Determination of the loose-laying coefficient (compaction coefficient) and the paving wastage rate of asphalt mixtures
The loose-laying coefficient (= loose-laying thickness / compacted thickness) is a construction control parameter, preferably determined by a trial section; without data, machine-paved asphalt concrete takes 1.15~1.35 and hand-laid 1.25~1.50; the wastage rate (= (norm resource consumption - net quantity) / net quantity) is a pricing/stockpiling parameter — for pricing, norm resource consumption already includes paving wastage, so apply the quota item directly on design area x compacted thickness without adding further wastage; only stockpiling/procurement multiplies by the wastage rate (generally 1%~3%).
Applicable Codes
- DB/T 29-74-2018 天津市城市道路工程施工及验收标准
- DB52/T 1599-2021 高性能沥青路面(Superpave)施工技术规范
- DB15/T 1957-2020 公路热拌沥青混合料施工技术规范
- GB 50092-96 沥青路面施工及验收规范
- SJG 181.1-2024 市政工程消耗量标准 Vol. 1 道路工程
Topic Positioning
This card explains how to determine two easily confused parameters of asphalt mixture pavement: the compaction coefficient (loose-laying coefficient) — a construction control parameter determining how thick the paver lays — and the paving wastage rate — a pricing/stockpiling parameter determining material consumption. Applicable to asphalt pavement project execution planning (construction methodology and site organization) and cost compilation.
Core Conclusions
(1) Loose-laying coefficient = loose-laying thickness / compacted thickness; conversion: loose-laying thickness = design compacted thickness x loose-laying coefficient. Determined preferably by a trial section: trial mixing + trial paving in two stages, with the trial paving stage fixing the loose-laying coefficient and rolling regime and establishing the correlation between non-destructive testing and core drilling; during paving, check layer thickness, crown, and cross slope at any time. (2) Reference values without test data (regional standards differ slightly): asphalt concrete mixture machine paving 1.15~1.35, hand laying 1.25~1.50; asphalt macadam mixture machine paving 1.15~1.30, hand laying 1.20~1.45; Superpave pavement preferably 1.15~1.30; without data, initially select 1.18~1.25 and adjust by test. (3) Wastage rate = (norm resource consumption - net quantity) / net quantity, with two calibers: for pricing, norm resource consumption already includes paving, jointing, and touch-up wastage — apply the quota line item directly on design area x compacted thickness, and adding wastage again is not allowed; only for stockpiling/procurement compute net quantity x (1 + wastage rate), with paving wastage of asphalt concrete generally about 1%~3%, governed by the current regional quota norms (prescribed resource consumption standards).
Applicable Boundaries
The loose-laying coefficient reference values come from local standards; on projects the trial-section results and the current local standard govern; commercial (externally purchased) asphalt concrete is priced at the local market price including freight, without additionally charging mixing and transport. GB 50092-96 is dated; its loose-laying coefficient table and average-thickness check formula (D=M/(L x W x T)) should, for highway and urban road projects, follow current codes such as JTG F40-2004 "Technical specification for construction of highway asphalt pavements" and CJJ 1-2008 "Code for construction and quality acceptance of urban road engineering". The loose-laying coefficient is a paving control parameter — do not confuse it with the compaction coefficient of earthwork backfill.
Further Reading
DB/T 29-74-2018 Table 11.5.5 (loose-laying coefficient reference values); DB52/T 1599-2021 Clause 8.6.5; DB15/T 1957-2020 Clause 8.6.14 (initial selection range) and Clause 8.9.5 (trial-section mixing and paving content); GB 50092-96 Clause 7.6.8 (average-thickness check); road base/surface course quantities by design dimensions in square meters, base-course mixed material centrally mixed and transported by compacted volume in cubic meters (SJG 181.1-2024 Clauses 2.2.2~2.2.4, 3.2.1).