Defining and selecting construction contract price forms: unit-rate, lump-sum and cost-plus contracts chosen by design depth, technical difficulty, time and pricing risk

GB/T 50500-2024 clause 3.4.1 fixes the selection: clear requirements, controllable measurement and pricing and small price-fluctuation risk suit the lump-sum contract; requirements not yet clear, high technical difficulty, many uncontrollable pricing factors and large price risk suit the unit-rate contract; extreme urgency precluding detailed planning and full negotiation, or specially complex works with large pricing risk, suits cost-plus - clause 3.4.3 adds emergency rescue, disaster relief or specially complex works. The statutory definitions are clauses 2.0.6~2.0.8 (unit-rate: quantities as executed, rates fixed within agreement; lump-sum: price fixed within agreement, no adjustment for quantity changes while drawings and conditions stand; cost-plus = cost + agreed fee). The choice also binds the BOQ-error liability (3.1.8), risk allocation (3.3.2/3.3.3) and settlement treatment (GB/T 51095-2015 clause 8.2.5).

Applicable Codes

  • GB/T 50500-2024 第2.0.6、2.0.7、2.0.8条
  • GB/T 50500-2024 第3.1.8条
  • GB/T 50500-2024 第3.3.1、3.3.2、3.3.3、3.3.5条
  • GB/T 50500-2024 第3.4.1、3.4.3、3.4.4、3.4.5、3.4.6条
  • GB/T 50500-2024 第8.2.1、8.7.2、8.9.3条
  • GB/T 50875-2013 第3.3.4、3.3.6、3.3.7、3.3.8条
  • GB/T 51095-2015 第8.2.5条
  • 建设部令第107号《建筑工程施工发包与承包计价管理办法》第十二条、第十三条(现行文本见住房和城乡建设部令第16号修订版)
  • DBJ/T 15-115-2016 · Specification for Construction Engineering Transactions of Guangdong Province 第6.7.3条

Positioning

Which construction contract price forms exist and by what conditions each is chosen: the standard definitions of unit-rate, lump-sum and cost-plus contracts under GB/T 50500-2024, the selection rules (design depth / clarity of requirements, technical difficulty, urgency, controllability of measurement and pricing, pricing risk), and the BOQ liability, risk allocation and settlement differences that follow the choice.

Core conclusions

1. Definitions (clauses 2.0.6~2.0.8)

  • Unit-rate contract: "a construction contract under which the employer and contractor agree to compute, adjust and confirm the contract price on the bill of quantities, item descriptions and all-in unit rates. Within the agreed scope the contract rates are not adjusted." Rates stay fixed within the agreed conditions and adjust beyond them per the contract; BOQ items and quantities follow the measured work actually done by the contractor.
  • Lump-sum contract: "a construction contract under which the parties agree to compute, adjust and confirm the price on the contract drawings and contract specification. Within the agreed scope the total price is not adjusted." While the drawings and conditions stand, changes in BOQ items and quantities are no ground for adjustment; when they change, the price adjusts per the change and the contract.
  • Cost-plus contract: "a construction contract under which the parties agree to compute, adjust and confirm the price on the works cost determined by the prescribed measurement and pricing bases plus a fee computed in the agreed manner." Main forms: cost plus fixed fee, cost plus fixed-percentage fee, cost plus bonus.

2. Selection rules (3.4.1, 3.4.3)

Clause 3.4.1: construction contracts may adopt unit-rate, lump-sum or cost-plus. The choice follows the factors bearing on the tender price - drawing depth, technical difficulty, project scale, implementation programme, BOQ preparation time and pricing risk:

  • requirements clear, measurement and pricing controllable, price-fluctuation risk small - lump-sum preferred;
  • requirements not yet clear, high technical difficulty, many uncontrollable pricing factors, large price-fluctuation risk - unit-rate preferred;
  • extreme urgency without time for detailed planning and full negotiation, or specially complex works with large pricing risk - cost-plus preferred. Clause 3.4.3: "emergency rescue, disaster relief or specially complex works suit the cost-plus contract."
Dimension Lump-sum Unit-rate Cost-plus
Clarity of requirements High (scope, quality fixed) Not yet clear Technical/structural scheme unforeseeable
Drawing depth at tender Complete; drawings and spec define all work Insufficient or still developing No drawings, scheme open
Technical difficulty Routine High Especially complex
Urgency Normal programme Normal programme Extreme urgency; rescue and relief
Controllability of pricing Controllable Many uncontrolled factors Large risk, unpriceable in advance
Market swing / pricing risk Small, contractor carries Large, re-measurement and adjustment Quantity and price risk mostly on the employer
BOQ preparation time Ample Fairly ample, design unsettled No time for a detailed BOQ

