Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Deducting unexecuted (unbuilt) items from the contract price: disallowance rules at final account (re-measurable vs lump-sum contract bases, linked deductions, and contractor compensation)

Unexecuted work must be disallowed from the contract-price BOQ: under re-measurable (unit-rate) contracts, measurement is against actuals and unexecuted items are deducted at the contract all-in unit rates (with rates reasonably marked up where the reduction exceeds 15%); under lump-sum contracts, the unexecuted portions are disallowed after checking settlement drawings, scope and taking-over (completion acceptance) reports against the contract price. Whole-item deletions require linked adjustment of preliminaries and statutory levies and fees; cancellation of nominated specialist subcontract works requires deduction of the corresponding main contractor's attendance and coordination provisions; dayworks not incurred are clawed back; for work cancelled for non-contractor reasons, the contractor's incurred costs and reasonable expected returns deserve compensation.

Applicable Codes

  • T/ZBD 100.5-2023 第3.1.4~3.1.6条
  • GB/T 50500-2024 第8.9.1/8.9.2/8.9.8条
  • GB/T 50500-2024 第8.5.3/8.6.5条
  • GB/T 51095-2015 第8.2.4条

Topic Positioning

This card gives the complete rules for "how unexecuted/unbuilt items are deducted from the contract price" at final account (including final account review): disallowance bases by contract type, easily missed linked deductions, and contractor-protection clauses.

Core Conclusions

  1. General principle (T/ZBD 100.5-2023, Clause 3.1.4): whether re-measurable (unit-rate) or lump-sum, work found unexecuted upon scope change or taking-over (completion acceptance) is disallowed from the contract-price BOQ; identification rests on consistency checks of settlement drawings against contract-price BOQ contents and site surveys of the physical works.
  2. Re-measurable (unit-rate) contracts: re-verify against actually completed and measurable quantities (Clause 3.1.6); unexecuted items are not measured and are deducted at the contract all-in unit rates; where variations reduce quantities by more than 15% (exclusive), per GB/T 50500-2024, Clause 8.9.2, the unit rate may be reasonably marked up before deduction — considering the loss of labour and material-purchase discounts — protecting the contractor's scale economics.
  3. Lump-sum contracts: check consistency of settlement drawings, contract scope, taking-over (completion acceptance) reports, and contract-price contents (Clause 3.1.5); unexecuted or inconsistent portions are generally disallowed; omissions are deemed verified by the contractor before signing and are generally not compensated (except where the employer provided the tender BOQ and the contract expressly allows adjustment).
  4. Linked deductions: when an item is wholly deleted from the scope or converted to specialist subcontracting, preliminaries and statutory levies and fees adjust accordingly (Clauses 3.1.4, 3.1.6); cancellation of a provisional sum for nominated specialist subcontract works or of specialist works directly let by the employer requires deduction of the corresponding main contractor's attendance and coordination provisions from the contract price (GB/T 50500-2024, Clause 8.5.3); dayworks enter the final account as actually incurred, and unincurred daywork amounts in the contract BOQ are deducted from the final account total (Clause 8.6.5).
  5. Contractor protection: where work originally scheduled is cancelled by the employer for non-contractor reasons and the contractor's incurred costs or due returns are not covered by other paid/payable or substitute items, the employer shall compensate the loss costs and reasonable expected returns (Clause 8.9.8).

Applicable Boundaries

Applies to disallowance of unexecuted work at final account preparation and review; not to in-process valuation of variations, replacement of provisional sums, or over-draws of free-issue materials (by the employer) (each has its own rules). Where the contract provides otherwise, the agreed terms prevail (GB/T 50500-2024, Clause 1.0.3). Before deducting, confirm the unbuilt facts in writing (site survey records, meeting minutes) and synchronously deduct the corresponding preliminaries, statutory levies and fees, and taxes and duties (VAT under the current standard) — avoiding "entity deducted, fees still hanging".

Further Reading

See T/ZBD 100.5-2023, Clauses 3.1.4-3.1.6 (deduction methods and review focus); GB/T 50500-2024, Clauses 8.9.1, 8.9.2 (unit-rate adjustment for reductions over 15%), Clause 8.5.3 (deduction of the main contractor's attendance and coordination provisions), Clause 8.6.5 (dayworks), Clause 8.9.8 (compensation for cancelled work); basis of preparation for the final account also in GB/T 51095-2015, Clause 8.2.4, and GB/T 50326-2017, Clause 18.3.3.