tender price ceiling
Concept Guide
Concept
A tender price ceiling is the maximum bid price that an Employer calculates on a bill of quantities pricing basis and publishes in the tender documents. It is not a negotiating reference figure but a binding ceiling: a tender priced above it is rejected at the evaluation stage and is not examined further.
Terminology. The institution was known under GB 50500-2013 as the tender control price (招标控制价) and has been renamed the maximum bid price / tender price ceiling (最高投标限价) from GB/T 50500-2024. Both names denote one and the same institution, and older documents using the earlier name should be read as referring to it.
Mechanism. First, preparation and publication are mandatory: for construction works financed by state funds the Employer must prepare the ceiling and must publish it in the tender documents; it may not be kept internal, and no minimum bid price may be set. Second, the device works in both directions — it prevents bids from exceeding the level the Employer can accept, discourages collusive bidding and artificial price inflation, and gives every tenderer a public, predictable pricing benchmark, reducing information asymmetry. Third, the basis of calculation has evolved: under the 2013 code it was cost quotas plus published price information (government guidance prices) at social-average levels; from the 2020 reform circular and GB/T 50500-2024 (in force 1 September 2025) it shifts to comparable-project ceiling and settlement data, competitive market rates, and market price information and indices, with transitional arrangements in some provinces. Taken at a socially average level of efficiency. It is therefore a price derived from public pricing infrastructure rather than the outcome of market enquiry or a cost-plus build-up.
Compared with the traditional confidential estimate, which was kept secret and used for reference only, with a bid above it not automatically invalid, the tender price ceiling is published and operates as a hard limit. The two instruments occupy different positions in the system and should not be treated as interchangeable.
FIDIC Mapping
FIDIC contract conditions contain no institution equivalent to the tender price ceiling. Under the 2017 Red Book and Yellow Book, the Employer commonly prepares an internal estimate (in practice often called the employer's estimate — not a term of the FIDIC Conditions), normally confidential, is not issued to tenderers and does not operate as a ceiling on bid prices — a bid above it is not thereby rendered invalid and serves only as a reference in tender analysis. Where the FIDIC commentary discusses the tender period (Red Book Sub-Clause 2.2, Tender Period), its concern is that adequate time be allowed for tenderers to obtain all necessary information as to risks, contingencies and other relevant circumstances; no price-limiting rule is imposed.
The substantive differences are three. (1) Pricing infrastructure: in China, cost quotas and government-issued published price information form a common basis of calculation, giving the ceiling comparability and verifiability; international tendering generally rests on market prices and the contractor's own cost data, so the Employer has no common benchmark from which to set a hard limit. (2) Decision-making body and procedure: in China the Employer sets and publishes the ceiling in advance, and it forms part of the tender documents; under FIDIC the reasonableness of prices is judged at evaluation, where the Employer or Engineer examines and may seek clarification on tenders, considers tenders invalid where warranted, and reviews abnormally low tenders case by case. (3) Timing of control: the Chinese model is an ex ante price limit, whereas FIDIC relies more on review during and after evaluation.
Usage note: when writing in English, use tender price ceiling and identify it as a China-specific institution; presenting it in a general international context would wrongly suggest that FIDIC or international tendering normally imposes a published bid ceiling.
| Chinese Term | English Term | FIDIC Term | Relation | Notes |
|---|---|---|---|---|
| 最高投标限价 | tender price ceiling | 无对应条款/术语(国际实践中 employer's estimate 为业主内部保密文件,非 FIDIC 合同条件术语) | absent | FIDIC 无公开投标限价制度:雇主估算通常保密且不构成报价上限。中国则强制编制并公布,以之否决超限投标,属计价基础设施驱动的行政性限价,两者性质不同。 |
| 否决投标 | rejection of a tender | rejection of tender (tender considered invalid) | adjacent | FIDIC 中否决投标发生在评标审查阶段,理由为投标未按期送达、未符合招标指示等;中国的否决事由包含明确量化门槛——报价超过最高投标限价,故为法定事由而非裁量判断。 |
| 异常低价投标审查 | review of abnormally low tenders | abnormally low tender | adjacent | 国际招标以个案审查异常低价投标控制报价合理性,属评标中的事中核查;中国则叠加事前统一限价与异常低价审查双重控制,控制时点与制度定位均不同。 |
Updated 2026-09-13
- 01
Re-examination of compilation errors in the tender price ceiling (renamed the maximum acceptable tender price in GB/T 50500-2024), bidder objections and complaint handling: the GB 50500-2013 route of '5-day complaint + order to rectify when the error exceeds +/-3%' versus the GB/T 50500-2024 Clauses 5.3.3 and 5.3.4 route of objection - referral - re-publication
