Provisional sums at final account: settlement line item, replacement paths, VAT basis and review essentials (GB/T 50500-2024)

At final account, provisional sums are dealt with as "the actually determined price replaces the provisional price, with the contract price adjusted by the difference": PC sums for materials (pre-tax) are replaced by the pre-tax winning bid price or by the pre-tax price from an inquiry/self-quotation confirmed by the employer, adjusting only the PC sum item for materials within the all-in unit rate, with all other cost elements unchanged; provisional sums for nominated specialist subcontract works (tax-inclusive) are replaced in their entirety by the winning tax-inclusive subcontract price. These enter settlement line item 4, "adjustment of provisional prices after procurement"; provisional sums for nominated specialist subcontract works do not enter the VAT calculation base; the core vouchers are the price-confirmation sheet (employer's approval of material prices) / letter of acceptance confirmed by both parties.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 50875-2013 工程造价术语标准
  • T/ZBD 100.5-2023 建设工程结算审核作业指引

Topic Positioning

This card covers the complete chain for provisional sums (materials/engineering equipment/nominated specialist works) at final account: the settlement line item, the two replacement-price paths, the adjustment-scope limits, the VAT summary basis, and review practice — and distinguishes provisional sums for specified materials/nominated works from provisional sums.

Core Conclusions

The core principle is "the actually determined price replaces the provisional price, with the contract price adjusted by the difference" (GB/T 50500-2024, Section 8.4), entering settlement price line item 4, "adjustment of provisional prices after procurement" (Clause 10.3.2, subdivided into adjustments for PC sums for materials and for provisional sums for nominated specialist subcontract works, the latter applying to main (general) contracting contracts). Two replacement paths: (1) where tendering is legally compulsory — materials are replaced by the pre-tax winning purchase price, nominated specialist works by the winning tax-inclusive subcontract price (8.4.1); (2) where tendering is not compulsory — materials by the contractor's inquiry/self-quotation pre-tax price confirmed by the employer; nominated specialist works by the tax-inclusive price determined per Section 8.10 or by joint tendering (8.4.5, 8.4.7). Adjustment-scope limits: PC sums for materials adjust only the PC sum item for materials (pre-tax) within the all-in unit rate; labour, machinery, management fee, profit and other cost elements are not adjusted (8.4.6). VAT basis: provisional sums for nominated specialist subcontract works are tax-inclusive and are excluded from the VAT calculation base when summarising (Appendix E.6.1). Review practice: re-measurable (unit-rate) contracts adjust by the price confirmed by both parties in accordance with the contract price-adjustment principles; lump-sum contracts verify the price-confirmation sheets for provisional materials and adjust per the agreed method (T/ZBD 100.5-2023, Clauses 3.1.5, 3.1.6). Unlike provisional sums: provisional sum items necessarily occur, with only the price tentative; provisional sums may not occur, and the unused portion is deducted from the contract price at final account.

Applicable Boundaries

Applies to the final account of works priced on a bill of quantities basis. PC sums for materials (including engineering equipment) are tax-exclusive pre-tax prices; provisional sums for nominated specialist subcontract works are tax-inclusive — the two bases must not be mixed. Price adjustment is capped by Clause 8.4.6 — management fee and profit are not recomputed on the difference; express contractual agreements govern. Absent vouchers (price-confirmation sheets, letters of acceptance, or employer confirmations), the final account takes the original provisional price and the difference is not supported.

Further Reading

See GB/T 50500-2024, Clause 10.3.2 (settlement line items), Clauses 8.4.1/8.4.5/8.4.6/8.4.7 (replacement and adjustment scope), Appendix E.6.1 (settlement summary and VAT base); terms: GB/T 50875-2013, Clause 2.2.60 (provisional sum for specified materials/nominated works), GB/T 50500-2024, Clause 2.0.13 (provisional sums); review practice: T/ZBD 100.5-2023, Clauses 3.1.5, 3.1.6; difference computation and tax adjustment details in the cited cards.