disallowance / downward adjustment on review
- 01
Disallowance grounds on final-account review for double counting of earthwork haul distance: the all-in unit rate cost envelope under GB/T 50500-2024 + the "disposal of surplus (excavated) material" itemisation basis in the measurement standards
Earthwork loading and haulage costs are already included in the correspo…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准GB/T 50857-2024 市政工程工程量计算标准2026-09-25 - 02
Bases the employer must provide for disallowance / downward adjustment on review of the settlement: the review-basis checklist, type-by-type reconciliation, and burden of proof
The employer's claimed disallowance / downward adjustment on review must…
GB/T 51095-2015 建设工程造价咨询规范 8.2.4/8.3.4/8.3.8GB/T 50500-2024 建设工程工程量清单计价标准 第10.3节T/ZBD 100.5-2023 建设工程结算审核作业指引 2.1.1/2.2/3.12026-09-25 - 03
Deducting unexecuted (unbuilt) items from the contract price: disallowance rules at final account (re-measurable vs lump-sum contract bases, linked deductions, and contractor compensation)
Unexecuted work must be disallowed from the contract-price BOQ: under re…
T/ZBD 100.5-2023 第3.1.4~3.1.6条GB/T 50500-2024 第8.9.1/8.9.2/8.9.8条GB/T 50500-2024 第8.5.3/8.6.5条2026-09-25