Time limits for objections in tendering: deadlines for objecting to prequalification/tender documents, the tenderer's 3-day reply duty and pre-reply suspension (Regulations Article 22), and objection as a precondition to complaints (Article 60)
Objections to tender documents shall be raised at least 10 days before the bid deadline; to prequalification documents, at least 2 days before the prequalification-application deadline; the tenderer shall reply within 3 days of receipt and suspend the proceedings until replying (Implementation Regulations Article 22). Complaints on Articles 22 (documents), 44 (opening), and 54 (results) require a prior objection to the tenderer; the objection-response period is excluded from the 10-day complaint period (Article 60).
Applicable Codes
- 中华人民共和国招标投标法实施条例(国务院令第709号,2019修订)第二十二条、第六十条
- 中华人民共和国招标投标法(2024修订)第二十三条
- https://fgw.lsz.gov.cn/fggz/zbtb/202404/t20240418_2665602.html
- https://fgw.jz.gov.cn/info/1056/1914.htm
Topic Positioning
The objection time-limit system under Implementation Regulations Articles 22 and 60 (Decree No. 709, 2019): statutory deadlines for potential bidders/interested parties to object to prequalification or tender documents, the tenderer's reply duty and pre-reply suspension duty, and the linkage of objection as the statutory precondition to complaints.
Core Conclusions
Article 22, original: "Potential bidders or other interested parties objecting to prequalification documents shall raise the objection at least 2 days before the prequalification-application deadline; objections to tender documents, at least 10 days before the bid submission deadline. The tenderer shall reply within 3 days of receiving the objection and shall suspend the tendering activities until replying." Three points: (1) Two deadlines: prequalification documents - 2 days before their application deadline; tender documents - 10 days before the bid deadline. In practice "10 days before" excludes the deadline day itself (i.e., by 24:00 of the 10th day prior); late objections carry no duty to reply, the objection remedy is lost, and only a harder complaint remains. (2) Reply duty: within 3 days of actual receipt (not dispatch). (3) Suspension: "shall suspend until replying" is mandatory - no opening or evaluation may proceed pending the written reply, else the procedure is defective. Article 60, original (complaint precondition): complaints may be filed within 10 days of knowing or should have known, with clear requests and evidence; for Articles 22/44/54 matters, a prior objection to the tenderer is required, and the objection-response period is excluded from the 10 days. Supporting rules:
- Objection is the statutory precondition for complaints on documents (22), opening (44), and results (54); response time does not consume the 10 days.
- Remedy upon sustained objection: the tenderer may clarify or amend the documents, but amendments possibly affecting bid preparation must be notified in writing at least 15 days before the deadline, extending it if short (Bidding Law Article 23, Regulations Article 21) - after objecting, watch the reply: amendments may move the deadline.
- Other objection windows differ: opening objections - raised on the spot and answered on the spot with records (44); result objections - during the winning-candidate publication (54).
- Version note: Article 22 is identical from Decree 613 (2011) through 709 (2019); the 2024-revised Bidding Law effective 2025-05-01 - per recent government citations (Liangshan and Jinzhou DRCs), the "10 days / 3 days / suspend before reply" wording remains cited as current; no official adjustment found; conclusions per the current text.
Applicable Boundaries
- Parties: potential bidders, bidders, other interested parties.
- Scope: objections to prequalification/tender documents; opening and result objections have different windows (on-the-spot / publication period).
- "10 days before"/"2 days before" run to the bid or application deadline; practice excludes the deadline day itself.
- Late objection does not forfeit all substantive rights (e.g., BOQ-defect risk allocation still per GB/T 50500-2024) but forfeits the statutory objection remedy.
- Covers procedural time limits and effects (suspension, precondition) only - not the merits of objections or the legality of document terms.
Further Reading
- Implementation Regulations (Decree No. 709, 2019) Articles 22 and 60; companion: Articles 21 (clarification/amendment notice), 23 (15-day written notice and extension), 44 (opening objections), 54 (result objections).
- Bidding Law (2024 revision, effective 2025-05-01) Article 23.
- Government citations verifying the texts: Liangshan DRC https://fgw.lsz.gov.cn/fggz/zbtb/202404/t20240418_2665602.html ; Jinzhou DRC https://fgw.jz.gov.cn/info/1056/1914.htm
Keywords
- Implementing Regulation of the Tendering and Bidding Law (State Council Decree No. 613)
- 第二十二条
- 异议时限
- 投标截止时间10日前
- 资格预审文件异议2日前
- 3日内答复
- 暂停招标投标活动
- 投诉前置程序
- 第六十条