The loose-laying coefficient of earthworks: standard definition, formulas and how it is fixed - trial sections, back-calcculating loose thickness from the degree of compaction, and converting stockpile quantities
Loose-laying coefficient K = loose thickness / compacted thickness = compacted dry density / loose dry density (GB 51254-2017 clause 2.1.4; CJJ 4-97 Appendix F formula F.0.3); earthworks have no code value table - K must be fixed by compaction trials (trial sections) per the fill-material x compaction-equipment pair, codes giving values only for specific materials (graded crushed stone 1.4~1.45 hand-mixed, 1.3~1.35 grader-spread); back-calculation: loose dry density = max dry density x degree of compaction / K, and loose / stockpile volume = compacted volume x K.
Applicable Codes
- GB 51254-2017 高填方地基技术规范 第2.1.4条
- GB 50201-2012 土方与爆破工程施工及验收规范 第4.5.4条
- GB 50202-2018 建筑地基基础工程施工质量验收标准 第9.5.2条
- GB 51004-2015 建筑地基基础工程施工规范 第8.5.4、8.5.6条
- CJJ 4-97 粉煤灰石灰类道路基层施工及验收规程 附录F 式(F.0.3)
- GB 50842-2013 建材矿山工程施工与验收规范 第9.6.6条、附录B
- CJJ/T 286-2018 土壤固化剂应用技术标准 第6.2.4条
- DB11/T 1832.1-2021 建筑工程施工工艺规程 第1部分:地基基础工程 第35.4.5条
- TB/T 10822-2024 铁路工程预算定额 Vol. 1 路基工程 册说明表2
- TB/T 10832-2024 铁路工程预算定额 Vol. 11 给水排水工程 册说明表1
Positioning
The standard definition, formulas, field determination and fixing path of the loose-laying coefficient K in earth and fill placement, the chain from design degree of compaction back to loose thickness, spread volume and stockpile quantity - and the boundary against three confusable concepts: coefficient of compaction, the looseness coefficient of soil, and volume conversion factors.
Core conclusions
1. Definition (original text) GB 51254-2017 Code for High Fill Foundations, clause 2.1.4: "Loose-laying coefficient: in placement, the ratio of the loose-laid thickness of the fill to its thickness after compaction (ramming)."
2. Two equivalent formulas
- Thickness (construction control): loose thickness = compacted thickness x K; GB 50842-2013 clause 9.6.6 reads "loose-laid thickness = compacted thickness x loose-laying coefficient".
- Density (materials testing): K = compacted dry density / loose dry density. CJJ 4-97 Appendix F, F.0.3: H is the loose thickness (cm), h the compacted layer thickness (cm), K = compacted dry density / loose dry density (both t/m3).
- The two field methods cross-check: 1) levels (geometry) - survey the loose surface after spreading and levelling, and the compacted surface after passing, K = loose / compacted thickness at the same points; 2) densities (materials) - measure loose and compacted dry densities. Compaction is checked by the ring-cutter, sand-replacement, water-replacement or water-bag methods (GB 50201-2012 clause 4.5.4; GB 50202-2018 clause 9.5.2 - ring-cutter, sand- and water-replacement).
3. Fixing principle: no code table for earth, trials only
- GB 50201-2012 clause 4.5.4: "Backfill shall be compacted to the design coefficient. In layered backfill, the next layer may proceed only after the lower layer's coefficient passes testing. Loose layer thickness and roller passes are fixed by test per soil class and compaction equipment."
- GB 50202-2018 clause 9.5.2: "Check during execution the drainage, layer thickness, roll overlap, moisture control, organic content and compaction coefficient. The coefficient shall meet the design; layered backfill proceeds only after the lower layer passes. Layer thickness and passes are fixed by soil, coefficient and equipment; without test data, Table 9.5.2 applies." And: "For important works the placement parameters (layer thickness, passes, coefficient) shall be set by field trial or by the designer."
- GB 51004-2015 clause 8.5.4: choose equipment from the works, soil, design coefficient and conditions; fix moisture range, layer thickness and passes; important backfill or new equipment - by trial. DB11/T 1832.1-2021 clause 35.4.5: layer thickness per soil, density requirement and equipment; without tests, its table applies.
4. Code values only for specific materials
- GB 50842-2013 clause 9.6.6: "The loose-laying coefficient of aggregates (loose / compacted dry density) or compaction factor is fixed by test: hand-mixed graded crushed stone 1.4~1.45; graded gravel 1.45~1.5; grader-spread both 1.3~1.35."
- CJJ/T 286-2018 clause 6.2.4: loose thickness = compacted thickness x K, each layer no more than 300mm; commentary: K is decisive for stabilised-soil layers and comes from trial sections; heavy rollers' optimal compacted thickness is 18~22cm, over 25cm the bottom under-compacts; machine-laid K is usually around 1.2, so loose thickness should not exceed 30cm.
