Recognising preliminaries costs of repeated scaffold erection and dismantling caused by the employer (instructions changing construction sequence): lump-sum exceptions, measurement anchors, pricing methods and procedural requisites (GB/T 50500-2024 clauses 3.3.7, 7.3.1, 7.4.4, 8.9.4~8.9.7, 8.11.10; GB/T 50854-2024 Appendix R, code 011601)

Preliminaries are lump-sum and unadjusted in principle, but clause 3.3.7 lists the exception: 'employer-caused extended use, reworking, addition or re-provision of preliminaries increasing their cost adjusts under chapter 8' - scaffolds re-erected after an employer instruction changing the sequence fall squarely under 'reworking' and 're-provision', with no need to prove excess over the bid scheme's assumptions, though a bid-versus-instructed scheme comparison must show the instruction caused it. Increments measure per 7.4.4 on the employer-approved scheme or actual content (extended use of existing preliminaries and management on non-critical paths never measures); material duration changes price per 8.9.4 as 'extended (shortened) duration x mid-term running costs', new plant and temporary works per 8.9.5; the scheme must be confirmed before execution (8.9.6), silence forfeiting (8.9.7). Codes: GB/T 50854-2024 Appendix R preliminaries run 011601 (scaffolds 011601001, unit 'item', no area rules at BOQ level); 011701 is the 2013 code - area / vertical-projection bases now serve only as increment pricing anchors, never to re-measure the whole scaffold list.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.2.1、3.3.7、6.2.13、7.3.1、7.4.3、7.4.4、8.7.6、8.9.4、8.9.5、8.9.6、8.9.7、8.11.9、8.11.10条及App. E.3Table E.3.3
  • GB/T 50854-2024 · Standard for measurement of building construction and fitting out works App. R Table R.1.1(措施项目,code 011601)
  • GB 50854-2013 · Code for Measurement of Quantities of Building and Decoration Works 附录(措施项目code 011701,2024版已调整为011601,旧版引用须核对原文)

Positioning

A specific dispute: the employer (or its engineer) instructs a change of sequence, forcing an erected scaffold to come down and go back up ('reworking', 're-provision'), and the contractor claims preliminaries - adjustable or not, under which clause, how measured and priced, through what procedure, and which cases never charge again. For BOQ pricing (GB/T 50500-2024 with GB/T 50854-2024); complements the cards on the lump-sum principle and scheme-change adjustment by focusing on the recognition elements and anchors, plus the code editions.

Core conclusions

1. Lump sum is the rule; employer-caused re-provision is the statutory exception (3.3.7)

Verbatim: 'The preliminaries scheme in the contractor's bid shall be deemed reasonably practicable... lump-sum, and the contractor bears the risk of adjusting its own scheme. Save variations, unforeseeable provisional-sum works, and employer-caused extended use, reworking, addition or re-provision of preliminaries adjusting under chapter 8, nothing adjusts.' Second paragraph: impracticable or beyond-capacity schemes cost the contractor; variations, unforeseeable works or employer interference materially changing duration, affecting or adding preliminaries, cost the employer. Hence: re-erection hits 'reworking' / 're-provision' expressly - no need to prove excess over bid assumptions - but practice still requires the bid-versus-instructed comparison to show the instruction, not the contractor's own choice, caused it. The contractor's own adjustments (impracticability, incapacity, self-optimisation) are always its own. Material duration change (critical path) is the other employer-borne trigger, distinct from non-critical paths.

2. 'No measurement adjustment' and its five exceptions (7.3.1)

Verbatim: 'Save as agreed and as follows, priced preliminaries shall not be measured or adjusted: 1 work-item-listed preliminaries and contractually measurable items (7.2.1, 7.2.2); 2 statutory safety provisions per contract; 3 variation-caused changes (7.4.4); 4 BOQ-error changes (8.2.2, 8.2.3); 5 unforeseeable provisional-sum works (7.7.2).' And: 'Specialist-subcontract preliminaries inside provisional sums are in the subcontract totals, never re-measured; however many items the bidder supplemented, the preliminaries of the contract total are not re-measured - save preliminaries of provisional-sum works, variations, interference, relic finds and the like done at the employer's request, which measure and adjust.' Point: the entries are variation / BOQ error / unforeseeable works / employer-requested events (including interference). An instruction issued as a variation runs 8.9; mere interference without variation runs 8.11 (point 6). Never mix the two paths: 8.9 adjusts price - cost only; 8.11 claims may add profit, on proof of employer fault.

3. Measurement anchor: increments on approved schemes / actual content (7.4.4)

Verbatim: 'Variation-caused preliminaries changes measure added management, added temporary works and other added preliminaries on the employer-approved scheme or actual content; duration changes compute per 8.9.4. New preliminaries measure by the types, quantities, durations and machine-shifts of the approved scheme. Non-critical-path extensions of existing preliminaries and management are not measured - deemed inside the contract total.' The measurable increment of a re-erected scaffold has four blocks, all against the approved scheme, net only, never re-charging the first erection:

Increment Measurement Pricing
(1) net re-erected quantity area basis per the contractual measurement standard or quota chapter (external / individual scaffolds by the served object's vertical projection; comprehensive by gross floor area; birdcage by laid horizontal projection) contract similar rates or quota build-up
(2) labour, transfer, rework, maintenance, dismantling, warehousing of the repeat approved scheme and actual content as (1) or quota
(3) new (absent) temporary works - protection canopies, ramps, loading platforms type, quantity, duration agreed reasonable market prices (8.9.5 item 2)
(4) new (absent) plant model, count, machine-shifts dayworks rates; absent dayworks, clause 8.6.3 (8.9.5 item 1)

The area basis clarified: GB/T 50854-2024 Appendix R Table R.1.1 lists scaffolds (011601) 'per item' - no area rules at BOQ level; area / projection bases are not BOQ measurement but pricing anchors for the increment (the actually re-erected net area), never grounds to re-measure the whole scaffold list. Legacy 2013 contracts on code 011701 still measure by area.

