Confirming spoil haul distance in municipal earthwork: centroid method, confirmation priority, and quota norms structure
Spoil haul distance = the shortest distance along the actual transport route from the excavation centroid to the spoil centroid, with positions determined in accordance with the approved project execution plan (construction methodology and site organization); confirmation priority: contract/BOQ stipulation > approved project execution plan (construction methodology and site organization) (centroid method) > site instruction / variation record and measurement; the quota norms (prescribed resource consumption standards) are structured as 'base haul <= 1 km + each additional 1 km' stacked, with less than 1 km counted as 1 km; outward haul quantity is measured by natural in-situ (undisturbed) volume with no separate loose coefficient, and on-site transport is not double charged.
Applicable Codes
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 A.4.13
- GB/T 50857-2024 市政工程工程量计算标准
- SJG 84-2020 市政维修工程消耗量标准 第二册 6.1.17、7.1.17
- GB 50202-2002 建筑地基基础工程施工质量验收规范 6.1.1
- TB/T 10832-2024 铁路工程预算定额 Vol. 11
Topic Positioning
How to confirm the outward haul distance of municipal earthwork, i.e. disposal of surplus (excavated) material: the distance definition, confirmation priority, quota line item structure, and settlement chain of evidence, for pricing and settlement disputes.
Core Conclusions
(1) Distance definition: the shortest distance along the actual vehicle route from the centroid of excavated (demolished) material to the centroid of the spoil (dumping) location, with centroid positions determined in accordance with the approved project execution plan (construction methodology and site organization). (2) Confirmation priority: contract/BOQ stipulation (the item description (work item specification) for disposal of surplus (excavated) material must describe the spoil haul distance; work content includes loading, unloading and transport) > approved project execution plan (construction methodology and site organization)/spoil disposal scheme (centroid method) > site instruction / variation record and measurement; in disputes the contractor bears the burden of proving actual haul distance (transport contracts, weighbridge slips, GPS tracks, disposal-site receipts). (3) Quota norms structure: machine-loaded dump-truck earth haulage is generally 'base distance (<= 1 km) + each additional 1 km' stacked, with less than 1 km counted as 1 km; manual vertical haulage distance is converted to horizontal haulage distance at a factor of 7. (4) Measurement basis: outward haul quantity is measured by natural in-situ (undisturbed) volume before excavation, with no separate loose coefficient added; the BOQ already includes on-site transport — haul distance is calculated only for off-site transport to prevent double charging. (5) Balance first: earth allocated and reused on-site is not included in outward haul distance; cut-fill balance should be done well, and surplus earth should be hauled in one go to the designated spoil site.
Applicable Boundaries
Applies to confirming and settling haul distances for disposal of surplus (excavated) material in municipal/building earthwork; provincial quota norms may differ in base distance and incremental step (0.5 km/1 km etc.) — the local quota norms govern; where the contract stipulates a lump-sum all-in haul distance, the contract applies and the centroid method does not; changes to the spoil site must be promptly recorded by site instruction / variation record and evidenced.
Further Reading
GB/T 50854-2024 Appendix A earthwork A.4.13 disposal of surplus (excavated) material (for the municipal equivalent see GB/T 50857-2024); SJG 84-2020 Municipal Maintenance Works Consumption Standard, Volume 2, Clauses 6.1.17 and 7.1.17 (centroid method and rounding up under 1 km); GB 50202-2002 Clause 6.1.1 earthwork balance allocation; railway TB/T 10832-2024 Volume 11 PY-129~136 earth haulage quota line item structure example.
Keywords
- 土方外运
- 运距确认
- disposal of surplus (excavated) material
- 弃土场
- 重心法
- 增运1km
- 土方运输
- 弃土运距