling and track-adjustment quotas; the ballastless material quota already includes complete fastenings.
  • Based on the 2024 edition (the 2017 edition carries the same statement with no corresponding adjustment clause); future revisions prevail.

Further Reading

  • TB/T 10825-2024 "Railway works budget quota, Volume 4: track works", Chapter 1 notes in full; Section 2 CWR "2. long-rail laying (rail length <=500 m)" (GY-9~11, GY-24~30) and "3. rail-material transport (rail length <=500 m)" (GY-31~36).
  • TB 10015-2012 "Code for design of railway continuous welded rail", Section 4.5 long-rail string layout: 4.5.1 unit sections; 4.5.3 breathing zones preferably 2-4 pairs of 25 m rails; 4.5.5 stagger of joints at unit-section ends <=100 mm; 4.5.8 glued insulated joints (TB/T 2975-2010).
  • TB 10811-2024 "Fee quotas for design estimates (budgets) of railway capital construction projects", Section 2.4 freight outside price: Table 2.4.1 train-freight composite coefficients (500 m long rail K1=K2=1.43); Table 2.4.2 train/truck handling rates.
  • TB 10801-2024, Clause 3.4.4 item 4 (long-rail supply-related costs).