Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Measurement unit for earthwork filling items: compacted volume (as-completed backfill / post-rolling volume); excavation, haul, and surplus disposal by natural in-situ (undisturbed) volume; loose volume only for loose-fill items and bulking estimates of waste haul

Filling (backfill/rolling/compaction) is measured in compacted volume: railway subgrade by design fill section as compacted volume (TB/T 10822-2024); building/water backfill by as-completed backfill volume and post-rolling volume (TB/T 10831/10832-2024) — neither loose nor natural volume; excavation, haul, and surplus disposal by pre-excavation natural in-situ (undisturbed) volume. Conversion baseline: loose 1.30 = loose-filled 1.08 = natural in-situ 1.00 = compacted 0.87 — i.e., 1 m3 compacted needs about 1.15 m3 natural in-situ soil or about 1.5 m3 loose volume; so filling items lock the compacted-product basis — quantity by design compacted volume with no bulking factor.

Applicable Codes

  • TB/T 10822-2024 铁路工程预算定额 Vol. 1 路基工程
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
  • TB/T 10832-2024 铁路工程预算定额 Vol. 11 给水排水工程
  • JGJ/T 498-2024 施工现场建筑垃圾减量化技术标准
  • GB/T 50854 房屋建筑与装饰工程工程量计算规范

Topic Positioning

Whether earthwork filling, when budget quota items are applied, is measured in compacted, loose, or natural volume: filling (backfill/rolling/compaction) by compacted volume — railway subgrade by "compacted volume", building backfill by "as-completed volume", water/drainage backfill by "post-rolling volume"; natural in-situ (undisturbed) volume only for excavation, haul, and surplus disposal; loose (bulked) volume only in "loose fill" items and waste-haul/dump estimates. This card consolidates the original measurement rules and volume conversion factors from the three railway volumes.

Core Conclusions

  1. Overall: the same soil mass has four different state volumes; the conversion baseline is loose 1.30 = loose-filled 1.08 = natural in-situ 1.00 = compacted 0.87 (alternative row: loose 1.50 = natural in-situ 1.15 = compacted 1.00), i.e. 1 m3 compacted requires about 1.15 m3 natural in-situ soil and about 1.5 m3 loose volume. If filling items are measured and priced by natural or loose volume, unit prices differ by 15%–50%, so quota measurement locks onto the finished-product (compacted) basis.

  2. Railway subgrade — TB/T 10822-2024 Vol.1 Ch.1 (XI) measurement rules, original: "fill preparation, fill haul, and filling-compaction quantities are measured as compacted volume per the design fill section"; "fill crushing measured as compacted volume"; berm and reserved settlement quantities included in fill; subgrade clearing and the backfill between the rolled base and original ground counted as fill; subgrade watering by design quantity in "t"; loosening, leveling, and compaction of zero fill-cut sections by design area; embankment slope trimming by design slope area; transition-section filling compaction (incl. wrapping volumes) by compacted volume per design section. Table 3 Group A/B fill densities (per compacted m3, t/m3): below subgrade bed (>200 km/h) 2.233; lower bed >200 km/h 2.305, 160<v<=200 2.257; purchased A/B fill by apparent density 2.5 t/m3.

  3. Railway building works — TB/T 10831-2024 Vol.10 notes, original: "Excavation and haul are by pre-excavation natural in-situ (undisturbed) volume. Backfill is by as-completed volume. Volumes in different states convert per Table 4." Table 4 (soil row as above); rock: loose 1.54 = loose-filled 1.31 = natural in-situ 1.00; block stone: loose 1.75 = loose-filled 1.43 = natural in-situ 1.00 = (stacked) 1.67; sand-gravel mix: loose 1.07 = loose-filled 0.94 = natural in-situ 1.00.

  4. Railway water supply and drainage — TB/T 10832-2024 Vol.11 notes, original: "Earth and rock volumes are by natural in-situ (undisturbed) volume; backfill is by post-rolling volume. Surplus soil and stockpiled soil use loose-soil items." Conversion factors per its Table 1.

  5. Surplus soil disposal estimate — JGJ/T 498-2024 Clause 4.0.2: estimated disposal Ve = lambda-c x Vc - lambda-f x Vf, measured in loose volume; Vc = excavation quantity (design dimensions, natural in-situ volume before excavation), Vf = on-site reuse backfill (as-backfilled volume); lambda-c (conversion factor to loose volume for off-site haul) soil 1.30, rock 1.54, sand-gravel 1.07; lambda-f (backfill volume conversion factor) loose-filled soil 1.20, rock 1.18, sand-gravel 1.14; for compacted backfill, interpolated from 1.45-1.58 using compaction factors 0.90-0.98 (loose/compacted ratio 1.50 corresponds to a backfill compaction factor of 0.93). Coefficients reference GB 50854-2013 Table 2.

  6. Practice notes for budget preparation: (1) fill BOQ/quota quantities directly by design compacted section — no bulking/conversion factor; (2) excavation, haul, and disposal of surplus material are measured and priced separately in natural in-situ volume; (3) soil consumption and compaction passes are already built into quota items on the compacted-volume basis (incl. natural-volume conversion and loss) — convert only for purchased soil settled by truck (loose) or for disposal estimates; (4) mind "loose-fill" items (e.g. backfill with no compaction requirement) whose m3 unit is loose volume — read the item name.

Applicable Boundaries

  • Basis applies to the railway budget quota system (TB/T 10822/10831/10832-2024), consistent with the general building/municipal BOQ principle (GB/T 50854, GB/T 50857: excavation and backfill are measured by design dimensions without state conversion). Other sectors/regions (e.g. highway JTG, Beijing DB11/T 2382-2024) may take slightly different conversion factors — follow the applicable volume notes of the project's sector/region.
  • "Compacted" holds only for finished-product items of filling compaction, rolling, and tamping; excavation/haul/disposal items are on a natural in-situ basis; loose volume appears only in loose-fill items, purchased-soil measurement, and surplus-soil disposal estimates.
  • Excludes working-space widths/slope factors, cut-fill balance and allocation, and BOQ coding — see related cards.

Further Reading

  • TB/T 10822-2024 Vol.1 Ch.1 Table 3 and (XI); clearing rules (stripping to 30cm below original ground; stump removal for trunks >=10cm at 1.3m height; waste spreading/rolling by natural in-situ volume).
  • TB/T 10831-2024 Vol.10 notes XI, Tables 4-6 (conversion factors, working space, slope starts) and trench-length rules.
  • TB/T 10832-2024 Vol.11 notes V, Table 1, trench/pit division (<=7m wide, long side >=3x short side as trench), +0.1m per side with shoring.
  • JGJ/T 498-2024 Clause 4.0.2.

Keywords

Cited By