Road structural-layer quantity calculation: BOQ and quota dual calibers, deduction rules, and compacted-volume algorithm
Road structural-layer quantities split into two calibers — BOQ quantities (GB/T 50857-2024 Appendix B) and quota quantities (local consumption quotas, e.g., Shenzhen SJG 181.1-2024) — with different deduction rules that must not be mixed: the BOQ base course is by top surface area without deducting chambers; the surface course deducts no chambers but deducts flat stones when present; the Shenzhen quota base course deducts chambers whose single internal area is > 0.6 m2, and the surface course additionally deducts flat stones, curbs, and edge stones; base-course mixed-material mixing and transport are measured in m3 by compacted volume.
Applicable Codes
- GB/T 50857-2024 市政工程工程量计算标准
- SJG 181.1-2024 市政工程消耗量标准 Vol. 1 道路工程
Topic Positioning
The BOQ and quota calibers, deduction rules, and volume algorithms for quantity calculation of municipal road structural layers (surface -> base -> subbase -> bedding), used for BOQ preparation and quota pricing.
Core Conclusions
- BOQ caliber (GB/T 50857-2024 Appendix B): base courses (040202) are measured in m2 by top surface area as shown on design drawings, without deducting any chambers; surface courses (040203) are measured in m2 as shown on design drawings, without deducting chambers, but surface courses with flat stones shall deduct the area occupied by flat stones.
- Quota caliber (Shenzhen SJG 181.1-2024 as an example): the base course is measured in m2 by design dimensions, deducting chambers whose single internal area is > 0.6 m2; prime coats, tack coats, seal coats, and pavements additionally deduct flat stones, curbs, and edge stones connected to the pavement and chambers > 0.6 m2; cement concrete pavement grooving follows the surface-course caliber.
- Volume: centrally mixed and transported base-course material is measured in m3 by compacted volume after paving (area x design compacted thickness); for trapezoidal-section bedding/base courses the area is computed by the average width of the section.
- Key difference: BOQ "base course does not deduct chambers" vs. quota "deducts chambers > 0.6 m2" — use BOQ rules when compiling the BOQ and quota rules when applying quotas; the two sets of quantities are computed separately and must not be mixed.
Applicable Boundaries
- Surface courses under quotas are generally measured by area, with thickness differences handled by "per 1 cm increase/decrease" adjustment sub-items rather than computing volumes separately.
- Volumes are always compacted volumes; no loose-volume coefficient is added for mixing and transport; for layered paving, compute layer by layer by layer thickness.
- SJG 181.1 is the Shenzhen local consumption standard; in other regions the deduction rules follow the current local quota of the project location.
Further Reading
GB/T 50857-2024 "Standard for measurement of municipal works" Appendix B Table B.2.1 (road base course 040202), Table B.3.1 (road surface course 040203); SJG 181.1-2024 "Municipal works consumption standard, Volume 1: road works" Clauses 2.2.2~2.2.4 (base-course area and mixing/transport volume), Clause 3.2.1 (prime coat/tack coat/seal coat/pavement), Clause 3.2.7 (cement concrete pavement grooving).