National provisions on reclamation and restoration costs of temporary land (temporary haul roads etc.): reclamation obligation, the land reclamation fee pre-deposit system, and railway estimate listing

Temporary haul roads and transport roads are temporary land and must be reclaimed and restored to their original state on expiry, following the principle of "whoever damages, reclaims" (Land Reclamation Regulations, Article 3); the user shall complete reclamation within one year of the expiry of the temporary land, demolish temporary buildings and structures, reclaim cultivated land as cultivated land and other agricultural land as agricultural land. Reclamation costs are subject to a dedicated-account full pre-deposit system: deposit within one month before the project commences; projects with a production-construction cycle of under three years deposit the full amount in one lump sum, while those of three years or more may deposit in instalments, with the first instalment no less than 20% of the total (Implementation Measures for the Land Reclamation Regulations, Articles 16, 18 and 19). In railway estimates and budgets (TB 10801-2024), the construction, demolition and restoration costs of heavy temporary works such as temporary haul roads for motor transport are included in the heavy temporary works costs, while land-related costs — land rent, crop compensation, relocation compensation, reclamation and the like — are listed under Chapter 1, temporary land use fees and temporary land reclamation (Article 3.8.4, item 4).

Applicable Codes

  • 自然资规〔2021〕2号《自然资源部关于规范临时用地管理的通知》
  • 《中华人民共和国土地管理法》(2019修正)第五十七条
  • 《土地复垦条例》(国务院令第592号)
  • 《土地复垦条例实施办法》(自然资源部令第5号,2019修正)
  • TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects
  • TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works

Topic Positioning

This card answers how the state regulates the reclamation and restoration costs of temporary land such as temporary haul roads. It follows two threads: the legal layer (definition of temporary land, the reclamation obligor, reclamation standards and time limits, and the land reclamation fee pre-deposit system) and the railway cost layer (TB 10801-2024 heavy temporary works costs and the listing of Chapter 1 temporary land fees and temporary land reclamation).

Core Conclusions

1. Temporary haul roads are temporary land and must be reclaimed and restored on expiry. Under Article 1 of the MNR Notice on Regulating Temporary Land Management (Zi Ran Zi Gui [2021] No. 2), temporary land means land temporarily used for construction project execution, geological exploration and the like, on which no permanent buildings or structures are erected and which can be restored after use (restored to its original land class or brought to a usable state through reclamation). Its scope covers land used for "auxiliary works for the project's own use directly serving construction", such as "temporary haul roads and transport roads", material yards, borrow pits and spoil (slag) yards; "land that cannot be restored to its original land class after use, or whose reclamation cannot bring it to a usable state, shall not be used as temporary land". Temporary land is characterised by its temporary nature and restorability.

2. Reclamation obligor: "whoever damages, reclaims". Article 3 of the Land Reclamation Regulations (State Council Decree No. 592): land damaged by production-construction activities shall be reclaimed by the production-construction unit or individual (the land reclamation obligor) in accordance with the principle of "whoever damages, reclaims"; land damaged as a historical legacy and land damaged by natural disasters shall be reclaimed under the organisation of the people's government at or above the county level.

3. Term, reclamation standards and time limits. Article 57 of the Land Administration Law (2019 amendment): the term of temporary land use shall generally not exceed two years; the user shall use the land for the purposes agreed in the contract and shall not erect permanent buildings. Article 2 of Zi Ran Zi Gui [2021] No. 2: for energy, transport, water conservancy and other infrastructure projects with a relatively long construction cycle, the term of temporary land shall not exceed four years, counted from the date of approval. Article 4: the user of temporary land shall complete land reclamation within one year from the date of expiry of the temporary land, and where reclamation is affected by force majeure such as climate or disasters, an appropriate extension may be granted upon approval; after expiry, temporary buildings and structures shall be demolished; where cultivated land is used, it shall be reclaimed as cultivated land, ensuring that the area of cultivated land does not decrease and its quality does not decline; where other agricultural land is used, it shall be restored to agricultural land; where unused land is used, reclamation as cultivated land is encouraged where conditions permit. Beam yards, mixing stations and the like, whose original planting conditions are difficult to restore, shall not occupy cultivated land or permanent basic farmland as temporary land.

4. Core cost institution: the land reclamation fee "pre-deposit". Article 16 of the Implementation Measures for the Land Reclamation Regulations (MNR Decree No. 5, 2019 amendment): the obligor shall open a dedicated land reclamation fee account at a bank agreed with the county-level natural resources department of the place where the damaged land is located, in the amount determined by the land reclamation plan, and deposit the full amount in advance, following the principle of "owned by the land reclamation obligor, supervised by the natural resources department, deposited in a dedicated account and used for dedicated purposes". Article 18: the deposit shall be made within one month before the project commences; where a plan is supplemented, within one month after the plan passes review; where a modified plan renders the deposited funds insufficient, the difference shall be made up within one month after the plan passes review. Article 19: pre-deposit may be made in one lump sum or in instalments — projects with a production-construction cycle of under three years shall deposit the full amount in one lump sum; those of three years or more may deposit in instalments, but the first instalment shall be no less than 20% of the total amount, and the balance shall be deposited in accordance with the deposit plan before the end of production-construction activities, one year ahead of completion.

