Railway 2024 quotas: applying concrete mixing/transport items — HT-0 placing items exclude mixing, transport, and materials; use basic-quota Chapter 4, with haul as loading/unloading + per-1 km increments (TB/T 10821-2024)

Under the railway 2024 quotas, concrete cost is applied in four segments: the discipline volumes' "HT-0" placing items exclude mixing, transport, and concrete materials — apply TB/T 10821-2024 Chapter 4 (mixing YY-41~46, transport YY-47~57); the unit 10 m3 means the concrete volume in the works; transport is two-step "loading/unloading item + per-1 km increment item", increments split plains/hills vs mountains/in-tunnel, small vehicles per 50 m.

Applicable Codes

  • TB/T 10821-2024 铁路工程基本定额
  • TB/T 10822-2024 铁路工程预算定额 Vol. 1 路基工程
  • TB/T 10825-2024 铁路工程预算定额 Vol. 4 轨道工程
  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
  • TB/T 10813-2024 铁路工程材料基期价格
  • TB/T 10814-2024 铁路工程施工机具台班费用定额

Topic Positioning

The quota-application rules for concrete cost in the railway 2024 system (TB/T 10821-2024 and the discipline volumes): how placing, mixing, transport, and materials are applied separately; the scope of Chapter 4 (YY-41~57); and the "loading/unloading + increment" conversion when the design haul differs from the quota.

Core Conclusions

  1. Concrete in four segments; HT-0 placing excludes mixing, transport, materials:
  • TB/T 10825-2024 Volume 4 note 3 as written: "The cast-in-place concrete items (HT-0) of this volume exclude concrete mixing, transport, and concrete materials — book separately by the relevant 'basic quota' items."
  • TB/T 10822-2024 Volume 1 note 2 as written: "Items marked 'HT-0' exclude concrete mixing and materials; cast-in-place concrete excludes off-site transport — book the excluded contents by the 'basic quota' items. Off-site transport here means transport from the temporary yard to the work point."
  • Basic-quota general note 5 as written: "For concrete with computer code 'HT-0', the items carry no 'material cost', 'weight', or constituent materials... book separately per the design materials."
  • Full chain (per 10 m3): (1) placing via the discipline volume's HT-0 item; (2) mixing via Chapter 4 Section 1 YY-41~46; (3) transport via Section 2 YY-47~57; (4) concrete materials per the design mix and prices.
  1. Chapter 4 covers only mixing and transport (note 1 as written: "This chapter compiles concrete mixing and transport.") — placing is not here:
  • Section 1 mixing YY-41~46: batching plant capacity <=90/<=120/<=180 m3/h (bases 186.88/167.10/140.30 yuan/10 m3); mixers <=250 L/<=400 L/<=800 L (398.35/380.46/249.30). Content: batching, mixing, discharge, cleaning.
  • Section 2 transport YY-47~57: agitator truck <=8 m3 loading/unloading YY-47 (159.94); per 1 km plains/hills YY-48 (24.31); mountains/in-tunnel YY-49 (32.05); <=10 m3 YY-50 (168.32) / YY-51 (22.00) / YY-52 (29.77); <=12 m3 YY-53 (175.11) / YY-54 (20.26) / YY-55 (27.50); small vehicles loading/unloading YY-56 (258.69), per 50 m YY-57 (11.76). Loading/unloading: load, turn, unload, clean; per 1 km: haul, empty return.
  1. Caliber points (chapter notes): the unit 10 m3 is the concrete volume in the works; site handling and operating waste not included; "in-tunnel" means completed tunnels; the "water" in mixing/transport consumptions is equipment-cleaning water.

  2. Conversion when haul differs from design: transport is "loading/unloading (base) + increment": transport cost = loading/unloading base + per-1 km base x excess kilometres (all per 10 m3; per-1 km items all plant). Increments split "plains/hills" and "mountains/in-tunnel" by the route; small vehicles increment per 50 m (YY-57) — short hauls in multiples of 50 m; the "mountains/in-tunnel" band only for completed tunnels.

Applicable Boundaries

  • For compiling railway discipline quotas (buildings excepted) and estimates (budgets); "rebar transport", "concrete mixing", "concrete transport", and "short-haul material transport" apply to estimate (budget) compilation for railway works excluding buildings (general note 1).
  • Compiled for rational organization and normal conditions; implementation-stage prices are market-determined (general note 2).
  • No placing (in the discipline volumes), no concrete materials (HT-0 booked per design); site handling and operating waste not included — rates in Chapter 10; otherwise material waste included.
  • Labor prices per TB 10811-2024; materials per TB/T 10813-2024; plant per TB/T 10814-2024.
  • Dimensions: unmarked are mm; "within/below" include the upper limit; "~" includes the upper limit.
  • This card covers Chapter 4 mixing/transport and the HT-0 rule only; special transport items in the tunnel and over-water chapters follow their own volumes.

Further Reading

  • TB/T 10821-2024: general notes (scope, HT-0, price bases); Chapter 4 — Section 1 mixing YY-41~46, Section 2 transport YY-47~57; Chapter 10 waste rates.
  • TB/T 10822-2024 Volume 1 notes (HT-0 excludes mixing and materials; cast-in-place excludes off-site transport; definition of off-site transport).
  • TB/T 10825-2024 Volume 4 notes (HT-0 excludes mixing, transport, materials — basic quota items directly).
  • Price companions: TB 10811-2024, TB/T 10813-2024, TB/T 10814-2024.