Composition, charging and cost attribution of spoil-site costs and residue disposal fees (tipping fees)

Spoil-site costs are costs arising around the "site" (temporary land occupation, site protection, reclamation); under the railway approach they are booked as temporary land use costs within project costs other than the works, and are usually borne by the employer. The residue disposal fee (tipping fee) is a paid disposal charge levied for dumping surplus mud and residue at government-designated reception sites, under a charging system, charged per local price documents in yuan/m³, and is included by the contractor in the all-in unit rate for surplus-spoil disposal. The two are different in nature and must not be mixed.

Applicable Codes

  • SJG 86-2020
  • 建设部令第139号 城市建筑垃圾管理规定
  • GB/T 50857-2024
  • GB/T 50854-2024
  • TB 10801-2024
  • TB 10001-2016

Topic Positioning

This card clarifies the cost composition, charging paths and cost attribution of two easily confused concepts — "spoil-site costs" and "residue disposal (tipping) fees" — for reference in the preparation of estimates and budgets and in the handling of settlement disputes on municipal, building and railway works.

Core Conclusions

The two differ in nature and in charging path:

  1. Residue disposal fee (tipping fee) = the paid disposal charge levied by the surplus mud and residue authority for dumping surplus mud and residue at fixed reception sites, under a charging system, charged per local government price documents in yuan/m³ (or yuan/tonne). Where the surplus-spoil BOQ item gives rise to disposal and stockpiling costs, its work content shall include the disposal and tipping required by local regulations; the cost of treatment and disposal provisions for non-recyclable construction waste is charged separately in accordance with local environmental requirements. On the contractor's side: all-in unit rate for surplus-spoil disposal ≈ transport cost (quota line items applied by haul distance) + residue tipping fee.
  2. Spoil-site costs = costs arising around the "site": temporary land occupation fees (land lease, crop compensation, demolition compensation, management fees, etc.), site protection works costs (retaining, drainage, fencing and warning signs, green protection), reclamation costs (topsoil stockpiling and respreading, levelling and restoration). Under the railway approach they are booked within project costs other than the works — as temporary land use costs within land acquisition (lease) and demolition compensation — and are generally borne by the employer; site protection works are priced by applying the corresponding quota line items to the design quantities.

Applicable Boundaries

Applies to the charging of the outward haul and disposal of spoil; not applicable to borrow/borrow-pit sites (opposite direction), internal allocation without outward haul, or special disposal of tunnel spoil. Local price documents differ in their basis (yuan/m³ or yuan/tonne, whether transport is included); the specific rates and their attribution follow the documents in force at the project location and the contract.

Further Reading

SJG 86-2020 Standard for Compilation of Estimates for Building and Municipal Works, 4.4.12 (surplus mud and residue disposal fee); Provisions on the Administration of Urban Construction Waste (Ministry of Construction Order No. 139), Article 16 (system of charging for disposal); GB/T 50857-2024 Appendix A.4.10, GB/T 50854-2024 Appendix A.4.13 (the work content of surplus-spoil disposal includes tipping); TB 10801-2024 Measures for Compiling Design Estimates (Budgets) for Railway Capital Construction Projects, 3.11.2 (temporary land use costs include borrow and spoil sites); TB 10001-2016 Code for Design of Railway Subgrade, 15.4 (reclamation and protection of borrow and spoil sites).