Provisional prices (materials / specialist works): the settlement adjustment procedure of replacing the provisional price with the actual confirmed price - legal position, the submission-checking-review-re-examination-confirmation chain and deemed approval on expiry, the two confirmation routes (compulsory tendering and otherwise), adjusting only the pre-tax material price, the deduction direction when the confirmed price is lower, the boundary against material price adjustment, and the clause mapping of GB/T 50500-2024 against GB 50500-2013

The final account replaces the provisional price with the 'confirmed price' (the tender-winning pre-tax price, or the tax-inclusive tender-winning specialist subcontract price, for items that must be tendered by law; or the pre-tax price from market enquiry or the contractor's own quotation confirmed by the employer for items outside compulsory tendering); published price information is not a basis for settlement adjustment (it only guides the provisional unit rate when compiling the tender price ceiling, or serves as the adjustment baseline where the contract makes that material price-adjustable); the procedure runs under GB/T 50500-2024 clauses 8.1.2 to 8.1.6 - submission, checking, review, re-examination and confirmation - and failure to confirm or comment within the time limit is deemed approval; the adjustment replaces only the material provisional price inside the all-in unit rate (pre-tax); labour, plant, overheads and profit do not move (clause 8.4.6), VAT being charged on the difference; where the confirmed price is below the provisional price the adjustment runs the same way down, deducted from the current progress payment or interim settlement by construction stage, and the final account lists 'provisional price adjustment amounts' separately; BOQ items carrying material provisional prices are outside the material cost adjustment of clauses 8.7.2 to 8.7.4 (clause 8.7.5). The 2013 counterparts are clauses 9.9.1 to 9.9.4.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.14、3.2.3、3.3.5、6.2.5、8.1.2~8.1.6、8.4.1~8.4.8、8.5.3、8.7.2~8.7.5、8.10、9.4.6、10.3.2条及App. A、App. G.2
  • GB 50500-2013 建设工程工程量清单计价规范 第5.2.5、6.2.5、9.9.1~9.9.4条
  • 中华人民共和国招标投标法实施条例(2018修订)第二十九条
  • GF-2017-0201 建设工程施工合同(示范文本)第10.7款

What this card covers

This card answers 'when the confirmed price of a provisional price differs from the published price information or the market price, by what procedure the settlement is adjusted': the legal position of provisional prices, the confirmation chain and deemed approval on expiry, the two confirmation routes (compulsory tendering versus otherwise), the scope of the difference adjustment (whether overheads and profit follow), the deduction direction when the confirmed price is below the provisional price, and the boundary between provisional price adjustment and material price adjustment, with a clause mapping of GB/T 50500-2024 against GB 50500-2013.

Core conclusions

1. Legal position: a sum provisionally estimated at tender because the price cannot be fixed - not the contractor's offer.

Article 29 of the Implementation Regulations of the Tendering and Bidding Law of the People's Republic of China (2018 revision): 'The tendering employer may, in accordance with law, tender the works and the goods and services relating to the works as a whole or in part on a main-contract basis. Works, goods and services included within the main-contract scope in the form of provisional prices, which fall within the scope of projects subject to tendering by law and reach the scale standards prescribed by the state, shall be tendered in accordance with law. The provisional prices in the preceding paragraph mean the sums of works, goods and services that the tendering employer provisionally estimates in the tender documents because their prices cannot be determined at the time of main-contract tendering.'

GB/T 50500-2024 clause 2.0.14, term 'material provisional price' (given in the standard as 'material prime cost rate'): 'the VAT-exclusive material price, estimated in the bill of quantities by the employer for materials that the design drawings require to be used but whose standard, specification or price cannot be determined at tender, on an arrival-at-site basis. The materials covered include works equipment.'

Not to be altered at tendering: 2013 clause 6.2.5: 'Provisional prices shall not be altered or changed. Materials and works equipment within provisional prices must be taken into the all-in unit rate at the provisional unit rates; provisional prices for specialist works must be entered at the amounts listed in the bill of other items.' The 2024 clause 6.2.5 changes this to taking the provisional unit rates stated in the BOQ (VAT-exclusive) into the all-in unit rate, listed in Table E.2.3 'material provisional unit rates and adjustment'; clause 3.2.3: 'The material price within the all-in unit rate of BOQ items carrying material provisional prices shall be taken at the pre-tax material provisional price given in the tender BOQ.' Key fork: the material provisional price is a pre-tax price (VAT-exclusive); the specialist-work provisional price is a tax-inclusive price (VAT-inclusive) - the two bases must not be crossed in replacement.

