TB/T 10824-2024 railway tunnel mucking quota: applying the out-of-tunnel truck incremental-haul items (SY-82~84) and where the haul distance starts (portal -> spoil site)
Where the out-of-tunnel mucking distance exceeds the distance included in the quota, apply "out-of-tunnel truck incremental haul" SY-82 (dump truck <=10 t, base 12.12 yuan/10 m3) / SY-83 (<=15 t, 9.76) / SY-84 (<=20 t, 8.82), stepped per additional 500 m, unit 10 m3, all plant cost. The out-of-tunnel distance runs from the main tunnel portal or auxiliary adit portal to the spoil site fixed by the project execution plan (construction methodology and site organization) (TB/T 10824-2024 volume note as written); the 2024 edition provides only incremental-haul items out of tunnel, with no separate out-of-tunnel base-distance item.
Applicable Codes
- TB/T 10824-2024 铁路工程预算定额 Vol. 3 隧道工程
Topic Positioning
The mucking pricing rules of the railway 2024 system (TB/T 10824-2024 Volume 3): how to apply the "out-of-tunnel truck incremental haul" items (SY-82~84) once the out-of-tunnel distance exceeds the included distance; where that distance starts (main tunnel portal / auxiliary adit portal -> spoil site); and the mucking quantity caliber.
Core Conclusions
Distance start (volume note as written): "3. For the out-of-tunnel mucking quotas, the start of rehandling or incremental haul is the main tunnel portal or auxiliary adit portal; the end is the spoil site fixed by the project execution plan (construction methodology and site organization)." — the incremental-haul distance = the actual haul route length from the portal (or adit portal) to the spoil site; it does not start at the tunnel face (loading point) and is not mixed with the in-tunnel work-zone length.
Incremental items (Chapter 1 mining-method tunnels, Section 2 mucking, (4) out-of-tunnel mucking — truck incremental haul, unit 10 m3; work content: haul, empty return; steps per additional 500 m, selected by truck tonnage):
- SY-82: dump truck <=10 t, base 12.12 yuan/10 m3 (all plant);
- SY-83: <=15 t, 9.76 yuan/10 m3 (all plant);
- SY-84: <=20 t, 8.82 yuan/10 m3 (all plant). Steps = out-of-tunnel distance / 500 m; each step beyond is booked and multiplied by the item's base price.
Base-distance attribution: the 2024 edition compiles only "incremental" out-of-tunnel items (per additional 500 m), with no separate out-of-tunnel base item — the out-of-tunnel base haul is already comprehended in the in-tunnel mucking base items (work-zone length <=500 m; e.g., trackless mucking SY-59, base 161.23 yuan/10 m3); hence all out-of-tunnel excess is booked via SY-82~84.
Trackless mucking base items (SY-59~66) step by clearance section into four bands — 31<=section<42, 42<=section<76, 76<=section<92, 92<=section<=105 m2; each band has a "work-zone length <=500 m" base item plus a "per additional 500 m" incremental item.
Quantity caliber (volume note "4. quantity rules"): mucking quantities of the tunnel body, attached chambers, and structures are per the design excavation sections, including allowed overbreak and reserved deformation; the work-zone-length rule matches excavation, deducting no auxiliary-adit passage; mucking via auxiliary adits is computed by passage length or own length.
Applicable Boundaries
- Applies to mining-method mucking with out-of-tunnel haul by dump trucks (<=10/<=15/<=20 t), covering main tunnels, auxiliary adits, portals, and related surface works.
- Where in-tunnel haul is rail-bound, use the volume's rail-bound mucking items — the trackless steps here do not apply.
- Rounding of step remainders (part 500 m as one step or rounded) has no express clause in the volume notes — determine per TB 10801-2024 and the project's compiling rules.
- Non-truck out-of-tunnel haul follows the relevant items of this volume or the relevant discipline quotas.
Further Reading
- TB/T 10824-2024 Volume 3: volume notes "3. out-of-tunnel mucking quotas", "4. quantity rules"; Chapter 1 Section 2 "mucking": (2) trackless mucking SY-59~66; (4) out-of-tunnel mucking "truck incremental haul" SY-82~84.
- Companion: TB 10801-2024 "Measures for compiling design estimates (budgets)..." (distance rounding and charging caliber); spoil sites and haulage organization per the approved project execution plan (construction methodology and site organization).
- For the excavation stepping and overbreak/reserved-deformation caliber, see the card "tunnel excavation quota clearance-section stepping" — the mucking quantities interface with the same caliber.
Keywords
- 隧道出渣
- 洞外汽车增运
- 洞外运渣
- SY-82
- SY-83
- SY-84
- 无轨出渣
- TB/T 10824
- 出渣运距
- 矿山法隧道