Statutory notice period for clarifications/modifications of tender documents: those possibly affecting bid preparation must be notified in writing at least 15 days before the deadline; below 15 days the deadline must be extended (Bidding Law Article 23, Implementation Regulations Article 21)
Clarifications or modifications of issued tender documents that may affect bid preparation must be notified in writing to all potential bidders at least 15 days before the submission deadline; if less than 15 days remain, the deadline must be extended (a statutory duty, not an option), with bid opening extended accordingly. Clarifications not affecting preparation are free of the 15-day rule - the tenderer informs at a reasonable time before the deadline.
Applicable Codes
- 《中华人民共和国招标投标法》(2017修正,主席令第86号)第二十三条、第二十四条、第三十四条
- 《中华人民共和国招标投标法实施条例》(2018修订)第二十一条、第二十二条
- 《建设工程项目招标投标活动程序标准》DB22/T 5036-2020
Topic Positioning
Rules on the statutory notice period when the tenderer clarifies or modifies tender documents after issue and before the deadline: which content requires 15-day advance written notice, what to do when time is short, and which clarifications are exempt - for compliant handling by tenderers/agents modifying documents before the deadline.
Core Conclusions
I. Basic rule (Bidding Law, Article 23): necessary clarifications or modifications of issued tender documents shall be notified in writing to all document recipients at least 15 days before the submission deadline; such content forms part of the tender documents.
II. The 15-day threshold and the extension duty (Implementation Regulations, Article 21): the tenderer may make necessary clarifications or modifications of issued prequalification or tender documents. Where content may affect preparation of prequalification applications or bids, it shall be notified in writing to all potential bidders at least 3 days before the prequalification deadline or 15 days before the bid deadline; if less, the tenderer shall extend the corresponding deadline. Key readings:
- "May affect bid preparation" triggers the 15-day rule - e.g., changes to the BOQ, evaluation method, contract terms, or technical requirements are normally held to affect preparation;
- Below 15 days, extending the deadline is mandatory - failure is a procedural violation; after extension, the gap from the notice must again be at least 15 days;
- Extension mechanics: (1) extend bid opening simultaneously (Article 34: opening occurs at the same time as the deadline); (2) state the new deadline in the written notice to all potential bidders; (3) where venue/opening time is affected, the agent shall complete the change formalities promptly;
- Mandatory-tender floor: from issue of documents to bid deadline, not less than 20 days (Article 24) - extension only postpones and normally cannot breach it, but the new deadline must be checked against it.
III. Exception: clarifications not affecting preparation. The 15-day threshold targets only affecting content; non-affecting items (e.g., changing the opening room) have no statutory notice period - the tenderer informs at a reasonable time before the deadline (local standard DB22/T 5036-2020 concurs).
IV. Practice tip: apply "affecting preparation" strictly - when in doubt, use 15 days; if truly pressed, extend the deadline - the cheapest, safest fix. "15 days before" runs in calendar days; leave margin to avoid borderline disputes.
Applicable Boundaries
- Applies to clarifications/modifications after issue and before the deadline; at prequalification the rule is "at least 3 days before" (do not confuse 3 and 15);
- The pivot is "possibly affecting bid preparation": substantive changes (BOQ, evaluation, contract, technical) trigger 15 days + extension; procedural/non-substantive items - tenderer sets reasonable timing;
- Mandatory-tender projects must also keep the 20-day minimum bidding period (Article 24);
- This is a procedural rule, complementing the substantive effect that clarifications form part of the tender documents and bind the contract price.
Further Reading
- Bidding Law (2017 revision, Decree No. 86) Articles 23, 24, 34.
- Implementation Regulations (2018 revision) Article 21 (3/15 days and extension duty).
- DB22/T 5036-2020 (local practice: non-affecting clarifications at reasonable time; extensions stated in writing with venue changes handled).
- Read with Regulations Article 22 (objections to tender documents at least 10 days before the deadline, answered within 3 days) - different periods, do not confuse.
Keywords
- 招标文件澄清
- 招标文件修改
- 十五日前
- 顺延投标截止时间
- tender submission deadline
- 实施条例第二十一条
- 招标投标法第二十三条
- 澄清修改通知