2. The role of published price information: a reference for the compilation stage and a baseline for adjustment only - not a basis for settlement. 2013 clause 5.2.5 (tender price ceiling): 'The unit rates of materials within provisional prices shall be determined from the construction cost information published by the government cost administration agencies or by reference to market prices' - a pricing reference at the stage where the tendering employer sets the provisional unit rates in the BOQ. At settlement, only the actual confirmed price can replace the provisional price; published price information or market prices must not be used to back-calculate directly. Only where the contract separately makes the material price-adjustable, with published price information as the baseline, does the route of adjustment for changes in costs open - a separate mechanism operating 'after the provisional price has been replaced'.

3. The confirmation chain: submission -> checking -> review -> re-examination -> confirmation; no reply in time is deemed approval. GB/T 50500-2024 clause 8.1.2: 'Where a contract price adjustment matter arises during performance, the contractor shall calculate the quantities of the adjustment matter under Chapter 7 of this standard, calculate the price adjustment under Sections 8.2 to 8.11, and submit it to the employer for checking within the agreed time together with the supporting records. The parties may handle contract price adjustment matters by the procedure of submission, checking, review, re-examination and confirmation.' Clause 8.1.3: 'Having received the contractor's contract price adjustment report and records, the employer shall verify it within the agreed time; if it confirms, it shall notify the contractor in writing; if it does not confirm, it shall reply in writing with its checking comments; if it neither confirms nor comments, the report submitted by the contractor is deemed accepted by the employer.' Clause 8.1.4: 'Where the employer raises checking comments, the contractor shall review them within the agreed time of receipt; if it accepts them, it shall notify the employer in writing; if not, it shall reply in writing with its review comments; if it neither confirms nor comments, the employer's comments are deemed accepted by the contractor.' Clause 8.1.6: 'The parties shall sign the measurement and pricing documents of the confirmed contract price adjustment, as the basis for payment of contract prices under Chapters 9 and 10 of this standard. Contract prices added (deducted) upon confirmed adjustment shall be paid together with the progress payment and the interim settlement by construction stage.' - the adjustment is not held to the final account but paid or deducted in the current progress payment / interim settlement (clause 9.4.6: adjustment amounts calculated under Chapter 8 and confirmed by both parties are included in the cumulative progress payments of the period). At implementation level, clause 10.7 of GF-2017-0201 (Model Construction Contract) offers a timing template: for items subject to tendering by law with the contractor as tendering party, the tendering plan goes to the employer for review through the supervising engineer 14 days in advance, and the employer approves or comments within 7 days; tender documents go for approval 14 days in advance, approval within 7 days; before signing a provisional-price contract, the winning-candidate particulars go across 7 days in advance and the winner is jointly fixed within 3 days of the employer's receipt, with a contract copy filed within 7 days of signature. For items outside compulsory tendering, the contractor applies in writing 28 days before signing the purchase / subcontract; the supervising engineer forwards within 3 days, the employer approves within 14 days, and failure to approve or comment in time is deemed consent.

4. Two confirmation routes (a procedural split).

(a) Within compulsory tendering - the tender result replaces the provisional price. Clause 8.4.1: 'Where materials and / or specialist works given provisional prices in the BOQ are subject to tendering by law, the pre-tax tender-winning price of the materials and / or the tax-inclusive specialist subcontract price so determined shall replace the provisional price and adjust the contract price. The material provisional price is a pre-tax unit rate (VAT-exclusive); the specialist-work provisional price is a tax-inclusive price (VAT-inclusive). The replacement follows: (1) the material provisional price is replaced by the pre-tax tender-winning purchase price; (2) the specialist subcontract is replaced by the tax-inclusive tender-winning price.' Tendering organisation and cost-bearing by party: clause 8.4.2 - where the employer is the tendering party, it bears the costs of organising the tendering, and any cooperation needed from the contractor is at the contractor's own cost; clause 8.4.3 - where the contractor is the tendering party, it bears the organising costs, 'which shall be deemed included in the contractor's tender total (contract price)', and any cooperation needed from the employer is at the employer's own cost; clause 8.4.4 - where both tender jointly, 'each party bears its corresponding costs'. Clause 8.4.8: 'Where the contractor tenders for a provisional-price specialist work let by the employer and wins, the main contractor's attendance and coordination provisions for that work shall be deducted under clause 8.5.3 of this standard.' 'A provisional-price specialist work won and carried out by the contractor shall not charge the main contractor's attendance and coordination provisions again.'

