Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Locating quota sub-items for earth backfill, replacement-subgrade, and muck loading/hauling in Beijing DB11/T 2382-2024

Replacement fill is priced under the ground-treatment chapter Table A.2.1-1 replacement subgrade (A-2-1 manual sand-gravel fill, A-2-3 sand (stone-chip) spreading; work content: layered spreading, leveling, compaction); indoor backfill under the earthworks chapter A.1.3-1 foundation backfill A-1-42 (backfill, leveling, compaction); site backfill and surplus-soil loading/hauling under A.1.3-2 / A.1.4-1 (A-1-51 soil loading, haul within 1 km; A-1-52 rock (muck) and spoil loading; work content includes haul, unloading, disposal, including spoil or muck disposal material).

Applicable Codes

  • DB11/T 2382-2024 建设工程施工消耗量标准(App. A 房屋建筑与装饰工程:A.1 土石方工程、A.2 地基处理与边坡支护工程)

Topic Positioning

Chapter attribution and sub-item location within Appendix A of Beijing's DB11/T 2382-2024 Consumption Standard for Construction Works for earth backfill, replacement subgrade, and muck loading/hauling — for quickly locating sub-items when compiling Beijing budgets/prices.

Core Conclusions

Replacement fill (ground-treatment chapter) — Table A.2.1-1 replacement subgrade:

  • A-2-1 manual sand-gravel fill (m3), work content: "1. Layered spreading, leveling, compaction (rolling). 2. Dozer pushing sand, sand filling, rolling." Consumption: composite labor class II 0.2000 workdays; natural sand-gravel 2315.4000 kg; electric rammer 250 Nm 0.0250 shifts; other materials 1.0%; other tools 1.5%.
  • A-2-3 spreading sand (stone chips) (m3), work content: "layered spreading, leveling, compaction." Consumption: composite labor class II 0.2930 workdays; sand 1787.6000 kg; electric rammer 250 Nm 0.0167 shifts; other materials 1.0%; other tools 1.5%.

Backfill (earthworks chapter) — A.1.3 backfill:

  • A-1-42 indoor backfill (m3, continuation of Table A.1.3-1 foundation backfill), work content: "backfill, leveling, compaction." Consumption: composite labor class III 0.2050 workdays; frog rammer 0.0490 shifts; other tools 1.5%.

Site backfill and loading/hauling — A.1.3-2 site backfill, A.1.4-1 earth (rock) haulage:

  • A-1-51 soil loading, haul within 1 km (m3), work content: "1. Mechanical loading with manual cleanup. 2. Haul, unload, dispose." Consumption: spoil/muck disposal 1.0000 m3; 12 t dump truck 0.0041 shifts.
  • A-1-54 rock (muck) and spoil loading, haul within 1 km (m3), same work content; consumption: spoil/muck disposal 1.0000 m3; 12 t dump truck 0.0057 shifts.

Chapter attribution matches the BOQ caliber: replacement fill sits in the ground-treatment chapter, backfill in the earthworks chapter; haul sub-items already include disposal material, so no separate disposal cost item is needed in price assembly.

Applicable Boundaries

Applies to compiling Beijing building budgets and price assembly under DB11/T 2382-2024; the above consumptions are standard values — convert per the standard's notes where actual conditions or work content mismatch; measurement calibers (cut/fill/haul all by drawing volume, no loose-coefficient multiplication) are covered in related cards and must not be mixed with consumptions. Haul beyond the base tier follows the "each additional 1 km" stacking rule.

Further Reading

DB11/T 2382-2024 Appendix A building and decoration works: A.1 earthworks (A.1.3-1 foundation backfill, A.1.3-2 site backfill, A.1.4-1 earth (rock) haulage), Table A.2.1-1 replacement subgrade; companion measurement calibers in Chapter 4, Section 4.2.

Keywords

  • 北京
  • DB11/T 2382-2024
  • 换填地基
  • 房心回填土
  • 土方装车
  • 渣土消纳
  • 消耗量标准