Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

Re-examination of compilation errors in the tender price ceiling (renamed the maximum acceptable tender price in GB/T 50500-2024), bidder objections and complaint handling: the GB 50500-2013 route of '5-day complaint + order to rectify when the error exceeds +/-3%' versus the GB/T 50500-2024 Clauses 5.3.3 and 5.3.4 route of objection - referral - re-publication

GB 50500-2013: a bidder which, on re-check, considers that the tender price ceiling was not compiled in accordance with the code shall complain to the tendering and bidding supervision authority and the construction cost administration institution within 5 days after publication (Clause 5.3.1); where the re-examination result differs from the published price by more than +/-3%, the tenderer shall be ordered to rectify (Clause 5.3.8). GB/T 50500-2024 removes the fixed percentage and the fixed day count: where the re-examination conclusion deviates significantly from the published maximum acceptable tender price, the tenderer shall explain and revise (Clause 5.3.3); a bidder may object in writing to the tenderer within the prescribed time, and where the tenderer fails to correct it reasonably, the bidder may refer the matter to the administrative supervision and administration department, and the price must be re-published under that department's procedures (Clause 5.3.4).

Applicable Codes

  • GB/T 50500-2024 第5.1.2条
  • GB/T 50500-2024 第5.3.3条
  • GB/T 50500-2024 第5.3.4条
  • GB 50500-2013 第5.3.1条
  • GB 50500-2013 第5.3.8条
  • 《中华人民共和国招标投标法》第23条
  • 《中华人民共和国招标投标法实施条例》第22条

Positioning

At the tendering stage, the channels available when a bidder suspects compilation errors in the maximum acceptable tender price (the tender price ceiling under the 2013 edition nomenclature), the error criterion applied to re-examination conclusions, and the wholly different nature of 'price adjustment for BOQ errors' at settlement. Used to distinguish 'procedural remedy for a wrong ceiling' from 'price adjustment for BOQ errors'.

Core conclusions

1. GB 50500-2013 (repealed; kept for comparison with old contracts)

  • Clause 5.3.1: 'Where a bidder, on re-check, considers that the tender price ceiling published by the tenderer was not compiled in accordance with this code, it shall complain to the tendering and bidding supervision authority and the construction cost administration institution within 5 days after publication of the tender price ceiling.' Commentary: this clause gives bidders the right to complain about ceilings not compiled per the code, and requires the two authorities to shoulder and perform the duty of supervising and handling such conduct.
  • Clause 5.3.8: 'Where the re-examination result of the tender price ceiling differs from the published tender price ceiling by an error greater than +/-3%, the tenderer shall be ordered to rectify.'
  • Key points: the 2013 edition gives two hard indices - a 5-day complaint window (running from publication) and a +/-3% error threshold (exceeding which rectification is ordered) - and the complaint goes to the administrative supervision authorities (the tendering and bidding supervision authority plus the construction cost administration institution), not to the tenderer.

2. GB/T 50500-2024 (current)

  • Clause 5.3.3: 'Where the maximum acceptable tender price is re-examined by the relevant administrative supervision and administration department and the conclusion deviates significantly from the published maximum acceptable tender price, the tenderer shall give an explanation and revise the unreasonable content.' 'Where a bidder considers that the maximum acceptable tender price published by the tenderer was not compiled in accordance with the tender documents and the relevant state provisions, or that the compiled amount is unreasonable, the bidder may raise an objection in writing to the tenderer within the prescribed time. Where the tenderer fails to correct it reasonably, the bidder may refer the matter to the relevant administrative supervision and administration department, and the tenderer shall bear responsibility for having compiled otherwise than in accordance with the relevant provisions or for having compiled unreasonably.'
  • Clause 5.3.4: 'Where, according to the re-examination conclusion of the maximum acceptable tender price, the tenderer needs to revise and re-publish the maximum acceptable tender price, it shall re-publish it in accordance with the relevant requirements and procedures of the government competent department.'
  • Key points: the 2024 edition turns to 'qualitative + steps' - (1) first a written objection to the tenderer (within the prescribed time; the specific time limit is set by the tender documents or the competent department, and the standard no longer fixes 5 days); (2) where the tenderer fails to correct it reasonably, referral to the administrative supervision and administration department; (3) a 'significant' deviation between the re-examination conclusion and the published value triggers explanation and revision, and the fixed +/-3% percentage is deleted; (4) after revision, re-publication follows the government competent department's requirements and procedures.

3. The divide from BOQ errors and settlement objections (to avoid taking the wrong channel)

Matter Stage Channel Consequence
Unreasonable compilation of the maximum acceptable tender price Before the tender deadline Written objection -> referral to the administrative supervision department The tenderer explains, revises and re-publishes
Errors in the tender BOQ (unit-rate contract) Tendering through settlement Written request for clarification -> price adjusted at settlement per Section 8.2 Adjustment of the contract price
Contradiction between the tender documents and the drawings Tendering stage Objection to the tender documents: raised 10 days before the tender deadline, answered by the tenderer within 3 days (Article 22 of the Implementing Regulations of the Tendering and Bidding Law); clarifications or modifications to be notified in writing at least 15 days before the deadline (Article 23 of the Tendering and Bidding Law) Clarifications and modifications form part of the tender documents; the deadline is postponed where necessary
Objection to the settlement review outcome Final account Itemised written objection within the agreed objection period (28 days if none) -> re-check / negotiation / dispute review / arbitration or litigation The undisputed part is settled first

An objection to the ceiling produces no 'automatic adjustment of the ceiling', nor is it equivalent to a price adjustment for BOQ errors; losses caused by a wrong ceiling are handled under 'the tenderer shall bear responsibility for having compiled otherwise than in accordance with the relevant provisions or for having compiled unreasonably'.

Boundaries of application

  • The 5-day complaint window and the +/-3% error threshold of the 2013 edition apply only to tendered projects contracted before 1 September 2025 that adopt the 2013 edition; current projects follow GB/T 50500-2024, which no longer fixes a day count or a percentage - check the tender documents and the local competent department's rules for the specific time limits.
  • The channels above address the maximum acceptable tender price / tender price ceiling as a tendering-stage document; BOQ errors, variations and quantity-difference price adjustments during contract performance follow the contract price adjustment provisions and are outside this card.
  • GB/T 50500-2024 is a recommended national standard whose procedural provisions bind the parties once invoked by the tender documents; state-funded projects must set a maximum acceptable tender price, and its compilation and publication are further subject to the competent department's procedures.
  • Objections and complaints are procedural rights and do not affect the bidder's substantive right to claim price adjustment under the contract and the standard, but missing the procedural window may forfeit the chance to correct the ceiling.

Further reading

  • GB/T 50500-2024 Standard for pricing of bills of quantities for construction works: Clause 5.1.2 (the compiling party), Clauses 5.3.3 and 5.3.4 (re-examination, objection, re-publication).
  • GB 50500-2013 Code of valuation with bills of quantities for construction works: Clause 5.3.1 (5-day complaint), Clause 5.3.8 (+/-3% order to rectify); repealed, kept as an evolution comparison.
  • Tendering and Bidding Law of the PRC, Article 23 (clarifications or modifications to be notified in writing at least 15 days before the tender deadline); Implementing Regulations of the Tendering and Bidding Law, Article 22 (objections to the tender documents to be raised 10 days before the tender deadline, the tenderer to answer within 3 days, tendering activities suspended before the answer).