Cut-and-fill balance calculation and allocation method for municipal road earthwork

The core of cut-and-fill balance: compute quantities by the cross-section method (average-end-area / prismoidal formula) or the grid method -> convert fill to natural in-situ (undisturbed) volume (compacted volume / 0.87 ~= 1.15x) -> compare and determine use/borrow/spoil -> allocate nearby with minimum haul distance. Code basis: GB 50201-2012, GB 50842-2013 Clause 5.1.3, CJJ 44-91 Clause 5.1.3.

Applicable Codes

  • GB 50201-2012 土方与爆破工程施工及验收规范
  • GB 50842-2013 建材矿山工程施工与验收规范
  • CJJ 44-91 城市道路路基工程施工及验收规范

Topic Positioning

A general method for cut-and-fill balance calculation and allocation in linear works such as municipal roads, covering earthwork quantity calculation, volume-state conversion, balance determination, and nearby allocation, providing reusable calibers and code basis.

Core Conclusions

(1) Quantity calculation: for linear works, measure cross sections by chainage along the centerline; average-end-area method V=(A1+A2)/2 x L; when higher precision is required use the prismoidal formula V=L/3 x (A1+A2+sqrt(A1 x A2)); for site leveling use the grid method (construction height = design elevation - natural elevation, summed block by block). (2) Conversion: cut-fill comparison must be unified to natural in-situ (undisturbed) volume — 1 m3 of natural in-situ (undisturbed) soil compacts to about 0.87 m3, i.e., fill requirement (natural) = design compacted volume / 0.87 (about 1.15x). (3) Determination: cut > fill requirement -> surplus spoil hauled away; < -> borrow soil; equal -> fully balanced (usually hard to achieve in road works, and reasonable allocation is allowed). (4) Allocation: take and dump nearby, cut before fill, avoid cross-hauling, coordinate zones with the whole line (GB 50842-2013 Clause 5.1.3); earthwork allocation means comprehensively balancing the spoil quantity with the backfill usage (GB 50201-2012 Clause 2.0.1). (5) Additional items: topsoil stripping (humus soil must not be used for subgrade fill), increments/decrements from soft-ground replacement, and pipeline trench earthwork listed separately and then merged into the overall balance.

Applicable Boundaries

Applies to planning/budget-stage earthwork balance and allocation schemes; conversion coefficients differ among regional quotas — the current local quota and geotechnical tests govern, and this card's calibers do not constitute a basis for settlement. Layered backfill requires the lower layer's compaction-coefficient test to pass before constructing the upper layer; loose-lift thickness and roller passes are determined by trials (GB 50201-2012 Clause 4.5.4); the compaction width of cut and no-cut-no-fill subgrades extends 20 cm beyond each side of the roadbed (CJJ 44-91 Clause 5.1.3), and roadbed-processing quantities should be listed separately in the balance.

Further Reading

See GB 50201-2012 "Code for construction and acceptance of earthwork and blasting engineering" Clauses 2.0.1, 4.5.4 (compaction testing: ring-cutter, sand-cone, water-filling, water-bag methods); GB 50842-2013 "Code for construction and acceptance of building-materials mine engineering" Clause 5.1.3 (four principles of balance allocation); CJJ 44-91 "Code for construction and acceptance of urban road subgrade engineering" Clause 5.1.3. Deliverables are the earthwork balance table (chainage/zone x cut/fill/use/borrow/spoil, allocation direction, haul distance) and the earthwork allocation diagram.

Keywords

  • 土方挖填平衡
  • 土方调配
  • 天然密实方
  • 压实方
  • 横断面法
  • 平均断面法
  • 方格网法
  • 借土弃土