(b) Outside compulsory tendering - enquiry / own quotation confirmed, or joint enquiry, or joint tendering. Materials (clause 8.4.5): 'Where materials given provisional prices in the BOQ are not subject to tendering by law, the contractor may enquire in the market or quote on its own and, once the employer confirms the price, replace the provisional price at the pre-tax price; or the parties may enquire jointly, confirm the price and replace the provisional price at the pre-tax price, computing the resulting change in VAT and adjusting the contract price.' Specialist works (clause 8.4.7): 'Where specialist works given provisional prices in the BOQ are not subject to tendering by law, the VAT-inclusive specialist price may be determined under Section 8.10 of this standard and replace the provisional price; or the parties may jointly tender, determine the VAT-inclusive specialist subcontract price and replace the provisional price, adjusting the contract price.'

5. Scope of the difference: only the pre-tax material price moves; overheads and profit do not follow. Clause 8.4.6: 'The price adjustment of BOQ items carrying material provisional prices shall adjust only the material provisional price within the all-in unit rate; the other costs in the all-in unit rate of that item should preferably not be adjusted; the adjusted contract unit rate may be used for the pricing of BOQ errors, provisional sums and variations under Sections 8.2, 8.3 and 8.9 of this standard.' Clauses 8.4.5 and 8.4.7 likewise require 'computing the resulting change in VAT'. Hence: material provisional price difference = (confirmed pre-tax unit rate - provisional pre-tax unit rate) x quantity; only the material provisional price item inside the all-in unit rate is replaced, labour, plant, overheads and profit standing; VAT is charged on the difference (consistent with clause 3.3.5: price difference adjustments of labour, materials and fuel and power within the all-in unit rate carry VAT but no overheads or profit). The specialist-work provisional price is tax-inclusive and is replaced wholesale by the winning / confirmed tax-inclusive subcontract price, with no separate VAT. Overheads and profit were allowed as risk money at tendering and do not move when the provisional price is fixed.

6. Confirmed price below the provisional price: adjust down the same way, deduct in the current progress payment. The direction is opposite to a rise but the path is the same - a contract price adjustment 'added (deducted)' is, under clause 8.1.6, 'paid or deducted with the current progress payment and interim settlement by construction stage', not held to a one-off write-down at the final account. At the final account, clause 10.3.2 lists it separately: item 4, 'provisional price adjustment amounts: 1) material provisional price adjustment amounts; 2) specialist-work provisional price adjustment amounts (for main-contract contracts)', listed apart from the provisional sums adjustment amount (item 3), the attendance and coordination provisions adjustment amount (item 5) and the changes-in-costs adjustment amount (item 7); no netting across them.

7. The boundary against material price adjustment (adjustment for fluctuation). Clause 8.7.5: 'The material cost adjustment of clauses 8.7.2 to 8.7.4 of this standard should not be applied to BOQ items of employer-supplied materials or items carrying material provisional prices. Items of employer-supplied materials may be adjusted by the employer per actual changes, outside the contract total; items carrying material provisional prices follow Section 8.4 of this standard.' Clause 3.3.5 routes adjustment for cost fluctuation through Annex A.1 (index-based adjustment) or A.2 (adjustment based on published price information), fixes the adjustable scope at labour, key materials and fuel and power for plant, and lets the difference carry VAT but no overheads or profit. The test: a provisional price is a sum not yet priced at tender; once confirmed it is replaced once and for all, and later fluctuation is not adjusted again; adjustment for fluctuation concerns materials already priced, adjusted within the band rules (the band agreed in the contract, or exceeding 5% under clause 8.7.2 absent or unclear agreement) on the excess only. The two must not be stacked on the same material.