4. Pricing formulas (8.9.4, 8.9.5)

8.9.4: material duration extension or shortening prices as preliminaries adjustment = extended (shortened) duration x mid-term running costs, duration per 7.4.4 and running costs per the 6.2.13 breakdown (Table E.3.3). Material means critical path; non-critical extensions are deemed inside the total. 8.9.5: added preliminaries outside 8.9.1~8.9.4: (1) added plant by actual model, count and shifts at dayworks rates, else 8.6.3; (2) added temporary works by type, quantity and duration at agreed reasonable market prices; determined on the confirmed scheme. Base data: 6.2.13's breakdown (initial / running / dismantling) serves chapters 8 and 9. Pricing form: 3.2.1 - preliminaries preferably total-price 'per item'.

5. Procedure and forfeiture (8.9.6, 8.9.7)

8.9.6: 'the disadvantaged party shall submit the intended scheme before execution, detailing the changes; after confirmation, adjust per 8.9.4 and 8.9.5. The contractor submits in writing the scheme, the extension sought and the preliminaries claimed; the parties compute and adjust on the employer-approved scheme.' 8.9.7: 'failure to propose within the agreed time deems no change or waiver; failure to confirm or object within the time deems approval; a contractor failing to submit the scheme or the claim in time waives; an employer failing to review in writing in time deems to accept the scheme.' The recognition chain: (1) evidence of the instruction / fault event -> (2) pre-execution scheme with item-by-item comparison (types, quantities, durations, models, shifts) -> (3) confirmation or deemed approval -> (4) measure the quantity gap on the approved scheme -> (5) price on similar / dayworks / market rates or the 8.9.4 formula. Missing any link may fall into 'no change presumed'.

6. The parallel claim channel with profit (8.11.10)

Employer-fault events allow economic loss, cost, extension and profit, item 5 being 'extra site restrictions, late approvals, disturbed construction order' and item 6 'employer-caused delay, suspension, late resumption'. Losses listed: idle crews, unusable materials, idle plant, others. Government-caused losses extend duration only, each party bearing its own.

7. Two exclusions

  • Price moves: 8.7.6 - preliminaries 'shall not adjust for price changes save as agreed'; scaffold hire or material rises never ground increases.
  • Specialist-subcontract preliminaries: 7.3.1 - inside the subcontract totals, never re-measured.

8. Codes and editions (Appendix R)

GB/T 50854-2024 Appendix R Table R.1.1: preliminaries 011601; scaffolds 011601001 'per item', work content covering erection, ramps, platforms, safety nets, boards, transfer, rework, maintenance, dismantling, stacking and return; scope: 'all scaffolds erected during construction per the codes and work needs'. So the BOQ level has no area rules - 'per item' lump sum; the content covering all erection and dismantling grounds both 'first erection not recharged' and 're-erection net-only'. 011701 (2013: comprehensive by gross floor area, external by vertical projection) is superseded by 011601 - never mix codes across editions.

Applicable boundaries

  • This card adjusts preliminaries; work items follow 8.9.1~8.9.3 (like / similar / new rates) - no substitution.
  • Non-critical-path extensions of existing preliminaries and management 'may go unmeasured' (7.4.4, 8.9.4) - deemed inside the total, employer fault notwithstanding; only critical-path duration changes open the door.
  • The contractor's own impracticability, incapacity or optimisation is always its own (3.3.7).
  • Statutory safety provisions follow the contract (7.3.1 item 2), outside variation / claim pricing.
  • 8.9.7's forfeiture and deemed approval presuppose agreed times - none agreed, no deemed effects.
  • Editions differ in codes and units ('item' versus area): follow the contractual standard; area bases across editions serve only as increment anchors.
  • Under lump-sum contracts, drawing-versus-list differences are BOQ errors that do not adjust (7.4.3); preliminaries still run 3.3.7 / 7.3.1 / 8.9.

Further reading

  • GB/T 50500-2024 clauses 3.2.1, 3.3.7, 6.2.13 with Appendix E.3 Table E.3.3, 7.3.1, 7.4.3, 7.4.4, 8.7.6, 8.9.4, 8.9.5, 8.9.6, 8.9.7, 8.11.9~8.11.10.
  • GB/T 50854-2024 Appendix R Table R.1.1 (011601) and scope note; local list rules and quota scaffold chapters (projection / gross-floor / birdcage bases) with the contractual breakdown and progress-measurement rules.

Keywords

  • 措施项目费包干
  • 发包人原因引起措施费调整
  • 脚手架重复搭拆
  • 拆改 重复提供
  • 措施项目费用分拆表
  • 011601
  • 011701
  • 工程变更措施项目计量