- Ordinary and cohesive soils, machine-spread: no code value; practice starts at 1.15~1.25 (examples often 1.2) - for trial-section layout and scheme estimates only, never acceptance or settlement.
5. The conversion chain compaction -> loose thickness -> stockpile
- Compacted dry density = max (heavy-compaction) dry density x design degree of compaction.
- Loose dry density = compacted / K = max x degree / K.
- Loose thickness = compacted x K; with compacted volume known, spread / stockpile volume = compacted volume x K.
- Compact to other states (borrow, off-haul): per TB/T 10832-2024 Table 1 volume conversion factors (loose 1.00 / loose-fill 0.83 / natural dense 0.77 / compacted 0.67; equivalently natural 1.00 = loose-fill 1.08 = compacted 0.87 = loose 1.30): compacted x 1.15 = natural dense; compacted x 1.50 = loose.
- Example: compacted 0.30m, K = 1.2 - loose 0.36m; max density 1.85 g/cm3, degree 0.94 - compacted 1.739, loose 1.739/1.2 = 1.449 g/cm3; compacted 10000 m3 - loose (stockpile) 12000 m3, natural dense about 11490 m3 (x 1.149), loose 15000 m3 (x 1.50).
6. Term traps and quota treatment
- CJJ 4-97 Appendix F calls K the "coefficient of compaction" (= compacted / loose dry density) - numerically the loose-laying coefficient; but the "coefficient of compaction" in GB 50201-2012 / GB 50202-2018 is compacted / maximum dry density (the degree of compaction, 0.90~0.96). Same name, different meaning - never interchange.
- Distinct from the "looseness coefficient of soil" (GB 50842-2013 Appendix B Table B.0.1): that covers excavation of intact ground (for haul and stockpile volumes), not placement thickness control.
- Railway quota measurement: TB/T 10832-2024 volume note 5(1) - "earth and rock measured in natural dense volume; backfill in compacted (rolled) volume; surplus and stockpiled soil on the loose-soil items", with Table 1 factors; TB/T 10822-2024 Table 2 gives dense-to-compacted factors by design speed (over 200 km/h: sections - loose soil 1.258, ordinary soil 1.156, hard soil 1.115, rock 0.941; stations 1.230/1.130/1.090/0.920; 160<v<=200: 1.225/1.133/1.092/0.921, stations 1.198/1.108/1.068/0.900; v<=160: 1.125/1.064/1.023/0.859, stations 1.100/1.040/1.000/0.840; the factors already include the widened-side allowance).
- Key basis: K does not change billed quantities (natural dense or compacted volume) - it serves thickness control and stockpile / borrow estimates only.
7. Companion compaction practice (GB 51004-2015 clause 8.5.6) Roll (ram) passes overlap; mechanical compaction controls travel speed; corners and confined areas by hand; large areas in layers and blocks with sloped interfaces, roll overlap 0.5~1.0m, layer thickness and passes per its table, adjacent interfaces staggered at least 1m; roller overlap width 150~250mm, speed about 2 km/h.
Applicable boundaries
- K binds one-to-one to fill type, moisture, spreading plant, compaction equipment and passes - no shared parameter sets across materials or machines.
- Trial-section practice: each material x equipment pair separately; 3~5 loose thicknesses (e.g. 25/30/35cm) x pass counts; measure coefficient and settlement per combination; take the most economical passes reaching a stable design coefficient, back-calculate K, and obtain the supervisor's approval before full-area work.
- 1.15~1.25 / "about 1.2" are starting values - never acceptance, settlement or design bases; replace with trial values wherever trials exist.
- Rock fill, stony mixed fill with high rock content and dynamic compaction (controlled by settlement) do not fit the soil K parameter; the 1.3~1.5 for graded stone/gravel fits only its stated spreading and mixing methods.
- The density formula needs rc and rd by the same method and comparable state (same moisture, same pit / cutter); else K distorts.
- Quota volume factors (1.30/1.08/0.87/0.67 etc.) never invert into thickness control; K and degree of compaction differ in numerator/denominator - no mixing.
Further reading
- GB 51254-2017 clause 2.1.4; GB 50201-2012 clause 4.5.4; GB 50202-2018 clause 9.5.2 and Table 9.5.2; GB 51004-2015 clauses 8.5.4, 8.5.6 and Table 8.5.6; CJJ 4-97 Appendix F; GB 50842-2013 clause 9.6.6 and Appendix B Table B.0.1; CJJ/T 286-2018 clause 6.2.4; DB11/T 1832.1-2021 clause 35.4.5; TB/T 10822-2024 Table 2; TB/T 10832-2024 volume note 5(1) and Table 1.