Data-taking rules of earthwork and rockwork budget quotas: classifying trenches and pits against general earthwork, classifying dry and wet soil, muck and frozen soil, items already comprehensively included in the quota and not adjustable, determination and successive-multiplication rules for efficiency-reduction conversion coefficients (wet soil, excavation within shoring, excavation between piles, local deepening, deep excavation, vertical soil transport, dynamically compacted ground, etc.), uphill-haul efficiency reduction and allowable over-excavation, and dewatering and shoring to be calculated separately
Earthwork quota data-taking starts with three preliminary steps: (1) classify trench or pit (base width up to 7 m and base length over 3 times the base width, or base length up to 3 times the base width and base area up to 150 m2 - beyond these limits, and not being site levelling, it is general earthwork); (2) split dry and wet soil at the normal groundwater level given in the geological survey data - where dewatering is adopted, the post-dewatering level is the normal water level and dewatering costs are calculated separately; (3) first remove items already comprehensively included and not adjustable (machine excavation already includes manual cleaning of residual layers up to 0.30 m thick on base and slopes, efficiency reduction for loaded uphill hauls at gradients up to 15%, and pipe laying already includes ordinary trench-side shoring). Efficiency reductions then follow the quota coefficients: wet soil by hand labour x1.18; wet soil by machine labour and machines x1.15; hand-dug trenches and pits within shoring x1.43 on labour; soil between piles x1.25 on labour under hand quotas (x1.10 on labour and machines under machine quotas); locally deepened trenches and pits x1.25 on labour and machines; vertical soil transport by hand x1.50; excavation on dynamically compacted ground x1.15; hand excavation beyond 6 m x1.15 per additional metre; where two coefficients coexist they are multiplied successively. Coefficients are taken from the notes of the quota volume actually applied and must not be mixed across volumes.
Applicable Codes
- TB/T 10831-2024 · Budget Quota of Railway Engineering (Volume 10: Housing Works) 册说明二~六
- TB/T 10832-2024 · Railway works budget quota manual: Water Supply and Drainage Works, Vol. 11 (2024 series) 册说明Ch. 2
- TB/T 10823-2024 · Budget Quota of Railway Engineering (Volume 2: Bridge and Culvert Works)
- SJG 181.4-2024 · Consumption Standard for Municipal Works (Volume 4: Water Supply and Drainage Pipeline Networks) (Shenzhen) 第1.1.4条
- 湖南2025版市政工程消耗量标准 册说明与第一章土石方工程说明
- 陕西省新编消耗量定额(2024年征求意见稿)土石方工程说明
Subject positioning
The three preliminary judgements most error-prone in earthwork and rockwork budget quota practice - classifying trenches/pits against general earthwork, classifying dry and wet soil, muck and frozen soil, and identifying items already comprehensively included in the quota - plus the determination of efficiency-reduction and conversion coefficients built on them (wet soil, excavation within shoring, excavation between piles, locally deepened trenches/pits, deep excavation, uphill haul, etc.), and the calculation rule where several coefficients coexist. For budget preparation, settlement review and quota conversion disputes.
Core conclusions
1. Classifying trenches/pits and general earthwork
A trench or pit means a trench whose base width (the base width of the blinding layer or foundation shown on the design) is up to 7 m with base length over 3 times the base width, or a pit whose base length is up to 3 times the base width with base area up to 150 m2; anything beyond these limits that is not site levelling is general earthwork. (TB/T 10831-2024, volume note 2)
2. Classifying dry soil, wet soil, muck and frozen soil
- Dry and wet soil are split at the normal groundwater level given in the geological survey data: above the normal groundwater level is dry soil, below is wet soil. Where dewatering measures are adopted, the post-dewatering water level is taken as the normal groundwater level, and the cost of dewatering measures is calculated separately.
- Muck: soil whose water content exceeds the liquid limit and whose soil-water mixture is in a flowing state.
- Frozen soil: soil at 0 C or below containing ice; frozen soil in the quota includes short-term and seasonal frozen soil. (TB/T 10831-2024, volume note 3)
3. Items already comprehensively included, not adjustable
- Machine-excavated earthwork already comprehensively includes manual cleaning and trimming of residual layers up to 0.30 m thick left on the base and slopes; no adjustment is allowed in application (TB/T 10831-2024, volume note 4).