5. Consequences of non-performance and incentives. Article 18 of the Land Reclamation Regulations: where an obligor fails to reclaim, or fails reclamation acceptance after rectification, it shall pay the land reclamation fee, and the competent land and resources department shall organise reclamation on its behalf; the amount of the reclamation fee shall be determined by comprehensively considering factors such as the land type before damage, the actual damaged area, the degree of damage, the reclamation standard, the intended use after reclamation, and the quantities of works required to complete the reclamation task; the reclamation fee paid shall be used exclusively for land reclamation, and no unit or individual may intercept, misappropriate or divert it. Article 32: where an obligor restores damaged cultivated land, forest land, grazing land and other agricultural land to their original state within the prescribed time limit, the farmland occupation tax already paid shall be refunded.

6. Railway estimate listing (TB 10801-2024). Article 3.8.1: heavy temporary works costs mean the costs incurred by the construction enterprise in constructing and demolishing/restoring the heavy temporary structures required, as determined by the project execution plan (construction methodology and site organisation), for the execution of construction and installation works and for maintaining the normal operation of existing lines. Article 3.8.3: temporary haul roads for motor transport (including temporary bridges, tunnels and culverts) are item 2 of the heavy temporary works items, meaning trunk haul roads for motor transport, longitudinal haul roads along the line, and access roads to key earthworks and rock works sites, bridges, tunnels, station buildings, borrow/spoil yards and other construction points. Article 3.8.4: the content of heavy temporary works costs includes the works costs and maintenance and repair costs of haul roads and the like; among these, "land rent, crop compensation, relocation compensation, reclamation and all other land-related costs incurred in constructing heavy temporary works" shall be listed under Chapter 1, temporary land use fees and temporary land reclamation (Article 3.8.6 makes the same provision for comparable land costs of transition works). Article 3.8.7: heavy temporary works and transition works costs shall be calculated in accordance with TB 10811, the Norms for On-Costs and Expenses of Railway Capital Construction Project Design Estimates (Budgets). Article 2.3.2, compilation depth table: heavy temporary works, transition works and temporary land reclamation shall be compiled on the basis of detailed work items and the scale and quantities determined by the project execution plan (construction methodology and site organisation); preliminary design shall use estimate (budget estimate) quota norms or budget quota norms, and construction drawing design shall use budget quota norms; the commentary notes that this compilation depth requirement was added pursuant to Zi Ran Zi Gui [2021] No. 2.

Applicable Boundaries

  • Objects of application: temporary land such as temporary haul roads, transport roads, borrow pits, spoil (slag) yards and material yards used for construction project execution, and temporary land for geological exploration; land that cannot be restored to its original land class after use, or whose reclamation cannot bring it to a usable state, shall not be used as temporary land.
  • Approval authority (Article 3 of Zi Ran Zi Gui [2021] No. 2): county (city) natural resources departments are responsible for approving temporary land; where cultivated land or permanent basic farmland is involved, approval shall be by the municipal or higher-level natural resources department, and shall not be delegated or entrusted; within urban development boundaries, temporary construction land planning permission and temporary land approval may be applied for together.
  • The cost listing basis is that of the railway sector (TB 10801-2024, TB 10811-2024); the basis for temporary works and reclamation costs in the highway, municipal and other sectors differs and cannot be directly applied.
  • Zi Ran Zi Gui [2021] No. 2 took effect on the date of issuance (4 November 2021) and is valid for five years.
  • Users may not transfer, lease or mortgage temporary land (Article 4 of Zi Ran Zi Gui [2021] No. 2).

Further Reading

  • MNR Notice on Regulating Temporary Land Management (Zi Ran Zi Gui [2021] No. 2): Article 1 (scope of temporary land), Article 2 (siting requirements and term of use), Article 3 (approval), Article 4 (restoration duty), Article 5 (supervision).
  • Land Administration Law of the People's Republic of China (2019 amendment, Presidential Decree No. 32), Article 57 (approval, contract and term of temporary land use).
  • Land Reclamation Regulations (State Council Decree No. 592), Article 3 (whoever damages, reclaims), Article 18 (reclamation on behalf and the reclamation fee), Article 32 (refund of farmland occupation tax).
  • Implementation Measures for the Land Reclamation Regulations (MNR Decree No. 5, 2019 amendment), Article 16 (dedicated account), Article 18 (timing of pre-deposit), Article 19 (one-off/instalment pre-deposit).
  • TB 10801-2024, Measures for Compiling Design Estimates (Budgets) of Railway Capital Construction Projects, Article 2.3.2, Section 3.8 and the commentary; TB 10811-2024, Norms for On-Costs and Expenses of Railway Capital Construction Project Design Estimates (Budgets), Section 2.8 (calculation of heavy temporary works and transition works costs).