Whether preliminaries adjust after a construction plan (project execution plan) changes: the lump-sum boundary, adjustable situations, measurement and pricing methods, and supporting records
After a plan (project execution plan) change, preliminaries follow lump-sum-no-adjustment as the principle (GB/T 50500-2024 Article 3.3.7): the contractor's tendered measures plan is deemed reasonable and feasible, preliminaries are priced lump-sum, and the contractor bears the risk of increases caused by his own plan changes; only three exceptions - variations, works within provisional sums not fully foreseen or detailed, and employer-caused extended use, dismantling, addition or duplicated provision of measures - adjust under Chapter 8; costs of changing an unworkable plan or one beyond the contractor's capability are his own. Time effects adjust only for substantive critical-path extension or reduction (8.9.4), non-critical items unmeasured; cost fluctuation is no ground (8.7.6), while laws and policy changes are a separate channel (8.8.1); measurement adjustment is a closed list under 7.3.1; varying preliminaries requires the plan approved and confirmed before execution, silence forfeiting the right (8.9.6, 8.9.7).
Applicable Codes
- GB/T 50500-2024 第3.3.7、3.2.5、6.2.13、7.3.1、7.4.4、8.7.6、8.8.1、8.9.4、8.9.5、8.9.6、8.9.7条
- T/ZBD 100.5-2023 第2.1.8、3.1.6、3.1.8条
- T/SDJZXH 004.1-2022 第10.6.3条
- TB 10801-2024 第3.11.11条(铁路安全生产费)
Scope of the question
Whether preliminaries adjust after the construction plan (project execution plan) changes: the lump-sum boundary, the triggers (major plan change, programme change, policy change), measurement and pricing, procedure and time limits, and the supporting records to keep. For interim settlement, variation claims and settlement review of BOQ-priced projects.
Core conclusions
1. Principle: preliminaries lump-sum, the contractor bearing his own plan-change risk (GB/T 50500-2024 Article 3.3.7)
The measures plan tendered by the contractor is deemed reasonable, feasible and matching actual construction; its preliminaries are priced lump-sum and the contractor bears the risk of increases from adjusting the plan himself. Save for variations, provisional-sum works not fully foreseen or detailed, and employer-caused extended use, dismantling, addition or duplicated provision of measures increasing preliminaries - adjusted under Chapter 8 - nothing else adjusts. Where the tendered plan is unworkable or beyond the contractor's capability and must be changed, the increase is his own. Where variations, provisional-sum surprises or employer-caused interference substantially change the programme and affect or add measures, the increase is borne by the employer. That is: increases from the contractor's own optimisation are his risk, unadjusted; only plan changes caused by variations or the employer (and approved) can increase.
2. Triggers
- Major plan (execution plan) change - adjustable only where caused by a variation or the employer. Variations interface through changes of sequence and timing, conditions, specification, position and dimensions; the contractor's own changes do not adjust.
- Programme change (8.9.4): where a variation or employer-fault event substantively extends or shortens the contract time, the parties compute the preliminaries adjustment = extension (shortening) x mid-term running costs of preliminaries; running costs follow the preliminaries breakdown per Article 6.2.13 across all affected items. Substantive change means on the critical path; delayed use of existing measures and added management staff off the critical path are deemed included in the lump-sum.
- Policy / legal change (8.8.1): laws and policy changes after the base date (added, amended, repealed, reinterpreted) adjust price and / or time per the contract and the rules published by the authorities. Limit: 8.7.6 lists preliminaries among fees not adjusted for cost fluctuation - fluctuation alone never adjusts preliminaries; legal / policy change is the separate channel.
- Closed-list measurement exceptions (7.3.1): save as agreed, priced-BOQ preliminaries are not re-measured, except: 1 measures itemised under work-item BOQ entries and contractually measurable; 2 statutory safety provisions per contract; 3 variation-induced changes; 4 BOQ-defect-induced changes; 5 provisional-sum surprises. Nominated-subcontract preliminaries are inside the subcontract lump sum, not re-measured; measures executed for provisional sums, variations, interference or antiquities are measured and adjusted. Special: statutory safety provisions are non-competitive (3.2.5), priced per national and provincial / industry rules; the railway equivalent is the statutory work safety levy.
3. Measurement and pricing
- Variation-induced measure changes (7.4.4): per the plan the contractor drew up for the variation and the employer approved, or actual content - added management staff, added temporary facilities and other added measures; new measures measured by type, actual quantity and duration of the new temporary facilities and by model, count and machine-shifts of new plant.