- Unless otherwise stated, the work content of pipe-laying items includes laying pipes along the trench, cleaning the trench bottom, visual inspection and cleaning of pipes; pipe laying and installation already comprehensively allow for ordinary trench-side shoring and strutting and are not calculated again; pipe joint lengths are comprehensively determined and not adjusted in application (SJG 181.4-2024, clause 1.1.4).
- Efficiency reduction for loaded uphill hauls (gradient up to 15%) by labour, handcarts and trucks is already comprehensively included in the corresponding haulage items and not calculated again (TB/T 10831-2024, volume note 6; the Shaanxi and Hunan local quotas are the same).
4. Efficiency-reduction and conversion coefficients (multiply the stipulated coefficient when executing the corresponding item)
| Case | Coefficient | Basis |
|---|---|---|
| Hand digging and hauling wet soil | labour of the corresponding item x1.18 | TB/T 10831-2024, volume note 5.1 |
| Machine digging and hauling wet soil | labour and machines of the corresponding item x1.15 | ibid |
| Hand-dug trenches/pits within shoring plates | labour x1.43 | volume note 5.2 |
| Excavating soil between piles (hand-excavation quota) | labour x1.25 | volume note 5.3 |
| Excavating soil between piles (machine-excavation quota) | labour and machines x1.10 | ibid |
| Locally deepened trenches/pits below the blinding of raft foundations | quantities by the trench/pit rules, labour and machines x1.25 | volume note 5.4 |
| Vertical transport of soil by hand | consumption of the corresponding hand-haulage item x1.50, haul distance taken as the vertical transport distance | volume note 5.5 |
| Bulldozers pushing soil with average layer thickness up to 0.30 m | labour and machines x1.25 | volume note 5.6 |
| Excavating earthwork on dynamically compacted ground | labour and machines of the corresponding item x1.15 | volume note 5.9 |
| Hand excavation deeper than 6 m where local hand digging is still needed | for the part beyond, per additional metre, corresponding quota x1.15 (the over-2 m items apply up to 6 m; beyond 6 m machine excavation should be considered) | volume note 5.10 |
| Concrete pipes laid directly on trench soil foundation | labour cost and machine-shift consumption x1.18 | SJG 181.4-2024, clause 1.1.4, item 6 |
| Excavators, piling machines and member hoisting on soft ground, operating on steel road plates or sleepers | labour and machines of the corresponding item x1.2; hire, erection/dismantling/moving and mobilisation costs of steel road plates or sleepers calculated separately | Hunan 2025 municipal works, volume note 10 |
Where several coefficients coexist, the local consumption standard states expressly that when the standard has two or more coefficients they are calculated by successive multiplication (Hunan 2025 municipal works, volume note 11); coefficients must not be added together, nor taken across volumes or trades.
5. Haulage and uphill efficiency reduction
- Loaded uphill hauls (gradient up to 15%) by labour, handcarts and trucks are already comprehensively included, not calculated again.
- For bulldozers and loaders hauling uphill under load, the efficiency reduction is the inclined ramp length multiplied by the stipulated coefficient: gradient 5%-10% coefficient 1.75, up to 15% coefficient 2.00, up to 20% coefficient 2.25, up to 25% coefficient 2.50 (Shaanxi consultation draft, table 1-3 loaded uphill efficiency-reduction coefficients; TB/T 10831-2024 volume note 6 points to the corresponding coefficients in table 3 of the volume).
- Hunan 2025 municipal works: where labour and handcart haulage of soil and rock goes uphill at gradients over 15%, and where loaded bulldozers and scrapers go uphill at gradients over 5%, the ramp haul distance is the ramp length multiplied by the stipulated coefficient.
6. Rockwork and over-excavation
- Rock excavation takes no slope easing; allowable over-excavation may be considered: permissible overbreak for blasted rock is 0.20 m for extremely soft and soft rock, 0.15 m for fairly hard and hard rock (Shaanxi consultation draft, item 9). The Hunan local rules are the same: soft and fairly soft rock 20 cm, fairly hard and hard rock 15 cm; no overbreak is counted at the bottoms of trenches and pits.
- Frozen-soil excavation may be executed under the soft-rock excavation quota (TB/T 10832-2024, volume note 3).
