Correspondence between the subcontract BOQ and the main contract BOQ: four-layer mapping of scope, BOQ elements, price, and fees

The subcontract BOQ is not built from scratch but the implementation-level refinement (projection) of the specialist-works portion of the main contract BOQ, and the two must be reconcilable item by item: (1) scope without overlap or omission; (2) the five elements (code/name/features/unit/calculation rules) consistent item by item, with codes reusable from the main contract; (3) on price, the specialist works provisional sum is wholly replaced by the tax-inclusive awarded price of the subcontract tender (material provisional sums are pre-tax prices — do not mix calibers); (4) measure costs are included in the subcontract total without double counting, the general contractor's service fee is listed separately on the main contractor side, and progress payments flow along the employer → main contractor → subcontractor chain.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB 50860-2013 构筑物工程工程量计算规范
  • GB/T 50358-2017 建设项目工程总承包管理规范
  • 建设部令第124号 房屋建筑和市政基础设施工程施工分包管理办法

Topic Positioning

This card covers how the subcontract BOQ corresponds to and connects with the main contract BOQ: the subcontract BOQ is not a separately compiled set but the implementation-level refinement (projection) of the specialist-works portion of the main contract BOQ, and the two must be reconcilable item by item.

Core Conclusions

Four-layer correspondence: (1) Scope correspondence — the subcontract BOQ exactly covers the specialist-works portion of the main contract BOQ, without overlap or omission, leaving no "responsibility vacuum items" (section/interface division follows the same principle). (2) BOQ element correspondence — the five elements of item code, item name, item features, unit of measurement, and quantity calculation rules are consistent item by item (GB 50860-2013 Clause 4.2.1 is a mandatory provision); the code is twelve digits, the first nine set per the appendix and digits ten to twelve per name and features, and the same tendered works must not have duplicate codes (Clause 4.2.2); the subcontract BOQ may reuse the main contract codes to keep the whole tendering-measurement-settlement process traceable. (3) Price correspondence — the portion listed in the main contract BOQ as a specialist works provisional sum is wholly replaced after the subcontract tender by the awarded tax-inclusive specialist subcontract price, adjusting the contract price; note that the specialist works provisional sum is a VAT-inclusive price while material provisional sums are pre-tax prices — do not mix the reconciliation calibers. (4) Fee correspondence — the measure costs of specialist subcontracted works are already included in the subcontract contract total and are not measured again; the general contractor's service fee (management, coordination, cooperation responsibilities and profit) is collected in the main contractor's other-items list and is no longer contained in the subcontract price; progress payments are paid along the employer → general contractor → subcontractor chain with synchronized verification.

Applicable Boundaries

Applies to general contracting - specialist subcontracting scenarios of building and municipal infrastructure works priced by bills of quantities; subcontract contracts should be brought into the overall contract management scope of the main contract and kept consistent (GB/T 50358-2017, Clause 16.3.1). Provisional-sum replacement is limited to specialist works subject to mandatory tendering by law (scale standards per NDRC Order No. 16); labor subcontracting involves no provisional-sum replacement mechanism and is outside the price correspondence of this card. Where the contract provides otherwise, its provisions prevail.

Further Reading

GB/T 50500-2024 Clause 8.4.1 (provisional sum replacement), Clause 7.3.2 (no double counting of measure costs), Clause 3.2.9 (composition of the general contractor's service fee), Clause 9.1.13 (progress payment chain), Clause 10.2.6 (proportional method for service fees in process settlement); GB 50860-2013 Clauses 4.2.1, 4.2.2 (mandatory BOQ element and coding provisions); GB/T 50358-2017 Clause 16.3.1; Ministry of Construction Order No. 124 Article 5 (subcontract definition), Article 13 (prohibition of transfer of work).