3. Liabilities bound to the form

  1. BOQ accuracy (3.1.8): under unit-rate contracts the completeness of itemisation, accuracy of item descriptions and quantities of the work-item lists are the employer's responsibility, and tenderers may not alter them; under lump-sum they are the contractor's, tenderers supplementing items from the drawings and standards; priced-by-item preliminaries lists are the contractor's responsibility in either form.
  2. Risk allocation (3.3.2, 3.3.3): the employer carries BOQ errors in its own lists (preliminaries excepted), errors in original data and reference bases, approved variations, directed acceleration / early completion / suspension, changes in laws and regulations, swings beyond the tendered risk band and beyond the adjustment scope of clause 8.7; the contractor carries the completeness of preliminaries lists, defects in the priced BOQ of lump-sum contracts (provisional-quantity unit-rate items excepted), all work needed to complete the unit-rate BOQ and its item descriptions, costs from its own methods, plant, technology or management, and price swings within the agreed band - but "carries no risk of changes in laws and policies".
  3. No uncapped risk (3.3.1): "the content and scope of risk in measurement and pricing shall not be agreed as uncapped risk, all risk or similar wording" - no form may push risk boundlessly onto one party.
  4. Total price and document precedence (3.4.5, 3.4.6): under unit-rate the total price covers all costs of completing the BOQ, BOQ errors adjusting per clause 8.2, the priced BOQ being a contract document whose rates serve adjustments (item-priced entries follow lump-sum rules); under lump-sum the total price covers all work required by the drawings and specification, the priced BOQ only reflecting its composition, its rates usable for variations and additional works, provisional-quantity unit-rate items following unit-rate rules. "Under unit-rate contracts, discrepancies between drawings and the tendered work-item list resolve in favour of the BOQ; under lump-sum, discrepancies between drawings and specification and the priced BOQ resolve in favour of the drawings and specification."
  5. No deviation from the tender's substance (3.4.4): the contract price is agreed from the tender and bid documents and may not depart from the tender's substantive content - scope, duration, price, quality.

4. A separate axis from "fixed / adjustable price"

MoHURC Order No. 107, Article 12: prices may be (1) fixed - total or unit price unadjustable within the agreed risk band; (2) adjustable - adjusted during performance per the agreed method; (3) cost plus. That clause governs the price-adjustment mechanism; unit-rate / lump-sum / cost-plus is the measurement-and-pricing basis. The two combine into fixed-lump-sum, adjustable-lump-sum, fixed-unit-rate and adjustable-unit-rate. A contract naming only "fixed price" without the basis, or only "unit-rate" without risk bands and adjustment rules, is incomplete. Article 13: "the parties shall consider the effect of market conditions and factor-price changes when fixing the contract price."

5. Settlement treatment by form (GB/T 51095-2015 clause 8.2.5)

The final account is compiled by contract type: lump-sum - adjust the agreed adjustable items and risk factors beyond the agreed scope on the total price; unit-rate - rates fixed within the agreed risk band, quantities measured as actually completed; cost-plus - compute cost, fee and taxes by the agreed method.

6. Local and sector notes

Guangdong DBJ/T 15-115-2016 clause 6.7.3 (from GB 50500-2013 clause 7.1.3): "works tendered on a bill of quantities shall adopt unit-rate contracts" - the practical norm of unit-rate as the default in BOQ tendering; the current national standard and the contract govern.

Applicable boundaries

  • For building and municipal works priced on BOQs - contract-form choice at tender, condition drafting and settlement characterisation.
  • Clauses 3.4.1/3.4.3 are recommendations ("should"); other choices per the project stand, but never breaching the ban on uncapped risk (3.3.1) or the tender's substance (3.4.4).
  • GB/T 50500-2024 is a recommended standard - express contract terms prevail; EPC and other modes fall outside this three-way split.
  • Versions: Order No. 107 was amended by Order No. 16 (effective 2014-02-01), the three price methods continuing - verify article numbers against the current text; the old mandatory "unit-rate shall be adopted" of GB 50500-2013 clause 7.1.3 became the recommendation of clause 3.4.1 in 2024.
  • This card gives selection rules and clause mapping only; risk bands, adjustment formulas and variation pricing sit in the dedicated cards.

Further reading

  • GB/T 50500-2024 clauses 2.0.6~2.0.8, 3.1.8, 3.3.1~3.3.3, 3.3.5, 3.4.1, 3.4.3~3.4.6, 8.2.1, 8.7.2, 8.9.3; GB/T 50875-2013 clauses 3.3.4, 3.3.6~3.3.8; GB/T 51095-2015 clause 8.2.5; Order No. 107 Articles 12-13 (as amended by Order No. 16); DBJ/T 15-115-2016 clause 6.7.3.