Main contractor's attendance and coordination fee: bases to which percentage rates are applied and rates — calculation bases for the three service targets, the C = A × B pricing formula, construction payment settlement adjustment, and tender price ceiling estimation (GB/T 50500-2024)

Main contractor's attendance and coordination fee = calculation base A × rate B (or a lump sum entered directly under a total-price package). Bases for the three targets: (1) materials/works equipment provided by the employer (free-issue) -> supply contract price; (2) specialized subcontracted works (within the contract, not executed by the contractor) -> the subcontract's contract price; (3) directly awarded specialized works (outside the contract) -> that specialized works' contract price. The national standard sets only rules, not rates; where the fee is priced per item the risk is lumped and no adjustment is made in the construction payment settlement, while where it is priced by rate and no base is agreed, it may be adjusted in the construction payment settlement on the contract price. Local rate references (Hubei 2024 norms for on-costs and expenses): pure management and coordination 1.5%, with attendance services 3%–5%, employer-supplied (free-issue) materials 1% of value.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.17条、第3.2.9条、第5.2.6条、第8.5.4条、App. ETable E.4.5
  • 湖北省建筑安装工程费用定额(2024)「九、总承包服务费」「十、甲供材」
  • https://zjw.beijing.gov.cn/bjjs/zwgk46/zcwj8/index.shtml

Topic Positioning

How the main contractor's attendance and coordination fee is computed under GB/T 50500-2024, the China national pricing standard for BOQ: the bases to which percentage rates are applied (calculation base A) for each of the three service targets, the percentage-rate based pricing formula C = A × B versus the lump-sum mode, adjustment rules for the construction payment settlement, tender price ceiling estimation, and local rate reference values in the norms for on-costs and expenses. The delimitation of the chargeable scope is in the referenced card (card_f7f83e16).

Core Conclusions

  1. Three service targets and the bases to which rates are applied (2.0.17, 3.2.9): (1) Materials/works equipment provided by the employer (employer-supplied, free-issue materials): the fee shall include the main contractor's coordination of the supplier so as to meet the programme and construction progress of the overall main contract and to complete supply in due time, together with materials custody costs and profit — base to which the rate is applied = the supply contract price (value) of the employer-supplied materials. (2) Specialized subcontracted works (provisional-sum specialized works within the contract scope but not executed by the contractor): it shall include the main contractor's coordination of and attendance on the specialized subcontractor in meeting the programme and construction progress of the overall main contract, covering detailed design drawings, work faces, progress, etc., plus profit — base = the specialized subcontracted works' contract price (cost). (3) Directly awarded specialized works (outside the contract scope, awarded directly by the employer and not executed by the contractor): it shall include the main contractor's coordination of and attendance on the directly awarded specialized subcontractor in meeting the programme and construction progress of the overall main contract, covering work faces, progress, etc. — base = the directly awarded specialized works' contract price. The fee is a VAT-exclusive price for the corresponding billed (BOQ) items and shall include profit; specialized works and labour works subcontracted by the contractor itself shall not be charged (2.0.17).

  2. Pricing modes (Appendix E, Table E.4.5): where percentage-rate based pricing is adopted, the tender price ceiling and the tender (priced offer) record "calculation base A1" and "rate B", and the amount C1 = A1 × B; when the construction payment settlement is prepared, the settlement amount is calculated as C2 = A2 × B on the "confirmed calculation base A2". Where lump-sum (per-item) pricing is adopted, the amount is entered directly. The national standard prescribes the pricing rules only and gives no rate values; rates are quoted by tenderers on their own initiative in their tenders (the tender documents list the service contents).

  3. Construction payment settlement adjustment (8.5.4): where the fee is priced per item, apart from deductions or adjustments under 8.4.8, 8.5.1–8.5.3 and 8.5.5, it is a lumped risk item and shall not be adjusted in the construction payment settlement; where it is percentage-rate priced and the contract does not stipulate the base to which the rate is applied or the stipulation is unclear, the construction payment settlement may be calculated and adjusted using the contract prices of the specialized subcontracted works and the directly awarded specialized works, and the supply contract price of the employer-supplied materials.

  4. Tender price ceiling estimation (5.2.6): taking into account the building type, building scale, delivery standard of the tendered works and the contractor's responsibilities set out in the contract conditions, it is prepared by comparison with and correction against reasonable competitive market prices for similar projects — for building works, the total fee of comparable main-contractor attendance and coordination items is divided by the gross floor area (GFA) to give a rate per square metre; for road works, the total fee is divided by road length to give a rate per metre; for other works, the total fee is divided by the contract price of the work sections and items to give a percentage.

  5. Local rate references (Hubei Province norms for on-costs and expenses of construction and installation works 2024, Section 9 "Main contractor's attendance and coordination fee", worded "may be determined autonomously, or by reference to the following standards"): (1) where the employer requires only main-contractor management and coordination of the subcontracted specialized works, 1.5% of the cost of the subcontracted specialized works; (2) where management and coordination are required together with attendance services (including management, coordination and construction attendance for the subcontractor, amortisation of site water and power installations and pipeline laying, amortisation of shared scaffolding erection and dismantling, depreciation and maintenance of shared vertical transport and pressurisation equipment, etc.), 3%–5% of the cost of the subcontracted specialized works; (3) where the employer supplies materials and works equipment itself, 1% of the value of the employer-supplied materials and works equipment. Employer-supplied material prices are not included in the all-in unit rates or in the project cost; their custody and coordination is charged only within this fee.

Applicable Boundaries

Applies to employer–contractor arrangements priced on a bill of quantities basis; GB/T 50500-2024 is a recommended national standard, and once the contract is signed the contract governs. The national standard does not prescribe uniform rate values; the 1.5%, 3%–5% and 1% given in this card are reference values from the Hubei 2024 norms for on-costs and expenses and must not be applied directly across regions — the norms for on-costs and expenses in force at the project location and the tender documents govern. Not chargeable: specialized works and labour works subcontracted by the contractor itself; provisional-sum specialized works that the contractor itself wins and executes shall not be charged again (8.4.8). Employer-supplied material prices are not included in the all-in unit rates or in the project cost.

Further Reading

See GB/T 50500-2024, the China national pricing standard for BOQ: 2.0.17 (term for main contractor's attendance and coordination fee), 3.2.9 (composition and calculation of the three service targets), 5.2.6 (pricing of the bill of provisional sums and other charges for the tender price ceiling and similar-project estimation), 8.5.4 (adjustment of the contract price), Appendix E, Table E.4.5 (pricing table for the main contractor's attendance and coordination fee). Local rate reference: Hubei Province norms for on-costs and expenses of construction and installation works (2024), Sections 9 "Main contractor's attendance and coordination fee" and 10 "Employer-supplied materials". Beijing: no unified rate for this fee has been published by the municipal housing and construction commission; it is determined by the tender documents/contract and by market competition (verify under the policy documents section of the commission's website, https://zjw.beijing.gov.cn/bjjs/zwgk46/zcwj8/index.shtml).