provisional sums
Concept Guide
Concept
A provisional sum is an allowance which the Employer states in the bill of quantities and carries within the Contract Price for work that cannot be defined at the time of contracting: possible variations, additional work, the purchase of particular equipment or materials, or additional services. It is a reserve held by the Employer, not an entitlement earned by the Contractor.
Key mechanics: the right to use the allowance rests with the Employer. In Chinese practice the Employer decides whether and when to call it up, normally after review by the supervising engineer, and issues the instruction by way of a variation or a signed record; valuation follows the agreed rules for valuation of variations, or is carried out as dayworks supported by certified dayworks records. At settlement the allowance is closed out against actual expenditure. Any unused balance does not automatically accrue to the Contractor; how it is dealt with is a matter of contract, most commonly by deducting it from the Contract Price. The Contractor bears no price risk on the unused portion and is paid only for work actually instructed.
Related mechanisms: provisional sums sit alongside the provisional sum for specified materials / nominated works in the bill of quantities. The latter covers items that will certainly be required but whose price is not yet fixed, whereas provisional sums cover items whose occurrence is itself uncertain.
FIDIC Mapping
| Chinese term | FIDIC term | Relation | Key point |
|---|---|---|---|
| 暂列金额 | Provisional Sums | adjacent | Both are a reserve within the Contract Price, but use requires the Engineer's instruction (FIDIC) vs the Employer's own decision (China) |
| 暂估价 | provisional sum for specified materials / nominated works | adjacent | The price is open, but the work will certainly be executed |
| 计日工 | dayworks | identical | Valued by the labour, materials and plant actually used |
| 工程量清单 | bill of quantities (BOQ) | adjacent | The provisional sum is listed as a separate item in the BOQ |
Points of difference: the terminology corresponds directly, yet the mechanism diverges on the right of use. Under FIDIC each Provisional Sum shall only be used, in whole or in part, in accordance with the Engineer's instructions, with the Contract Price adjusted accordingly, and payment covers only the work, supplies or services the Engineer has instructed. In Chinese practice the Employer exercises that discretion itself and approves the call-up through its own procedure, while the destination of any balance is governed by the contract. The cause is institutional: FIDIC places the Engineer at the centre of contract administration, so the mechanism runs along an instruction-and-adjustment chain, whereas the Chinese BOQ-based system places the Employer at the centre and settles on an actual-expenditure basis.
Usage warning: when reading a FIDIC contract, do not treat a provisional sum as a discretionary budget line the Contractor may commit on its own — without the Engineer's instruction no part of it may be used and no payment arises.
| Chinese Term | English Term | FIDIC Term | Relation | Notes |
|---|---|---|---|---|
| 暂列金额 | provisional sums | Provisional Sums (Sub-Clause 13.4;定义见红皮书 1.1.67/黄皮书 1.1.68) | adjacent | 同为合同价款内的预设备用金;但 FIDIC 由工程师指示动用并相应调整合同价格,中国由发包人自主使用、余额归属按合同约定处理。 |
| 暂估价 | provisional sum for specified materials / nominated works | Provisional Sums for specified materials or nominated works | adjacent | 暂估价针对价格待定但必然发生的材料、设备或专业工程,暂列金额针对是否发生尚不确定的工作,二者动用条件不同。 |
| 计日工 | dayworks | Dayworks | identical | 均按实际投入的工时、材料与设备计量计价,作为动用待定款项时的一种计价方式。 |
| 工程量清单 | bill of quantities (BOQ) | Bill of Quantities | adjacent | 暂列金额在中国以清单单列项出现;FIDIC 红皮书通常将其列入工程量清单(评注明示 the amount is included in the Bill of Quantities),黄皮书语境则随合同 Schedules/Employer's Requirements 界定每笔用途与范围——载体不是 Specification(规范)。 |
Updated 2026-09-13
- 01
Dividing preliminaries liability when site conditions change: site conditions contemplated at tender as lump-sum risk versus employer-changed sites during construction adjusting through variation and claims
GB/T 50500-2024 clause 3.3.7 draws the line: the preliminaries scheme bi…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.3.7条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.2.5条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.3.4条2026-10-25 - 02
