provisional sum for nominated specialist subcontract works
- 01
Provisional prices (materials / specialist works): the settlement adjustment procedure of replacing the provisional price with the actual confirmed price - legal position, the submission-checking-review-re-examination-confirmation chain and deemed approval on expiry, the two confirmation routes (compulsory tendering and otherwise), adjusting only the pre-tax material price, the deduction direction when the confirmed price is lower, the boundary against material price adjustment, and the clause mapping of GB/T 50500-2024 against GB 50500-2013
The final account replaces the provisional price with the 'confirmed pri…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.14、3.2.3、3.3.5、6.2.5、8.1.2~8.1.6、8.4.1~8.4.8、8.5.3、8.7.2~8.7.5、8.10、9.4.6、10.3.2条及App. A、App. G.2GB 50500-2013 建设工程工程量清单计价规范 第5.2.5、6.2.5、9.9.1~9.9.4条中华人民共和国招标投标法实施条例(2018修订)第二十九条2026-10-25 - 02
The VAT charging base of the bill of quantities and the non-duplication of tax on provisional sums for specialist works (GB/T 50500-2024 clauses 3.2.11 and 3.1.6)
VAT = [work-item list + preliminaries list + other-items list (less the…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 3.1.6 条、第 3.2.11 条及条文说明2026-10-18 - 03
GB/T 50500-2024 VAT pricing basis: all-in unit rates are fully inclusive prices excluding VAT, with VAT listed and assessed separately
BOQ item all-in unit rates and their totals are fully inclusive prices e…
GB/T 50500-2024 建设工程工程量清单计价标准 第3.1.6条、第3.2.11条GB/T 50875-2013 工程造价术语标准 第2.2.58条2026-09-25 - 04
Pricing rules for prime-sum estimates (provisional sums) of specialist works: GB/T 50500-2024 VAT-inclusive, lump-sum per item, deduction from the VAT base, and substitution on adjustment (compared with GB 50500-2013)
GB/T 50500-2024 defines the prime-sum estimate of specialist works as "s…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works (第2.0.15、3.1.6、3.2.7、3.2.11、8.4.1、8.4.7条)GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works (第4.4、5.2.5、9.9节,已废止)住房城乡建设部公告2024年第212号2026-09-25 - 05
GB/T 50500-2024 comparison of specialist-work provisional amounts (VAT-inclusive) and material provisional prices (VAT-exclusive): listing, taxation, and adjustment rules
Under GB/T 50500-2024 "Standard for BOQ pricing of construction works"…
GB/T 50500-2024 建设工程工程量清单计价标准(第2.0.14、2.0.15、3.1.6、3.2.11、6.2.5、8.4.1、8.4.6、8.4.7、8.10节,App. ETable E.1.1、Table E.2.3、Table E.4.3)2026-09-25 - 06
Correspondence between the subcontract BOQ and the main contract BOQ: four-layer mapping of scope, BOQ elements, price, and fees
The subcontract BOQ is not built from scratch but the implementation-lev…
GB/T 50500-2024 建设工程工程量清单计价标准GB 50860-2013 构筑物工程工程量计算规范GB/T 50358-2017 建设项目工程总承包管理规范2026-09-25 - 07
Determining re-tendering of provisional-sum specialty works, organization modes, and tax-inclusive price confirmation rules (Implementation Regulations Article 29 + GB/T 50500-2024 Section 8.4)
Specialty works included in the general-contract scope as provisional su…
招标投标法实施条例(2018修订)第二十九条GB/T 50500-2024 建设工程工程量清单计价标准 第8.4节必须招标的工程项目规定(发改委16号令)第五条2026-09-25 - 08
Old-vs-new rules on the advance payment ratio: GB/T 50500-2024 Clauses 9.2.2/9.2.3 vs GB 50500-2013 Clause 10.1.2 — the 10%–30% band and changed deduction bases
The 10%–30% payment band is retained in GB/T 50500-2024 but the deductio…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 9.2.2 条、第 9.2.3 条GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第 10.1.2 条(已废止)2026-09-25 - 09
Provisional sums at final account: settlement line item, replacement paths, VAT basis and review essentials (GB/T 50500-2024)
At final account, provisional sums are dealt with as "the actually deter…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准T/ZBD 100.5-2023 建设工程结算审核作业指引2026-09-25