Divergent classification of trench, foundation pit and general earthwork: the BOQ measurement standard treats an excavation with bottom width no more than 3m and bottom length over 3 times the bottom width as a trench and anything beyond as a foundation pit (bottom width and bottom length both exclude working space); the consumption quota treats bottom width no more than 7m with bottom length over 3 times the bottom width as a trench, bottom length no more than 3 times the bottom width with bottom area no more than 150m2 as a foundation pit, and anything beyond as general earthwork. The two criteria run on separate tracks and must not be cross-inferred

BOQ itemisation follows the measurement standard: GB/T 50854-2024 Annex A, A.4.5 'Classification of trench and foundation pit earthwork: within foundation earthwork, a bottom width of no more than 3m with a bottom length over 3 times the bottom width is a trench, and anything beyond that range is a foundation pit. Bottom width and bottom length shall not include working space dimensions'; foundation earthwork (010102) is split into only two items, trench excavation and foundation pit excavation. Quota application follows the quota's own classification (e.g. local consumption standards and the railway buildings quota: bottom width no more than 7m and bottom length over 3 times the bottom width is a trench; bottom length no more than 3 times the bottom width and bottom area no more than 150m2 is a foundation pit; anything beyond is general earthwork). One and the same foundation excavation may be classed as a 'foundation pit' in the BOQ yet remain a 'trench' under the quota; the two criteria are applied on separate tracks and must not be cross-inferred. Classify trench versus foundation pit on the net dimensions shown on the design drawings (no working space added); never add working space first and then test the 3m threshold.

Applicable Codes

  • GB/T 50854-2024 App. A A.4.5、Table A.2.1、A.4.6、A.4.7
  • DB11/T 2382-2024 第7.1.3、7.1.6、8.1.3条
  • TB/T 10831-2024 册说明二

Topic positioning

This card settles in one place the classification criteria for trench, foundation pit and general earthwork: the BOQ measurement standard and the consumption quota use different threshold values (3m versus 7m/150m2), and mixing the two during BOQ preparation, tender rate build-up and final account review frequently mis-sorts items and mis-applies quota line items. The card gives the verbatim thresholds of both criteria and the rules for running them on separate tracks.

Core conclusions

1. The BOQ criterion (GB/T 50854-2024 Annex A) - two categories, a 3m threshold.

  • A.4.5 verbatim: 'Classification of trench and foundation pit earthwork: within foundation earthwork, a bottom width of no more than 3m and a bottom length over 3 times the bottom width is a trench, and anything beyond that range is a foundation pit. Bottom width and bottom length shall not include working space dimensions.'
  • Table A.2.1 foundation earthwork (code 010102) sets only two items, 'trench earthwork excavation' and 'foundation pit earthwork excavation'; there is no 'general earthwork' item within foundation earthwork (site levelling and general earthwork belong to 010101 in Table A.1.1 earthwork).
  • Key detail: bottom width and bottom length exclude working space dimensions - the trench or foundation pit attribute is judged on the net dimensions shown on the design drawings. Never add the working space width under A.4.6 first and then test the 3m threshold, otherwise a genuine trench is misjudged as a foundation pit (the BOQ item code, the all-in unit rate and the final account review path all change).
  • BOQ quantities are still computed under their own rules: foundation pit and trench earthwork excavation is measured as the bottom area of the foundation (including the bed) shown on the design drawings plus the working space area, multiplied by the excavation depth, in volume.

2. The quota criterion - three categories, thresholds of 7m and 150m2.

  • Local consumption standards (e.g. DB11/T 2382-2024 clauses 7.1.3 and 8.1.3): 'Earthwork excavation items should be set up by manual or mechanical excavation as trench, foundation pit and general earthwork items, and the division between trench, foundation pit and general earthwork shall comply with the following: 1 bottom width no more than 7m and bottom length over 3 times the bottom width is a trench; 2 bottom length no more than 3 times the bottom width and bottom area no more than 150m2 is a foundation pit; 3 anything beyond the above ranges is general earthwork.'
  • The railway buildings quota is cast in the same mould: a trench or pit is a trench with a bottom width (bed or foundation bottom width shown on the design drawings) of no more than 7m and a bottom length over 3 times the bottom width, or a pit with bottom length no more than 3 times the bottom width and bottom area no more than 150m2; excavations beyond these limits that are not site levelling count as general earthwork.
  • The quota classification exists to select the quota line item (manual and mechanical, trench, pit and general earthwork line items carry different consumption inputs); it is unrelated to the BOQ measurement criterion.

3. Rules for running the two on separate tracks.

  • Preparing the BOQ: classify and code under the BOQ measurement standard (3m threshold, two categories, judgement on net dimensions).
  • Applying the quota for rate build-up: select the line item under the classification of the applicable quota (7m/150m2, three categories); line item quantities follow the quota calculation rules (including working space and battered sides).
  • The two must not be cross-inferred: 'a foundation pit in the BOQ' does not imply 'a pit quota line item', nor may quota line item classification change the BOQ item attribute. Foundation earthwork with a bottom width between 3m and 7m and a bottom length over 3 times the bottom width is typically 'foundation pit under the BOQ, trench under the quota' - the criterion mismatch most often met in checking.

Applicability boundaries

  • A.4.5 applies only to foundation earthwork (010102) in GB/T 50854-2024 Annex A; pipeline trench earthwork, rock and site levelling have their own rules; other sector standards (urban rail transit GB/T 50861-2024, the railway TB/T 10831-2024 system, etc.) follow their own classification criteria and annex tables, which must not be cross-applied with the building criteria.
  • The 7m/150m2 three-way classification belongs to the consumption quota criterion, not to the BOQ measurement standard; boundary values may differ between regional and sector quotas, and the quota actually applicable to the project governs.
  • The classification only decides 'which item to list, which quota line item to apply, which rate to use'; it does not change the measurement standard and measurement rules agreed in the contract, and final account quantities are still re-measured under the quantity take-off standard agreed in the contract.
  • Trench and pit classification, excavation depth, the batter start point and working space widths are distinct parameters, each independent (working space widths and batter coefficients: see the earthwork excavation parameters card).

Further reading

  • GB/T 50854-2024 quantity take-off standard for building and decoration works, Annex A: A.4.5 (classification of trench and foundation pit), Table A.2.1 foundation earthwork (code 010102, calculation rules and work content for trench and pit earthwork excavation), A.4.6 (working space width), A.4.7 (excavation depth).
  • DB11/T 2382-2024 construction works consumption standard, clauses 7.1.3 (earthwork classification for municipal general items), 8.1.3 (earthwork classification for landscape works) and 7.1.6 (working space and excavation depth).
  • TB/T 10831-2024 railway works budget quota manual, Volume 10 buildings, volume notes item 2 (boundary between trench-pit and general earthwork).
  • Judging cross-volume misapplication between BOQ items and quota line items: see the cards on the railway QY/LY boundary.