- Added measures (8.9.5): plant not on site, needed for the variation, is measured by model, count and machine-shifts actually incurred, priced at the dayworks rates in the contract BOQ, else per 8.6.3; temporary facilities not on site are measured by type, quantity and duration, priced at reasonable market rates agreed; determinable from the variation plan confirmed by both parties.
- Preliminaries breakdown (6.2.13): tenderers submit per Appendix E.3 Table E.3.3 listing each item's initial set-up, mid-term running and final removal costs, usable for Chapter 8 claims and Chapter 9 progress payments.
- Review basis (T/ZBD 100.5-2023 Article 3.1.6): preliminaries adjust per the contract's items and methods; absent or unclear terms: 1 work-related measures (formwork, scaffolding) follow the related work-item quantities at agreed all-in unit rates; 2 competitive stand-alone measures (slope protection, dewatering, retention, temporary roads, hoardings) per contract or original tender; 3 project-wide rate- or plan-based measures (mandatory HSE provisions, vertical transport, above-height increase) per state rules and the tendered base and rates or build-up.
4. Procedure and time limits (8.9.6, 8.9.7)
8.9.6: where a variation substantively changes scope, time, quality or specification and alters measures, the disadvantaged party seeking adjustment submits the intended plan for review before execution, detailing changes against the original; once confirmed and executed, 8.9.4 and 8.9.5 apply. The contractor submits the variation plan and its time and cost requests in writing; the parties compute and adjust per the employer-approved plan. 8.9.7: no timely request deems no change to preliminaries or forfeiture of the right; no timely confirmation or comment deems acceptance of the requested adjustment ... failure to submit the plan or cost request in time deems no change or forfeiture; failure of the employer to review in time or reply in writing deems approval of the submitted plan.
5. Supporting records (T/ZBD 100.5-2023 Articles 2.1.8, 3.1.8)
- Variations (instructions): all variation sheets, ledgers, price filings, pre-change drawings, completion confirmations.
- Claims: claim letters, reports and cost computations, event records, drawings and confirmations.
- Price-quality approvals and schedules; free-issue material handover and returns; paid-on-behalf proofs; advance, progress and interim settlement files and schedules.
- Execution plans and method statements tied to measure or price confirmation, adjustments, variation and claim disputes.
- Programme and progress records: tender baseline, as-executed programme, start / completion / suspension / resumption reports.
- Minutes, works instructions, completion records (as-built drawings, acceptance certificates, material test reports, commissioning plans and records).
- Site instruction procedure (T/SDJZXH 004.1-2022 Article 10.6.3): assess reasonableness and responsibility - agree the treatment - survey and record the original state before execution - measure and record quantities as incurred with imagery - attend acceptance, compute the final cost, obtain the chief supervising engineer's sign-off and written employer approval.
Applicability limits
Applies to general procurement under BOQ pricing; GB/T 50500-2024 is recommendatory and express contract terms (especially lump-sum preliminaries clauses) prevail - Articles 3.3.7, 6.2.3 and 7.3.1 all open with save as otherwise agreed. Increases from the contractor's own optimisation, unworkable plans or capability shortfalls are always his. Cost fluctuation alone never adjusts preliminaries (8.7.6); legal / policy change is the separate channel (8.8.1). Statutory safety provisions are non-competitive and unaffected by other variation rules. Railway and other industry works follow industry rules (railway statutory work safety levy: TB 10801-2024 Article 3.11.11). This card is a rules guide; the tender documents, contract and standard text govern.
Further reading
GB/T 50500-2024: Articles 3.3.7 (lump-sum and plan-change risk), 3.2.5 (non-competitive safety provisions), 6.2.13 (breakdown), 7.3.1 (closed measurement exceptions), 7.4.4 (variation-induced measurement), 8.7.6 (feeds not adjusted for fluctuation), 8.8.1 (laws and policy), 8.9.4 (programme formula), 8.9.5 (added measures), 8.9.6-8.9.7 (pre-approval procedure and deemed outcomes). Review bases: T/ZBD 100.5-2023 Articles 2.1.8 (supporting records), 3.1.6 (adjustment methods), 3.1.8 (variation basis and pricing); site instructions: T/SDJZXH 004.1-2022 Article 10.6.3; railway safety levy: TB 10801-2024 Article 3.11.11.
Keywords
- 措施项目费调整
- 施工方案变更
- 施工组织设计变更
- 措施费包干
- 措施项目费用分拆表
- 工程变更措施费
- statutory work safety levy (earmarked funds)
- 法规政策性变化调整