Railway 2024 quota: classification and application rules of cast-in-place concrete foundation items (TB/T 10831-2024 Volume 10 housing works, FY-458~470)
TB/T 10831-2024 "Railway works budget quota, Volume 10: housing works", Chapter 1 Section 5 "cast-in-place concrete members (1) foundations" sets 13 items FY-458~FY-470 (unit 10 m3): strip foundations are split by rubble/plain/reinforced concrete, the reinforced ones into ribbed and flat types with the boundary "rib-height:rib-width within 4:1 counts as ribbed; beyond 4:1 the base slab is flat-type and the portion above the slab counts as wall"; isolated foundations split three ways by rubble/plain/reinforced; a cup foundation counts as a high-cup foundation when the cup opening height exceeds the opening length; rafts split into without-beam / with-beam, "with-beam" meaning beams cast integrally with the base slab — the beam volume merges into the foundation and is computed as solid volume, with no further beam item; pile caps split into strip / isolated. Structure foundations use the corresponding building-foundation items; equipment foundations, except block type, are computed by the corresponding foundation, column, beam, wall and slab items, deducting reserved openings.
Applicable Codes
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
Topic Positioning
Item numbers, base-period prices, and classification/application rules of cast-in-place concrete foundations (strip / isolated / cup / high-cup / raft / pile cap) in the railway 2024 quota system, per "Railway works budget quota, Volume 10: housing works" TB/T 10831-2024, Chapter 1 civil works, Section 5 concrete and reinforced-concrete works, "1. cast-in-place concrete members (1) foundations". For pricing cast-in-place foundations of railway buildings (station buildings etc.): how rafts, isolated and strip foundations are classified, whether the beams of a with-beam raft merge into the foundation, and how to apply the items.
Core Conclusions
(1) Items and base-period prices (unit 10 m3; work content uniformly: formwork making, erecting, cleaning, release-agent application, stripping, tidying, stacking; concrete placing, compaction, curing):
- FY-458 strip foundation, rubble concrete, 1467.28 yuan; FY-459 strip foundation, plain concrete, 1616.58 yuan; FY-460 strip foundation, reinforced concrete, ribbed, 1340.35 yuan; FY-461 strip foundation, reinforced concrete, flat, 803.46 yuan;
- FY-462 isolated foundation, rubble concrete, 1414.39 yuan; FY-463 isolated foundation, plain concrete, 1390.46 yuan; FY-464 isolated foundation, reinforced concrete, 1347.02 yuan;
- FY-465 cup foundation, 1286.39 yuan; FY-466 high-cup foundation, 1727.35 yuan;
- FY-467 raft foundation, without beams, 449.07 yuan; FY-468 raft foundation, with beams, 979.04 yuan;
- FY-469 pile-cap foundation, strip, 2185.65 yuan; FY-470 pile-cap foundation, isolated, 1947.96 yuan.
(2) Classification and application rules (volume notes "10. Quantity calculation rules" item 3):
- Strip foundation (the commonly so-called strip footing): where the rib-height:rib-width ratio is within 4:1, compute as ribbed strip foundation (FY-460); beyond 4:1, the base slab computes as flat strip foundation (FY-461) and the portion above the slab computes as wall.
- Where the cup opening height exceeds the cup opening length, apply the high-cup foundation quota (FY-466); cup and high-cup foundations compute by solid volume.
- For equipment foundations other than block type, compute separately by the corresponding foundation, column, beam, wall and slab items; deduct the volume of reserved openings of equipment foundations.
- Foundations of structures use the corresponding building-foundation items.
(3) Beams of a with-beam raft merge into the foundation: yes. The quota splits rafts overall into "without beams" (FY-467) and "with beams" (FY-468); "with beams" is a raft whose beams are cast integrally with the base slab — the beam body is applied together with the slab as solid volume under FY-468, and no separate foundation-beam or rectangular-beam item is applied. If the beam were meant to be computed separately, the quota would not have a distinct "with-beam" step.
(4) General quantity rules for cast-in-place members (volume notes item 10): quantities of cast-in-place concrete members do not deduct volumes occupied by reinforcement, iron fitments and bolts; cast-in-place walls and slabs do not deduct concrete volumes of holes up to 0.30 m2. In addition, for concrete trenches, wells and basins: the base slab uses the corresponding raft-foundation items, the sidewalls the wall items, and the cover slabs the slab items (i.e. trench/well/basin base slabs are priced as rafts).
(5) Related volume rules (same item, for companion application): beam-slab column height runs from the top of the column base (or floor slab) to the top of the floor slab above; flat-slab column height to the underside of the drop panel; constructional columns run full height with the parts bonded into brick walls merged in; corbels attached to columns merge into the column volume. Where a beam connects to a column the beam length runs to the column face; secondary beams run to the primary-beam face; beam ends and pads built into block walls merge into the beam volume. Beam-slab is the sum of beam and slab volumes; flat-slab the sum of slab and drop panel; plain slab the solid slab volume; cast-in-place canopies and gutters take the external wall as boundary against slabs and the beam's outer edge line against beams. Monolithic stairs compute by horizontal projection, without deducting stairwells narrower than 0.50 m and without adding parts built into walls.
Applicable Boundaries
- This card applies only to cast-in-place concrete foundation pricing in railway housing works (Volume 10); the foundation/cap item numbers and rules of railway bridges (Volume 2 TB/T 10823-2024), tunnels (Volume 3 TB/T 10824-2024), subgrade (Volume 1) etc. differ, and FY-458~470 must not be used there.
- The listed base prices are 2024 quota base-period prices; actual pricing must adjust per railway price-difference regulations.
- "With-beam raft: beams merge into the foundation" refers to the housing volume's overall raft-item arrangement; equipment foundations and other types are still computed separately by foundation, column, beam, wall and slab items — that clause does not apply.
- The 4:1 rib-height:rib-width boundary only distinguishes ribbed from flat strip foundations; beyond 4:1 the portion above the slab switches to wall items — mind the interface with wall quantity rules.
- This card interprets quota clauses and contains no quantity or price data of any specific project.
Further Reading
- "Railway works budget quota, Volume 10: housing works" TB/T 10831-2024, Chapter 1 civil works, Section 5 concrete and reinforced-concrete works, "1. cast-in-place concrete members (1) foundations", items FY-458~FY-470.
- Same volume, notes "10. Quantity calculation rules" items (1)-(8) (original cast-in-place member volume rules).
- This card's evidence is from desk-retrieved quota text, with no government website URL; for verification see the official publication TB/T 10831-2024 (China Railway Publishing House).