7. Not included; to be calculated separately
- The chapter notes do not include removal of surface obstructions, construction dewatering below the normal groundwater level, exclusion of surface water during earthwork excavation, or slope protection; where these occur they are calculated under the relevant provisions of other chapters; backfill assumes soil taken from within the site and does not include purchased soil - where purchased soil is used, calculate as stipulated (Shaanxi consultation draft, items 13 and 14; Hunan: this section does not include clearing surface obstructions, and dumping-ground occupation and levelling fees are calculated separately).
- Hand-dug pipe trenches and foundation pits are compiled for weak water inflow and can be built normally without pumping machinery; where pumping machinery must be used, it is calculated separately (TB/T 10832-2024, chapter 2 note).
- Cofferdams and island filling, steel sheet piling and well-point dewatering use the relevant items of TB/T 10823-2024 Railway Engineering Budget Quota Volume 2 Bridge and Culvert Works (TB/T 10832-2024, volume note 4).
8. Key measurement points
- Excavation, filling and haulage are measured in natural dense volume (natural volume); backfill in compacted volume with embedded structures deducted; extra excavation from slope easing and working-space allowances at trench and pit bottoms goes into the excavation quantity; slope method, slope coefficients and working-space widths follow the design or the approved construction scheme, or the quota annex tables where unspecified (local consumption standards, earthwork chapter notes).
- Site levelling means on-site cut, fill and levelling of thickness within +/-30 cm at the building site; cut-only or fill-only cannot use the site-levelling item; where cut/fill thickness exceeds +/-30 cm the full thickness follows the earthwork provisions; where earth is open-cut in bulk, site levelling is not calculated again (Shaanxi consultation draft, item 11).
- 'Within xx' and 'xx or less' include the number itself; 'beyond xx' and 'xx or more' exclude it (Hunan 2025 municipal works, volume note 13).
Applicability boundaries
- The coefficients belong to different quota systems: TB/T 10831-2024 (railway housing works), Hunan 2025 municipal works, the Shaanxi consultation draft (earthwork) and SJG 181.4-2024 (municipal water supply and drainage pipe networks) each have different coefficient tables and thresholds - coefficients must be taken from the notes of the quota volume actually applied, never across volumes or self-combined.
- Quotas are compiled for rational construction planning and normal construction conditions; apart from coefficients expressly allowing conversion, consumption must not be adjusted for differences in actual mix proportions, machine types or construction methods; unit prices may be adjusted to compilation-period prices, but consumption is a quantity standard (adjusting quantity is not adjusting price).
- Auxiliary contents already comprehensively included in the quota (manual cleaning up to 0.30 m, ordinary trench-side shoring, loaded uphill efficiency reduction up to 15%, etc.) must not be claimed again or converted for payment.
- Wet-soil classification follows the normal groundwater level from the geological survey; where dewatering is adopted the post-dewatering level applies, but the dewatering cost itself must be calculated separately - the two must not be duplicated.
Further reading
- TB/T 10831-2024 Railway Engineering Budget Quota, Volume 10 Housing Works: volume notes 2 to 7 and the loaded uphill efficiency-reduction coefficient table (table 3).
- TB/T 10832-2024 Railway Engineering Budget Quota, Volume 11 Water Supply and Drainage Works: chapter 2 notes, pipe trenches and pit excavation, items 1 to 4.
- TB/T 10823-2024 Railway Engineering Budget Quota, Volume 2 Bridge and Culvert Works (cofferdams, island filling, steel sheet piling, well-point dewatering).
- SJG 181.4-2024 Consumption Standard for Municipal Works, Volume 4 Water Supply and Drainage Pipe Networks, clause 1.1.4.
- Local consumption standards: earthwork chapter notes (slope coefficient tables, working-space width tables, allowable overbreak, soil and rock classification tables, loaded uphill efficiency-reduction coefficient tables).
- Conversion and missing items: judging conversion where an item's work content differs from site reality; compiling and submitting supplementary unit-price schedules for approval.
Keywords
- 土方定额系数
- 湿土系数
- 挡土板内挖土
- 挖桩间土方
- 人工降效
- 槽坑划分
- 干湿土划分
- 重车上坡降效
- 超挖量