Adjusting haul-distance changes in quota transport items: items are compiled as a base-haul band plus increment bands; cost is not proportional to distance, so scaling by distance ratio is forbidden
Quota transport items come in a banded ladder of a base haul band plus an increment band; each band's cost carries distance-independent fixed consumptions - loading and unloading, waiting, empty returns - so cost is not proportional to distance: a shortened haul must not be scaled by ratio (1 km cut to 200 m is not x 0.2); where a first band up to 200 m exists, apply that band directly; where the first band is 1 km or more, 200 m still falls within it and the base item applies without reduction; only beyond the first band does base item + increment item x number of increments stack, the count rounding at the half (a remainder under half an increment unit is dropped, at half or more it counts as one); adjusted items must carry a conversion mark on the item number.
Applicable Codes
- DB63/T 2013-2022 公路养护工程预算定额 App. A(规范性)路基工程 A.2.1
- JTG/T 3821-2018 公路工程估算指标(路基工程章节说明)
- TB/T 10822-2024 铁路工程预算定额 Vol. 1 路基工程(LY-123~126)
- TB/T 10821-2024 铁路工程基本定额(YY-47~57、YY-81~82)
- TB/T 10832-2024 铁路工程预算定额 Vol. 11 给水排水工程(PY-129~136)
- SJG 111.1-2022 城市地下综合管廊工程消耗量标准(Vol. 1)1.2.10 及Table 1.2.10
Scope of the question
How to adjust quota transport items when the haul distance changes (e.g. 1 km cut to 200 m): whether the cost may be scaled by distance ratio, and the correct application and increment-counting method. Applies to transport items banded by haul in highways, railways, municipal works and the like.
Core conclusions
1. Scaling by distance ratio is forbidden (conversion red line) Quota transport items are a banded ladder compiled as base haul band plus increment band. Every band's cost includes loading and unloading, waiting, loading assistance, turning, cleaning and empty returns - fixed consumptions largely independent of distance; only the marginal hauling part varies with distance, so cost is not proportional to distance. Scaling by a coefficient (e.g. the 1 km item x 0.2) discounts the fixed consumptions too and grossly distorts. Coefficients apply only where the quota text or chapter notes expressly give one; haul distance is never scaled by ratio.
In the railway basic quotas, concrete mixer trucks (up to 8 / 10 / 12 m3) split loading and unloading from each 1 km hauled as two items (YY-47 loading/unloading / YY-48 per 1 km, plains and hills; YY-49 mountains and tunnels); small trucks split YY-56 loading/unloading / YY-57 per 50 m; short-haul materials YY-81 haul up to 100 m / YY-82 increment 100 m - fixed and distance consumptions are separated at item-structure level precisely because they are not proportionally convertible. The same for railway subgrade fill haulage LY-123 granular fill, load and haul up to 1 km / LY-124 increment 1 km, LY-125 stabilised soil up to 1 km / LY-126 increment 1 km.
Expressly allowed coefficients are another matter: e.g. DB63/T 2013-2022 Budget Quota for Highway Maintenance Works, Appendix A roadbed works A.2.1.2: for machine-excav earth and rock where machines cannot reach and labour completes part of the quantity per the execution plan, that labour part takes the corresponding quota x 1.15.
2. The correct adjustment method (steps)
- First check whether the volume has a first-band item matching the target haul; if so, apply it directly with no conversion. Example: railway water-supply and drainage earth haulage is compiled in four bands - manual carry PY-129 haul up to 20 m / PY-130 increment 10 m; barrows PY-131 up to 50 m / PY-132 increment 50 m; hand-loaded small trucks PY-133 up to 200 m / PY-134 increment 200 m; machine-loaded dump trucks PY-135 up to 1 km / PY-136 increment 1 km. Hand-loaded small-truck haulage of 200 m takes PY-133 (unit 100 m3) directly - PY-135 is never discounted.
- Where the volume's first band is large (1 km or more) and the actual haul does not exceed it, apply the base-haul item as it stands - no coefficient, no reduction. The base item covers any haul within its band (1 km includes 200 m); the quota does not subdivide downward.
- Only where the actual haul exceeds the base haul does base item + increment item x number of increments stack.
- Where the quota notes genuinely allow an adjustment (e.g. a coefficient), the converted item number must carry a conversion mark stating the conversion, lest review treat it as unfounded base-price tampering.
3. The half-rounding rule for haul remainders DB63/T 2013-2022, Appendix A roadbed works A.2.1.3: dump-truck haulage of roadbed earth applies only to average hauls within 15 km; beyond, charge per public-carriage rules. Where the haul exceeds the first quota haul unit, a remainder under half an increment unit is not counted; at half or more it counts as one increment unit. The Highway Works Estimate Indicators (JTG/T 3821-2018) roadbed chapter notes the same: dump-truck haulage of earth and rock applies to average hauls within 15 km; beyond, charge at surveyed market freight rates. Example: with increments of 200 m and an actual haul of 350 m, the excess 150 m is at least 100 m (half of 200 m) - one increment; an excess of 90 m, under 100 m - none.
4. Determining the haul Earth and rock hauls are the shortest distance from the excavation centroid to the filling (or spoil) centroid, the centroids fixed by the project execution plan. Where bulldozers haul uphill on grades over 5%, or manual and barrow haulage climbs over 15%, the haul is the ramp length of the graded section x the grade adjustment coefficient (see SJG 111.1-2022 Table 1.2.10).
Applicability limits
- Base hauls and increment units differ across industries and volumes (railway subgrade fill: load-haul up to 1 km / increment 1 km; mixer trucks: loading / per 1 km; small trucks: up to 100 m / increment 100 m; water and drainage earth: four bands up to 20 m / 50 m / 200 m / 1 km; tunnel concrete: up to 500 m / per 500 m and up to 100 m / per 100 m) - always check the chapter notes of the volume actually applied; never carry bands across volumes.
- The rules suit haul-banded transport items; coefficients only where the quota expressly gives them; hauls are never scaled by ratio.
- Actual haul within the first band applies that band at any value - no downward subdivision, no reduction.
- Highway roadbed earth haulage beyond an average 15 km is not charged by quota (indicator) but per public-carriage rules or surveyed market freight.
- Haul determination needs an approved (settled) execution plan; centroids are not fixed subjectively.
Further reading
- DB63/T 2013-2022 Budget Quota for Highway Maintenance Works, Appendix A (normative) roadbed works, A.2.1 notes: A.2.1.1 (item contents), A.2.1.2 (labour for machines x 1.15), A.2.1.3 (15 km and half-rounding), A.2.1.4 quantity rules, Table A.2 bulkage coefficients.
- JTG/T 3821-2018 Highway Works Estimate Indicators, roadbed chapter notes (15 km limit; beyond, market freight).
- TB/T 10822-2024 Railway Works Budget Quota Manual, Volume 1 Roadbed Works, Chapter 1 Section 3 fill haulage (LY-123 to 126).
- TB/T 10821-2024 Railway Works Basic Quota, Chapter 4 Section 2 concrete haulage (YY-47 to 57), Chapter 7 Section 3 small-truck haulage (YY-81 to 82).
- TB/T 10832-2024 Railway Works Budget Quota Manual, Volume 11 Water Supply and Drainage Works, Chapter 1 Section 1 earth haulage (PY-129 to 136).
- SJG 111.1-2022 Consumption Standard for Urban Utility Tunnel Works (Volume 1 earthworks, support and piling), 1.2.10 haul determination and Table 1.2.10 grade adjustment coefficients.