Municipal road surface course quantity calculation: manhole and rain-inlet areas not deducted; surface with curb stones deducts curb stones (GB/T 50857-2024 Table B.3.1)
Per GB/T 50857-2024 "Standard for measurement of municipal works" Appendix B Table B.3.1 "Road surface course (code 040203)", cement concrete (040203007) and asphalt concrete (040203006) share the same rule: computed by area per design dimensions, without deducting areas occupied by various manholes; surface courses with curb stones shall deduct the curb-stone areas (unit m2). That is, manhole and rain-inlet areas are never deducted; the old GB 50857-2013 Table B.3 rule was identical (that edition is abolished) — no change between editions.
Applicable Codes
- GB/T 50857-2024 · Standard for Measurement of Quantities of Municipal Works App. B Table B.3.1
- GB 50857-2013 · Code for Measurement of Quantities of Municipal Works Table B.3(已废止)
- DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) App. D 市政工程(北京)
Topic Positioning
A close reading of the quantity calculation rules for municipal road surface courses (BOQ code 040203): cement and asphalt concrete surface courses are measured by area (m2) per design dimensions; areas occupied by "various manholes" such as inspection manholes and rain inlets are not deducted, while curb-stone areas are deducted for courses laid with curb stones. Applicable when compiling BOQs under the current GB/T 50857-2024.
Core Conclusions
Per the current GB/T 50857-2024 Appendix B Table B.3.1 "Road surface course (code 040203)", where 040203007 cement concrete and 040203006 asphalt concrete share one rule, the original text: "Computed by area per the design dimensions shown, without deducting areas occupied by various manholes; surface courses with curb stones shall deduct the areas occupied by the curb stones" (unit m2).
Key points: (1) areas occupied by inspection manholes and rain inlets (both within "various manholes") are never deducted; (2) for courses with curb stones, the curb-stone area shall be deducted.
Historical comparison: the old GB 50857-2013 Table B.3 "Road surface course (code 040203)" rule was exactly the same (that edition is abolished and replaced by the 2024 edition) — no change on this item; simply follow the current 2024 edition.
Companion caliber (Beijing): the current DB11/T 2382-2024 "Consumption standards for construction works" Appendix D municipal works has matching sub-items, e.g., D2-2-20 cement concrete surface course 18 cm thick (100 m2) and D2-2-21 per 1 cm increase/decrease, measured per design dimensions, matching the BOQ rule.
Practice tip: concrete around manholes (reinforcement around inspection manholes and rain inlets) belongs to the shaft reinforcement process, accounted separately by the corresponding manhole/rain-inlet BOQ items and companion sub-items — it can neither be reversely deducted from the surface area nor double-counted into the surface; when compiling, distinguish the BOQ measurement layer (GB/T 50857-2024) from the quota consumption layer — under quota pricing, the chapter notes of the adopted quota volume govern.
Applicable Boundaries
- Applies to municipal road surface course BOQ measurement, focusing on cement concrete (040203007) and asphalt concrete (040203006) items.
- Whether other surface materials (e.g., block surfacing) deduct manholes follows each table row's own rule; do not apply this rule to them.
- This rule is a BOQ measurement caliber (GB/T 50857-2024); quota consumption rules (local quotas) may have different deduction calibers (some local quotas additionally deduct curb, side, and edge stones) — the two cannot be mixed; follow the chapter notes of the adopted quota volume.
- The manhole deduction rule for road base courses (e.g., cement-stabilized macadam base) differs from surface courses (BOQ base measured by top area without deducting manholes); apply each table row's rule separately and never apply the surface rule to bases.
Further Reading
- Current original: GB/T 50857-2024 Appendix B Table B.3.1 "Road surface course (code 040203)" (040203006 asphalt concrete, 040203007 cement concrete).
- Old comparison (abolished): GB 50857-2013 Table B.3 "Road surface course (code 040203)".
- Beijing companion: DB11/T 2382-2024 Appendix D municipal works, sub-items D2-2-20 cement concrete surface 18 cm, D2-2-21 per 1 cm increase/decrease.
- Extension: base course measurement rules (GB/T 50857-2024 Appendix B base-related rows), manhole/rain-inlet measurement rules (by design count in units, perimeter reinforcement separate).
Keywords
- 道路面层
- 水泥混凝土面层
- 沥青混凝土面层
- 检查井
- 雨水口
- 不扣除
- 平石
- 040203
- GB/T 50857
- 市政工程工程量计算