8. Clause mapping: GB 50500-2013 vs GB/T 50500-2024.

Matter GB 50500-2013 GB/T 50500-2024
Legal basis Article 29 of the Implementation Regulations of the Tendering and Bidding Law same
Materials and works equipment subject to tendering by law: replacement by tender price clause 9.9.1 clause 8.4.1 (fixes the two bases: pre-tax for materials, tax-inclusive for specialist works)
Materials outside compulsory tendering: contractor purchases, employer confirms unit rate, replacement clause 9.9.2 clause 8.4.5 (adds the joint-enquiry route + computing the VAT change; adjusts only the pre-tax material provisional price)
Specialist works outside compulsory tendering: price determined, then replacement clause 9.9.3 clause 8.4.7 (VAT-inclusive specialist price under Section 8.10, or joint tendering)
Tendering organisation, costs and selection for compulsory-tendering specialist works clause 9.9.4 (where the contractor does not tender, it tenders and its costs are deemed included in the contract price; where it tenders, the employer tenders and bears the costs, and on equal terms the contractor wins preferentially) clauses 8.4.2, 8.4.3, 8.4.4 (costs split by employer / contractor / joint tendering; the 'preferential award to the contractor' wording is dropped) + clause 8.4.8 (no attendance and coordination provisions where the contractor wins)
Only the material provisional price in the all-in unit rate adjusts, other costs do not no explicit counterpart clause 8.4.6
Material provisional price items outside material cost adjustment no explicit clause clause 8.7.5
Tender takes provisional unit rates into the all-in unit rate clause 6.2.5 (provisional prices shall not be altered) clauses 6.2.5 and 3.2.3 (fixes pre-tax)
Pricing reference for provisional unit rates at compilation clause 5.2.5 (published price information or market price) none
Final account listing none clause 10.3.2 item 4 'provisional price adjustment amounts'

Note: GB 50500-2013 has been superseded by GB/T 50500-2024; newly signed contracts follow the 2024 edition, the contract signature date being the test in application.

Applicable boundaries

  • Agreed terms prevail: where the particular conditions agreed otherwise on the confirmation mode, approval time limits or cost bearing, those terms govern (clause 10.7 of GF-2017-0201 models several options); the time limits in the standard and the model text (14 / 7 / 3 / 28 days) are reference values - the contract governs, and absent agreement they may be applied by reference.
  • The bases must not be crossed: the material provisional price is a pre-tax unit rate (may include works equipment); the specialist-work provisional price is a tax-inclusive total; materials adjust by unit-rate difference, specialist works replace wholesale at the tax-inclusive price - mixing them double-counts or omits VAT.
  • Clause 8.7.5 says 'should not', not an absolute bar: where the contract expressly brings material provisional price items into the adjustable-material scope with adjustment rules agreed, the contract governs; but in practice this easily double-counts against the replacement rules of Section 8.4, and the contract should state their order and mutual exclusion.
  • Not for employer-supplied (free-issue) material items: these adjust per actual changes outside the contract total and do not go through provisional price confirmation.
  • This procedure is the general procedure for 'contract price adjustment matters' (Section 8.1) and likewise covers BOQ errors, variations, provisional sums, claims and other adjustment matters; objections and remedies at final account review are a separate procedure.

Further reading

Clauses: GB/T 50500-2024 (standard for BOQ pricing of construction works) clause 2.0.14 (term: material provisional price), clauses 3.2.3, 6.2.5 (tender pricing), 8.1.2 to 8.1.6 (adjustment procedure), 8.4.1 to 8.4.8 (provisional prices), 8.5.3 (deduction of attendance and coordination provisions), 8.7.2 to 8.7.5 (material cost adjustment and the provisional price boundary), Section 8.10 (pricing of specialist works), clause 9.4.6 (progress payment includes adjustment amounts), clause 10.3.2 (final account listing), clause 3.3.5 and Annexes A.1 / A.2 (adjustment for changes in costs); GB 50500-2013 clauses 5.2.5, 6.2.5, 9.9.1 to 9.9.4; Article 29 of the Implementation Regulations of the Tendering and Bidding Law (2018 revision); GF-2017-0201 Model Construction Contract, clause 10.7 (confirmation and approval time limits for provisional price items). Extensions: how material and specialist-work provisional prices feed the main contractor's attendance and coordination provisions and the VAT base; how a confirmed provisional price links to the variation rate rules (Section 8.9).

Keywords