Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

TB/T 10824-2024 railway tunnel shotcrete quantity computation and the pricing rules for rebound and overbreak/reserved-deformation backfill (Volume 3, Chapter 1 Section 3 support)

Per TB/T 10824-2024 Volume 3: shotcrete quantity = spray area x design thickness, the spray area per the design outer profile line, and shall include the quantities to be backfilled with shotcrete for design-allowed overbreak and reserved deformation (mining method also includes design face-sealing quantities). Rebound loss is not in the spray item's consumptions — the quota is compiled as "wet-mix spraying" and "rebound and treatment" separately, rebound taken at 16% of the shotcrete quantity and adjustable per the design (SY-85 spraying / SY-86 rebound and treatment 16% / SY-87 per +/-1%). The quota does not allow for design-allowed overbreak backfill or reserved-deformation backfill — backfill enters via enlarged quantities under the same spray item, not via added consumptions.

Applicable Codes

  • TB/T 10824-2024 · Budget Quota of Railway Engineering (Volume 3: Tunnel Works) Ch. 1第三节 支护

Topic Positioning

The quantity rules and pricing calibers for shotcrete in "Section 3: support", Chapter 1 of TB/T 10824-2024 Volume 3: are quantities per design thickness; are rebound loss and overbreak/reserved-deformation backfill inside the consumptions; and the corresponding item application.

Core Conclusions

  1. Quantities: shotcrete quantity = "spray area x design thickness", the spray area per the design outer profile line; and shall include the quantities backfilled with shotcrete for design-allowed overbreak and reserved deformation (the mining-method chapter notes add "design face-sealing quantities"). That is: quantity = design-profile spray area x design thickness + allowed-overbreak/reserved-deformation backfill (+ face sealing).
  2. Rebound loss is not in the spray item: the quota compiles "wet-mix spraying" and "rebound and treatment" separately (chapter note 3); rebound and treatment is taken at 16% of the shotcrete quantity, adjustable per the design. Items (unit 10 m3): SY-85 support shotcrete, wet-mix machine <=20 m3, spraying; SY-86 rebound and treatment 16%; SY-87 rebound per +/-1%. Booking: rebound = spray quantity x 16% via SY-86; if the design rebound rate is not 16%, adjust per 1% with SY-87.
  3. Overbreak backfill is not in the consumptions: "the quota does not allow for design-allowed overbreak backfill and reserved-deformation backfill factors" (chapter note as written) — the spray item's labor/material/plant consumptions are not increased for backfill; that concrete enters through the quantity rules and still prices under the same spray item. Lining concrete likewise ("the quota allows only for concrete operating waste; design-allowed overbreak backfill and reserved-deformation backfill are not considered").
  4. Interface with the excavation side: heading advance and mucking/haulage quantities are per the design excavation sections including allowed overbreak and reserved deformation (volume note 5); the support side's shotcrete backfill likewise enters its quantities — the two sides match, neither double counting nor omitting.
  5. The spray item's consumptions exclude the concrete mix (SY-85 material cost is only water and sundries — a negligible share of the base price): shotcrete mix is booked under this volume's centralized mixing (shotcrete) items; synthetic/steel fibers add the fiber items.
  6. TBM method: the Section 2 support quotas include TBM on-machine shotcrete, bolts, and steel arches; on-machine mechanical wet spraying is the basis, rebound and treatment refers to the Chapter 1 Section 3 items; the TBM sections likewise exclude allowed-overbreak and reserved-deformation backfill; in-tunnel transport of shotcrete is already comprehended in the mucking and materials-transport quotas.

Applicable Boundaries

  • Applies to shotcrete pricing of primary and temporary support in mining-method main tunnels, auxiliary adits, portals, and surface works under TB/T 10824-2024 Volume 3; TBM-section shotcrete refers to the Chapter 1 Section 3 items.
  • The 16% rebound is the quota's composite value, adjustable per the design — with SY-87 in 1% steps.
  • Overbreak/reserved-deformation backfill enters via quantities, not by adjusting consumptions — never both enlarge the quantities and add consumptions.
  • This card covers shotcrete only; in the same section, bolts are per 100 m (sum of design lengths); rebar mats/mesh/steel arches per design weight (bolt and nut weight excluded); grouted bolts are per 3 m length and 22 mm diameter — swap when the design exceeds 5 m per bolt or differs in spec.
  • Not applicable to building/municipal quota systems (their own chapter notes govern).

Further Reading

  • TB/T 10824-2024 Volume 3, Chapter 1 Section 3 "support" chapter notes and quantity rules (items 1, 3, 10); volume note "5. quantity rules"; items SY-85 (spraying, wet-mix machine <=20 m3), SY-86 (rebound and treatment 16%), SY-87 (rebound per +/-1%), unit 10 m3.
  • For the excavation-side overbreak/reserved-deformation caliber and the clearance-section stepping (left-closed right-open; boundary values 42/76/92 m2 take the next step), see card card_90c144c3-2f3a-42f5-9a63-7feeb367877a.
  • Quota consumptions may not be adjusted at will (except expressly permitted swaps; price adjustment is not quantity adjustment): see card card_bf45be66-c2e1-4f37-ba3b-cc4884d91a38.
  • The desktop evidence is the quota text (not an official .gov.cn page); no official URL to attach.

Keywords