Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Railway 2024 quota norms (prescribed resource consumption standards; TB/T 10822-2024): subgrade slope smooth (pre-split) blasting and deep-hole blasting — application of quota items and dual area/volume overlay measurement rules

In the Railway 2024 quota norms, smooth (pre-split) blasting is an independent quota item family LY-58/59/60 (hole diameter 70-120 mm, unit of measurement 100 m2, measured by design slope area) that must be applied separately and 'shall be used in addition to other rock-excavation quota norms'; the main deep-hole blasting LY-46~51 is measured per the natural in-situ (undisturbed) volume inside the design excavation line (100 m3). The two are priced cumulatively, with quantities mutually non-deducting and each listed independently.

Applicable Codes

  • TB/T 10822-2024 铁路工程预算定额 Vol. 1 路基工程(Ch. 1 路基土石方,第二节 石方挖运 LY-46~51、LY-58~60)
  • GB 50862-2013 爆破工程工程量计算规范(Table A.2 预裂爆破 090102、Table A.3 光面爆破 090103)

Topic Positioning

The item setting, quantity splitting, and overlay pricing rules of subgrade slope smooth (pre-split) blasting and main deep-hole blasting in Chapter 1 'subgrade earthworks (earth and rock)', Section 2 'rock excavation and haulage' of TB/T 10822-2024 'Railway Works Budget Quota Manual (China Railway), Volume 1: Subgrade Works' — answering 'does smooth blasting need its own quota item, and how do volume and area split?'.

Core Conclusions

  1. It needs its own quota item. Smooth (pre-split) blasting is an independent family, unit of measurement 100 m2, three items by rock: LY-58 soft rock, LY-59 sub-hard rock, LY-60 hard rock (hole diameter 70-120 mm); work content: hole layout, drilling, charging, hookup, sentry, firing, inspection, and trimming of slope and floor.
  2. Chapter note (5) as written: 'The smooth (pre-split) blasting unit of measurement in the quota norms is computed per design slope area and shall be used in addition to other rock-excavation quota norms. Smooth blasting applies only to non-controlled blasting.' — i.e., an overlay relationship with the main excavation quota norms, neither inclusion nor substitution.
  3. Deep-hole blasting items LY-46~51, unit of measurement 100 m3, two groups by rock x use: spoil/crush group LY-46/47/48 (soft/sub-hard/hard rock) and direct fill group LY-49/50/51. Chapter note (4) as written: 'For deep- and shallow-hole blasting of rock, when used as spoil or requiring crushing before filling, use LY-46, 47, 48, 52, 53, 54 (crushing per the fill-crushing quota items separately); when used directly as cut-to-fill, use LY-49, 50, 51, 55, 56, 57.' For the same rock type, the direct-fill group has a higher base price than the spoil/crush group.
  4. Measurement rules (note 12) as written: 1. 'Excavation and haulage quantities are measured in natural in-situ (undisturbed) volume.' 2. 'Smooth (pre-split) blasting quantities are measured per design slope area.' 4. 'Cut excavation is measured per the design excavation line.'
  5. Quantity splitting: main deep-hole blasting takes the rock volume inside the design excavation line in natural in-situ (undisturbed) volume (m3) via LY-46~51 (rock at the slope **not deducted** — all included in the deep-hole volume); slope smooth (pre-split) blasting takes the design slope area (m2) via LY-58~60 as a separately listed additional control-blasting cost for slope shaping. Two independent BOQ items/quota items, each applied on its own, quantities mutually non-deducting, priced on an overlay basis.
  6. Selection note: smooth blasting applies only to non-controlled blasting — for rock excavation near an existing railway adding a second track, use the controlled-blasting quota items by the A/B/C conditions (line spacing, cut height/thickness, existing slope gradient — see Table 1 of the chapter notes), not smooth (pre-split) blasting.
  7. System difference: the railway quota manuals merge 'smooth' and 'pre-split' into one family 'smooth (pre-split) blasting'; under the GB 50862-2013 'Code for Quantity Take-off (Measurement) of Blasting Works' BOQ system, pre-split blasting (code 090102) may be measured per design area (m2) or total design drilling length (m), and smooth blasting (code 090103) per m2. The two systems differ — railway projects follow the railway quota manuals' basis; do not mix.

Applicable Boundaries

  • Applies to subgrade blasting pricing (including cut-slope shaping) in the 'rock excavation and haulage' section of TB/T 10822-2024 Volume 1.
  • Smooth (pre-split) blasting is per design slope area, not volume; when overlaid with the main excavation volume, neither deducts nor double-counts the other.
  • Not applicable to controlled blasting (near an existing railway adding a second track, meeting the A/B/C conditions) — those use the controlled-blasting quota items.
  • Base prices in the quota norms are base-period prices; at compilation, price adjustment (for fluctuation) is required per the companion compilation measures and published price information (government guidance prices).
  • Under the GB 50862-2013 BOQ system the units of measurement and codes differ — do not mix with the railway quota manuals' basis.

Further Reading

  • TB/T 10822-2024 'Railway Works Budget Quota Manual (China Railway), Volume 1: Subgrade Works', Chapter 1: volume notes, Part 2 'Chapter Notes', Article 1 (4)(5) and (12) measurement rules; Section 2 rock excavation and haulage — item tables LY-46~51 (deep-hole blasting), LY-58~60 (smooth (pre-split) blasting).
  • A/B/C controlled-blasting conditions: chapter-note Table 1 (line spacing, excavation height/thickness, existing slope gradient, rock hardness).
  • GB 50862-2013 'Code for Quantity Take-off (Measurement) of Blasting Works', Table A.2 'pre-split blasting works (code 090102)', Table A.3 'smooth blasting works (code 090103)'.

Keywords