Masonry (brick masonry/block wall) quantity calculation rules: volume caliber, deductions and merges, wall length and height determination

Brick masonry and block walls are calculated by volume (m3) per design-drawn dimensions: deduct door/window openings, reinforced concrete columns/beams/ring beams/cantilever beams/lintels embedded in walls, and wall-recessed niches/duct grooves/heating grooves/fire-hose cabinets; do not deduct beam ends, slab ends, wood bricks, iron parts, steel pipes, or holes with individual area <= 0.3 sqm; waistlines, overhanging eaves, copings, windowsill lines, tiger-head bricks, and door/window casings protruding from the wall face are not added; brick pilasters are merged into the wall; exterior walls take the centerline, interior walls the net length; hollow bond walls by outer-profile volume, openwork walls do not deduct the openwork, and brick columns deduct beam pads, beam ends, and slab ends.

Applicable Codes

  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
  • SJG 111.2-2022 城市地下综合管廊工程消耗量标准(Vol. 2)
  • SJG 181.2-2024 市政工程消耗量标准 Vol. 2 桥涵工程
  • DB11/T 638-2016 房屋修缮工程工程量计算规范

Topic Positioning

Quantity calculation rules for brick masonry, block walls, and special masonry (hollow bond walls, openwork walls, brick columns, attached chimneys, etc.), covering the volume caliber, deduction/merge lists, and wall length/height determination, applicable to measurement of buildings (including railway houses and utility tunnels) under both BOQ and quota calibers.

Core Conclusions

Brick masonry and block walls are calculated by volume (m3) per design-drawn dimensions. Deduct: door/window openings, passage holes, and void rings; reinforced concrete columns/beams/ring beams/cantilever beams/lintels embedded in walls; wall-recessed niches/duct grooves/heating grooves/fire-hose cabinets. Do not deduct: beam ends, slab ends, purlin ends, sleeper timbers, wood ledger ends, wood bricks, door/window run heads; wall-reinforcing rebar/wood studs/iron parts/steel pipes within walls; holes with individual area <= 0.3 sqm. The volumes of waistlines, overhanging eaves, copings, windowsill lines, tiger-head bricks, and door/window casings protruding from the wall face are not added; brick pilasters protruding from the wall are merged into the wall; chimneys, ventilation ducts, and garbage chutes built attached to the wall are merged into the same-material wall by volume (deducting holes). Wall length: exterior walls by centerline, interior walls by net length, walls between frame members by net dimensions. Wall height by boundary: exterior walls under flat roofs to the underside of the roof slab; with roof trusses to the underside of the truss lower chord plus 0.2/0.3 m; interior walls with frame beams to the beam underside; parapets to the underside of the coping; gable walls by average height. Hollow bond walls are calculated by outer-profile volume (solid masonry at corners and intersections merged; solid parts such as between window openings and below window sills switched to miscellaneous masonry items); openwork walls do not deduct the openwork part; brick columns deduct the volumes of concrete beam pads, beam ends, and slab ends; masonry guide walls are calculated separately with the wall height reduced accordingly.

Applicable Boundaries

Applies to brick masonry/block wall measurement in buildings, railway houses, and utility tunnels; the 0.3 sqm hole threshold is consistent with other works but applies independently. Municipal bridge/culvert masonry (SJG 181.2-2024) has a simplified caliber: explicitly not deducting only steel pipes, settlement joints, expansion joints, and holes <= 0.3 sqm. Brick foundations and walls are divided at the design indoor floor level; local quotas (e.g., Shaanxi, Hunan) differ in wall-height details (interior walls with floor separations counted to slab top or underside) — the quota in force governs.

Further Reading

GB/T 50854-2024 Appendix D masonry works D.5.13 (attached chimneys/ventilation ducts/garbage chutes merged into walls); TB/T 10831-2024 railway budget quota Volume 10 building works volume notes (masonry deductions and merges, wall length/height, hollow bond/openwork walls, brick columns, guide-wall rules); SJG 111.2-2022 utility tunnel consumption standard Volume 2, 4.2.2 masonry works, 4.1.6 (hollow block walls); SJG 181.2-2024 municipal consumption standard Volume 2 bridge and culvert works 1.2.1 masonry works; DB11/T 638-2016 building repair quantity calculation code A.3.1 (brick foundation/wall division).