GB 50500-2013: a bidder which, on re-check, considers that the tender pr…
GB/T 50500-2024 第5.1.2条GB/T 50500-2024 第5.3.3条GB/T 50500-2024 第5.3.4条2026-10-25 - 02
Labour cost pricing basis within the all-in unit rate: norm-based labour cost (base-period workday rate) versus current-period published labour price information and labour market prices, the applicable rules at the tender price ceiling and tender stages, and the test that the labour cost differential and the labour cost inside the all-in unit rate are not adjusted twice
Labour cost in the all-in unit rate = norm (budget) labour consumption x…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.9、3.1.6、3.3.5、5.2.1、5.2.4、5.2.8、6.1.1、6.1.3、6.2.1、8.6.3、8.7.1条,App. A.2.1、A.2.4GB/T 51095-2015 建设工程造价咨询规范 第5.3.9条、App. CTB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.1.1~3.1.5条、第4.1.1~4.1.2条2026-10-25 - 03
Judging the synonymy of the tender price ceiling and the maximum tender price ceiling, the rejection rule for tender offers above the ceiling, and the item-by-item comparison of the compilation bases of the three and the division of their roles in tender evaluation and contract price formation
The tender price ceiling (GB 50500-2013 Clause 2.0.45) and the maximum t…
GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第 2.0.45、2.0.46、5.1.1、5.1.4、5.1.6、5.2.1、6.1.5、6.2.1 条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 2.0.19、5.1.1、5.2.1、5.2.8、6.1.2、6.1.3、6.2.1 条《中华人民共和国招标投标法实施条例》(国务院令第 709 号,2019 修订)第二十七条、第五十条、第五十一条2026-10-25 - 04
Maximum bid price (former tender price ceiling) compilation framework and cost composition under GB/T 50500-2024
State-funded projects must set a maximum bid price (the former tender pr…
GB/T 50500-2024 建设工程工程量清单计价标准GB 50500-2013 建设工程工程量清单计价规范招标投标法实施条例 第27条2026-09-25 - 05
Preparing the subcontract control price and the subcontract target price: concept distinction, preparation bases, inversion check, and linking the two prices
The subcontract control price is the enterprise's internal maximum bid l…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50326-2017 建设工程项目管理规范T/ZBD 100.1-2022 建设工程造价数据建设通用标准2026-09-25 - 06
"Tender control price" and "tender price ceiling" are one and the same thing: term unification in GB/T 50500-2024 and the 2013→2024 changes in preparation requirements (basis of preparation, price sources, publication requirements, reasonable construction duration)
"Tender control price" and "tender price ceiling" are one and the same t…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.19条、第5.1.1条、第5.2.1条、第5.2.8条GB/T 50875-2013 工程造价术语标准 第3.3.1条https://zjt.jiangxi.gov.cn/jxszfhcxjst/wjtz/pc/content/content_2006185954536067072.html2026-09-25 - 07
Price-taking time point for the tender price ceiling: the latest issue of price information published as at the date of completion of preparation; "28 days before the tender deadline" is the adjustment base price time point, not the price-taking time point
The tender price ceiling (employer's maximum acceptable price) takes pri…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51290-2018 建设工程造价指标指数分类与测算标准GB/T 50875-2013 工程造价术语标准2026-09-25 - 08
Main contractor's attendance and coordination fee: bases to which percentage rates are applied and rates — calculation bases for the three service targets, the C = A × B pricing formula, construction payment settlement adjustment, and tender price ceiling estimation (GB/T 50500-2024)
Main contractor's attendance and coordination fee = calculation base A ×…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.17条、第3.2.9条、第5.2.6条、第8.5.4条、App. ETable E.4.5湖北省建筑安装工程费用定额(2024)「九、总承包服务费」「十、甲供材」https://zjw.beijing.gov.cn/bjjs/zwgk46/zcwj8/index.shtml2026-09-25 - 09
Price bases and setting procedure for the material procurement maximum price limit (internal control price / tender price ceiling)
The material maximum price limit = base price × (1 ± adjustment coeffici…
GB/T 50500-2024 建设工程工程量清单计价标准 第5.2.1/5.2.8/5.2.9条DB37/T 5096-2017 建设工程项目管理咨询规范 第6.5.1/6.5.2条DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范 第7.6.4条2026-09-25 - 10
GB/T 50500-2024, China's BOQ pricing standard: positioning, 2024-vs-2013 changes, chapter map and card-group navigation
GB/T 50500-2024, the China national pricing standard for BOQ-based prici…
GB/T 50500-2024 建设工程工程量清单计价标准(住建部公告 2024 年第 212 号;第1.0.1~1.0.3条、Ch. 8、App. A~G、前言)GB 50500-2013 建设工程工程量清单计价规范(已废止,对照)GB/T 50854-2024~GB/T 50862-2024 各专业工程量计算标准(配套计量体系)2026-09-25 - 11
Variance analysis between the construction-drawing based budget (pre-tender estimate) and the winning tender budget: a five-step method (total price → cost composition → item-by-item all-in unit rates → attribution → conclusions)
The two budgets share the same quantities (both measured per the tender…
GB/T 51095-2015 建设工程造价咨询规范GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准2026-09-25