Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Distinguishing and applying tile (block) finishes vs stone finishes: separate BOQ items and three quota criteria (material -> size -> workmanship)

"Block finish" carries two senses — a collective chapter name (all slab finishes including stone) and a material-specific sense (non-stone tiles); which sub-item applies is decided by the face material, not the table name: those consuming natural-stone facing panels/marble apply stone sub-items; those consuming floor tiles, glazed tiles and other ceramics apply block sub-items; in GB/T 50854-2024, stone floors / rubble-stone floors / tile floors (code 011102) and stone wall-columns / rubble / tile wall-columns (code 011203) are separate BOQ items priced under their own quotas; the railway caliber expressly runs vitrified tiles under ceramic-tile sub-items and stone within 100x100 under accent sub-items.

Applicable Codes

  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准(App. L Table L.2.1、App. M Table M.3.1)
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程(Ch. 2 装饰装修工程)
  • DB11/T 2382-2024 建设工程施工消耗量标准(App. A A.11.2 块料面层)

Topic Positioning

The criteria for distinguishing "block (tile) finishes" from "stone finishes" in BOQs and budget quotas, and the basis for pricing by applying quota line items — for BOQ listing, quota line item selection and conversion in floor and wall/column decoration (building works BOQ per GB/T 50854-2024; pricing by applying quota line items illustrated with railway building works TB/T 10831-2024 and Beijing DB11/T 2382-2024).

Core Conclusions

1. The two senses of "block finish"

  1. Collective sense: used as a table or chapter name, it is a collective term — stone, ceramic tiles and other slab finishes all fall under it — GB/T 50854-2024 Table L.2.1 is titled "stone and block finishes" (code 011102), with stone and block line items set out side by side.
  2. Specific sense: when set side by side with "stone", "block" means non-stone blocks specifically (ceramic floor tiles, glazed tiles, vitrified tiles, etc.). -> Which quota line item applies depends on the "finish material type", not on the table name.

2. BOQ level: stone and block are separate BOQ items in themselves GB/T 50854-2024:

  • Floors (Table L.2.1, 011102): 011102001 stone floor, 011102002 rubble-stone floor, 011102003 block floor;
  • Wall/column faces (Table M.3.1, 011203): 011203001 stone wall/column, 011203002 rubble-stone wall/column, 011203003 block wall/column. Each is listed separately, and at the budget stage each is priced under its corresponding quota line item.

3. Quota level: three criteria (material -> size -> workmanship/position) (1) Material type (primary): check the quota line item's main-material consumption — items consuming natural stone facing panels / marble slabs / shaped slabs take stone line items; items consuming floor tiles, glazed tiles and other ceramic products take block line items. Examples (DB11/T 2382-2024 Table A.11.2): A-11-45 stone floor (panel area within 0.64 m2) consumes "natural stone facing panel 800x800"; A-11-48 stone marquetry consumes "shaped marble slabs"; A-11-54 block marquetry consumes "floor tiles". Railway TB/T 10831-2024 puts it more plainly: "stone finishes inlaid within 100x100 take the accent line items of this node" and "vitrified tiles take the corresponding ceramic tile line items" (however stone-like vitrified tiles may look, they must take ceramic/block line items). (2) Size tier: tier by the actual area of the designed panel — stone at 0.36/0.64/1.0 m2 per panel (railway FY-1218, FY-1219 granite finishes); block tiers are finer-grained and include small sizes (railway FY-1214-1217 ceramic floor tiles <=0.1/<=0.36/<=0.64/>0.64 m2). (3) Workmanship and position: marquetry, rubble mosaic, border strips (banding) and accents are dedicated line items (railway FY-1220-1223); wall faces are split by fixing method into mortar bedding / hang-and-bed / dry hanging, with dry hanging further split into hook type and back-bolt type (railway FY-1384-1391 granite wall faces). Metal furring is not included in the line items for block finishes, facing finishes or curtain wall works and must be calculated separately.

4. Companion conversions and measurement points (based on the volume notes of Chapter 2, Vol. 10, railway TB/T 10831-2024)

  • Stone floors needing division joints and colour zoning: labour x 1.10; curved and other irregular floor inlays: labour x 1.15; curved skirtings and stair-flight skirtings: labour and machinery x 1.15;
  • Stair decoration quota covers treads, landings and stair skirtings; for curved stair finishes: labour x 1.25;
  • Floor cushion courses with underfloor heating: apply the corresponding item by material, with labour x 1.30 and materials x 0.95;
  • Steps, ramps and aprons: the quota covers the finish and bonding course but not the cushion; where the step platform (outer wall face to the outer edge of the top riser) is within 2.50 m, the step line item applies; beyond 2.50 m, the corresponding floor line item applies;
  • The cement-and-stone-chip mix for terrazzo floors may be adjusted where it differs from the quota; terrazzo floors include acid washing and waxing, and where other finishes require acid washing and waxing, the corresponding dedicated line item applies;
  • Wood flooring is based on finished tongued-and-grooved boards; for square-edge installation: labour x 0.85; wood flooring infill materials take the corresponding "floor insulation, heat insulation and sound insulation" line items;
  • Measurement basis: stone marquetry is measured by the maximum bounding rectangular area; for floors with marquetry, the paved area is taken as the designed dimension less the maximum bounding rectangle of the marquetry; accents are counted by number and are not deducted from the paved floor area.

Applicable Boundaries

  • The "material -> size -> workmanship" chain of criteria is common across systems; the specific conversion coefficients reflect railway TB/T 10831-2024; building works and other provinces follow the volume notes of their own current quota or consumption standards, and systems must not be mixed.
  • BOQ item setup and coding are per GB/T 50854-2024; local and industry standards may refine the item breakdown differently — check the item descriptions and work content of the applicable standard before applying it.
  • Distinction and application do not depend on specific amounts; in pricing, labour, material and machinery unit rates are calculated separately at compilation-period prices.

Further Reading

  • GB/T 50854-2024 Standard for Measurement of Building and Decoration Works, Appendix L Table L.2.1 (stone and block finishes, code 011102), Appendix M Table M.3.1 (wall and column block finishes, code 011203);
  • TB/T 10831-2024 Railway Works Budget Quota Manual, Vol. 10: Building Works, Chapter 2 Decoration Works — volume notes and Section 1 Floor Works (line items FY-1214-1241), Section 2 Wall and Column Works: stone wall line items (FY-1384-1391);
  • DB11/T 2382-2024 Consumption Standard for Construction Works, Appendix A A.11.2 block finishes (A-11-45 stone floor, A-11-48 stone marquetry, A-11-54 block marquetry, etc.).

Keywords