Distinguishing the birdcage scaffold (a work platform, by m2) from full-space steel-tube falsework (formwork support of cast-in-place beams, by m3): purpose, unit, quota volume, and non-interchangeability
The birdcage scaffold and full falsework are two different objects: the birdcage scaffold is a work platform for masonry, finishing and ceiling decoration, measured by net room area in m2 (railway FY-440 basic layer for clear heights of 3.6-5.2m, FY-441 one added layer per extra 1.2m, both per 100m2), belonging to building scaffold works; full steel-tube falsework supports the formwork of cast-in-place beams, slabs and bent caps, measured by space volume in m3 (railway QY-970 erection and removal per 100m3 of space; municipal SJG 181.2-2024 likewise m3 of space), belonging to bridge temporary structures. Different purpose and unit - never interchangeable; the building volume's separate FY-442 item (100m3) for true full-space steel falsework shows that only the platform-type birdcage scaffold bills by m2; bridge falsework items exclude soffit formwork and ground improvement.
Applicable Codes
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程 Ch. 1 第四节 脚手架工程 二、单项脚手架(二)满堂脚手架 FY-440~FY-442
- TB/T 10823-2024 铁路工程预算定额 Vol. 2 桥涵工程 Ch. 5 第四节 二(二)支架安拆 QY-970
- SJG 181.2-2024 市政工程消耗量标准 Vol. 2 桥涵工程 8.2.2 措施项目
- 湖南省2025版市政工程消耗量标准 桥涵工程 支架章说明
Positioning
'Full-area' framing means two things in cost terms: the building birdcage scaffold (work platform) and the full-space steel-tube falsework of cast-in-place bridge beams (formwork support). This card gives their purposes, units, quota volumes and item differences, with the non-interchangeability test - one of the commonest pricing errors.
Core conclusions
1. The essential differences
| Item | Birdcage scaffold | Full falsework (full-space steel-tube falsework) |
|---|---|---|
| Purpose | Platform for masonry, wall / ceiling finishing | Formwork support of cast-in-place beams, slabs, bent caps |
| Unit | Net room area, m2 (basic + added layers) | Space volume, m3 |
| Quota home | Building works - scaffolds (preliminaries) | Bridge works - temporary structures / falsework (preliminaries) |
| Typical items | Railway TB/T 10831-2024 Vol. 10 FY-440, FY-441 (100m2) | Railway TB/T 10823-2024 Vol. 2 QY-970 (100m3 space); municipal SJG 181.2-2024 bridge falsework items |
Conclusion: different purposes (people standing versus carrying formwork and concrete), different physical quantities (area versus volume), different volumes - never interchangeable, and never double-charged on the same element.
2. The birdcage side (building, by area)
TB/T 10831-2024 Volume 10, chapter 1 section 4, scaffold works, individually priced scaffolds (2) birdcage scaffold; work content: '1. birdcage scaffold - erection and removal, safety nets, re-decking, and material stacking after removal. 2. full-space steel-tube falsework - placing pad timbers, erecting and removing the falsework.' Items:
- FY-440 birdcage scaffold, basic layer, clear height over 3.6m up to 5.2m, per 100m2;
- FY-441 birdcage scaffold, one added layer per extra 1.2m, per 100m2;
- FY-442 full-space steel-tube falsework, per 100m3 - note the volume's separate m3 item for true full-space falsework beside the m2 scaffold items: only the platform-type birdcage scaffold bills by area. Layer conversion (added layers = (clear height - 5.2) / 1.2, remainder rounding) sits in the related card.
3. The falsework side (bridge, by space volume)
TB/T 10823-2024 Volume 2, chapter 5 section 4 steel works, temporary structures and preloading, falsework erection (steel columns and distribution beams): QY-970 full-space falsework erection and removal, per 100m3 of space, QY-971 auxiliary steel falsework (10t). Municipal SJG 181.2-2024 clause 8.2.2: 'bridge full-space steel and assembled steel falsework measured by space volume in cubic metres', over-water falsework height from the working-platform top.
4. Two adjacent traps
- Soffit formwork is not in the falsework item - local standards state 'arch centring and falsework exclude soffit formwork and ground improvement'; formwork by contact area, falsework by space volume - listed apart, never merged for both being 'support'.
- Erection-removal and use are separate - municipal items cover erect / dismantle / haul only; use is charged as hire per tonne-month (50kg/m3 for full-space without a scheme); the m2 birdcage scaffold is a one-time area charge with no hire concept.
Applicable boundaries
- Judge by purpose and load: carrying formwork and concrete (cast beams, slabs, bent caps) - falsework (m3); standing work (masonry, finishing, ceilings) - scaffold (m2).
- The mutual exclusion of birdcage and wall-finishing scaffolds above 3.6m is a building rule - it never licenses scaffold items inside bridge works.
- Within building works the birdcage scaffold never bills m3 (save the volume's FY-442 full-space falsework); within bridge works the cast-beam falsework never bills net room m2.
- Comprehensive and individually priced scaffolds are mutually exclusive - no double charge; where formwork is already inside an item per the quota notes, no separate formwork / support item.
Further reading
- TB/T 10831-2024 Volume 10 chapter 1 section 4 (FY-440~FY-442, work content verbatim).
- TB/T 10823-2024 Volume 2 chapter 5 section 4 (QY-970, QY-971); volume note 14 (quantity rules).
- SJG 181.2-2024 Volume 2 clause 8.2.2; Hunan 2025 municipal standard, falsework chapter notes 2-4.
Keywords
- birdcage (full-area) scaffold
- 满堂支架
- 模板支撑
- unit of measurement
- FY-440
- FY-442
- QY-970
- 脚手架与支架区别