Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Overhead contact system (OCS) quota pricing calibers: pit stepping, item compilation bases, and measurement rules (TB/T 10830-2024 Volume 9, Chapter 1)

Applying Chapter 1 (23 sections) of TB/T 10830-2024 Volume 9 to OCS works requires checking: pits stepped by soil and depth (sub-hard/hard rock bounded at 2 m, others 3 m; non-blast); fixed compilation bases per item (phi-350 mast, type-A flange foundations, triangular steel-tube portal beams, wedge/cone-sleeve dead-end clamps, GDL6 anchoring beams, etc.) — adjust parts or swap materials where the design differs; wire stringing per "wire-km" with auxiliary-wire reserves 2.5 m/corner anchor and 2.0 m/terminating anchor; messenger-wire waste 1% mechanical / 5% constant-tension stringing; main-material prices and weights booked separately.

Applicable Codes

  • TB/T 10830—2024 · Budget Quota of Railway Engineering (Volume 9: Electric Traction Power Supply Works) Ch. 1 接触网工程
  • TB 10012 · Code for Geological Investigation of Railway Engineering
  • TB 10009 · Code for Design of Railway Electric Traction Power Supply
  • TB 10421 · Standard for Construction Quality Acceptance of Railway Electric Traction Power Supply Works

Topic Positioning

A compilation of the pricing calibers to check when applying Chapter 1 OCS works (23 sections) of TB/T 10830-2024 Volume 9 (electric traction power supply): pit stepping, compilation bases (material models/structures/quantities), units and reserve lengths, waste rates — for preventing misapplication, omissions, and double counting in estimates (budgets) and audit.

Core Conclusions

  1. Pit excavation (Section 1): hard-soil, water-rich clay, flowing-sand, sand-gravel, and soft-rock pits step by "depth <=3 m / >3 m"; sub-hard and hard rock by "<=2 m / >2 m". Water-rich clay means clay with high natural moisture, high compressibility, low bearing capacity, soft-plastic to fluid states, extremely cave-in prone (sludge, organic silty clays and other highly compressible saturated clays and silts). The soft/sub-hard/hard-rock items are compiled for non-blast excavation (the 2024 edition deleted blast items). Pit-drainage items merge into "pit pumping".
  2. Foundation strengthening/casting (Sections 2-3): circular uniform-diameter prestressed concrete mast items compiled for phi-350 masts; "surplus soil removal" within 50 m of the working point, "per additional 1 km" by dump truck (<=15 t); non-hard-rock OCS mast foundation items compiled for type-A flange H-steel mast foundations; "OCS foundations constructed with the subgrade" include pit excavation, embedded rebar, and casting — only for foundations actually built in step with subgrade works, not transferable.
  3. Post-installed anchors (Section 4): anchor materials swapped per the design model; per "spot", the items already include the fixing anchors of that spot's earthing conductor (no separate booking).
  4. Portal beams (Section 5): preassembly items compiled for beam lengths "<=30 m" and "<=40 m"; erection items compiled for triangular steel-tube portal beams.
  5. Cantilevers and steady devices (Sections 7-8): G-type cantilever and L-type steady-device preassembly items are compiled with equipotential bonding leads only between the steady seat and the steady arm — adding one between the steady tube and the cantilever requires material adjustment; L-type items are compiled with bonding leads at both places. Double/triple cantilever seats compiled for channel-steel forms; horizontal-suspension and arch cantilever installation items compiled for non-insulated tension joint sections; in double-track tunnels the contact suspension is booked per up and down line.
  6. Anchoring assemblies and stays (Section 9): spring full-compensation and pulley-block full-compensation items are compiled for wedge-type dead-end clamps; ratchet full-compensation items for cone-sleeve contact-wire dead-end clamps. The 2024 edition adds items for in-tunnel, H-steel masts, and 1:3+1:3 / 1:3+1:4 force-ratio combinations.
  7. Wire stringing (Section 12): per design length in "wire-km"; auxiliary wire length = block length + reserves — 2.5 m per corner-anchor wire, 2.0 m per terminating anchor; messenger-wire waste 1% for mechanical stringing, 5% for constant-tension.
  8. Suspension adjustment (Section 13): bonding-resistance tests per "spot", each based on one lead; dropper materials swapped per design; the 2024 edition deletes intermediate droppers, and elastic stitch and dropper assemblies split into preassembly and installation.
  9. Earthing, return conductors, feeders, positive-feeders and protection wires, overhead earth and lightning wires (Sections 14-18): "low-resistance non-metallic grounding module" items compiled for 4 modules per spot; earthing bonds and jumpers for hard aluminium strand; integrated-earthing connections for earthing cables. Return-conductor brackets compiled for insulated forms (adjust parts for non-insulated); vertical boosting-line items for double cables — 15 m each outside tunnels, 18 m inside. Feeder items: double branch = double brackets, split conductor = double wires; suspension clamps compiled non-preformed; cable termination earthing wires for copper; feeder anchoring beams for GDL6 (channel 6.3). Protection wires all non-insulated; lightning wires insulated — adjust parts where forms differ.
  10. Safety protection and signage (Section 19): "steel height-limit gantry erection" compiled for 5 m limit and 5 m road width; "protection nets, overpass" for 5 m height; "protection nets, cantilever mast" for 2 m2 per spot; "gauge-gate signs" for 8 boards per spot; H-steel mast glued number plates per "board" — count per design; number-plate items include the mast bracket.
  11. OCS testing and adjustment (Section 20): fine adjustment uses the PIII precision network, adjusting static geometry and regularity from trolley inspection; dynamic adjustment tunes arc rate, elasticity, uplift, contact force, dynamic electrical clearances, and twist-related wire-lift coefficients, and re-checks fastening torques; the 2024 edition adds "OCS current-receiving test".
  12. Others: the chapter grows from 21 to 23 sections — Section 22 "other suspension forms" (rigid suspension, integrated cantilevers) and Section 23 "OCS equipment" (adds "surface magnetic sleeper installation").

Applicable Boundaries

  • These calibers apply only to TB/T 10830-2024 Volume 9 Chapter 1; traction substation and depot-supply chapters (2-3) have their own (e.g., 27 sections on structures and pits, foundations, busbars, supports, cables).
  • The compilation bases (phi-350 masts, type-A flanges, triangular tube beams, GDL6, non-preformed clamps, insulated/non-insulated forms) are "quota-included bases": where the design differs, adjust parts or swap materials as the volume notes allow — with basis, never without.
  • Main materials (masts, drop masts, portal beams, contact and messenger wires, auxiliary wires, cables and fittings, insulators) are priced and weighed separately per the "summary table of items containing main materials" — do not double-count in item unit prices.
  • Demolition books only labor and plant with Table 1 factors; on in-service lines, rail-car shifts increase 45%, or 220 kW rail-car shifts are booked at 45% of the electrification work-car shifts.
  • Ground classes per TB 10012; special tests per GB 50150 are outside this volume.

Further Reading

  • TB/T 10830-2024 Volume 9 notes, "Chapter 1 OCS works" chapter notes (23 sections' notes and compilation bases) and foreword (2024 vs TZJ 2009-2017 revisions); item details and the main-material summary table in the volume's appendices.
  • Technical standards: TB 10009 "Code for design of railway electric traction supply", TB 10421 acceptance, TB 10012 ground investigation.