Cost items expressly excluded from the all-in unit rate in BOQ-based pricing (VAT, statutory levies and fees, main contractor's attendance and coordination provisions, provisional sums, employer-borne costs, statutory safety provisions), the correct billing position of each, and audit identification of mixed allocation
Under GB/T 50500-2024 Clause 2.0.9 the all-in unit rate 'includes labour…
GB/T 50500-2024 第 2.0.9、2.0.13、2.0.17 条GB/T 50500-2024 第 3.1.6、3.2.2、3.2.4、3.2.5、3.2.9、3.2.11、3.6.1、3.7.4 条GB/T 50500-2024 第 4.2.6 条、第 6.2.4 条、第 8.3.1 条、App. E Table E.4.5、App. G.1 Table G.1.12026-10-25 - 03
Completion-settlement treatment of provisional sums: incurred amounts entered per actuals, unused amounts wholly deducted (GB/T 50500-2024, Section 8.3)
The provisional sum is controlled by the employer and used on the employ…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.13条(暂列金额术语)GB/T 50500-2024 第8.3.1条(发包人掌握、未使用归发包人)GB/T 50500-2024 第8.3.5条(未发生事件全额扣除、按实际完成计算)2026-10-25 - 04
Boundary distinctions among omitted BOQ items (BOQ errors), provisional prices, provisional sums, dayworks and site instruction records in contract price adjustment: required but not listed vs listed but unpriced vs confirmation evidence for unforeseen matters
Under GB/T 50500-2024: omission falls under 'BOQ errors' (clause 2.0.27…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.27、7.2.1、8.2、8.3.1、8.3.2、8.3.5、8.4.1、8.4.5、8.4.7、8.6.1、8.6.5、8.9、10.3.2、12.2.1条GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.9、5.9.1、5.9.2条GB/T 50875-2013 · Standard glossary of project costs 第3.4.8条2026-10-25 - 05
Pricing channels for works outside the contract scope and unforeseen works: recognising and pricing additional works, when dayworks apply, and the rules for using provisional sums
Where the contractor, at the employer's request, completes additional wo…
GB/T 50500-2024 建设工程工程量清单计价标准 第8.10.1条GB/T 50500-2024 第7.5.2条GB/T 50500-2024 第8.3.2条2026-09-26 - 06
Charging the cost of fine-decoration show flats (model rooms): classifying by nature to determine the cost-attribution path (process → measure costs / delivery → divisional works / display → other-item costs or separate award)
Show-flat costs are charged by first classifying nature, then setting th…
GB 50210-2018 建筑装饰装修工程质量验收标准GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准2026-09-25 - 07
Should the construction-installation cost in a design estimate carry provisional sums? — the stage division of provisional sums (BOQ/contract level) vs reserve funds (estimate level)
No. The construction-installation cost (works cost) in a design estimate…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 2.0.13、1.0.2、8.3.1 条T/ZBD 100.3-2022 · Work Guideline for Compilation of Design Estimates of Construction Projects 第 4.1.1、4.5.1、4.5.4 条及App. A、App. ETB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第 2.6 节2026-09-25 - 08
Provisional sums - ownership and use, two editions compared: GB 50500-2013 Section 9.15 vs GB/T 50500-2024 Clauses 2.0.13/8.3.1/8.3.5 - held by the employer, used per instruction, balance to the employer
Both editions share the core logic: the provisional sum is included in t…
GB/T 50500-2024 建设工程工程量清单计价标准(第2.0.13、7.2.3、8.3.1、8.3.5、9.4.6条)GB 50500-2013 建设工程工程量清单计价规范(第9.15节,已废止)2026-09-25 - 09
Screening double counting in budget documents: five high-frequency duplication scenarios and judgment principles
The general principle for judging double counting: content already inclu…
GB/T 51095-2015 第5.1.5条、第5.3.8条GB 50860-2013 第3.0.5条GB 50861-2013 第4.2.7条2026-09-25 - 10
Adjustment of the contract price (GB/T 50500-2024 Chapter 8): eleven triggering events, mechanism by section, and FIDIC mapping
Adjustment of the contract price is the mechanism for changing the contr…
GB/T 50500-2024 建设工程工程量清单计价标准(第8.1.1/8.1.2条、第8.2~8.11节、第7.5节、App. A、App. G)FIDIC Red/Yellow Book 2017(第13.3、13.4、13.6、13.7、20.2.1 条〔对照〕)GB/T 50875-2013 工程造价术语标准2026-09-25 - 11
GB/T 50500-2024: definitions of the three pricing methods (unit rate / lump sum / rate-based) and their applicability to each BOQ category
GB/T 50500-2024 provides: work-section BOQ items and day-work items shou…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.10~2.0.12、3.1.5、3.2.1、3.2.7条2026-09-25 - 12
Old-vs-new rules on the advance payment ratio: GB/T 50500-2024 Clauses 9.2.2/9.2.3 vs GB 50500-2013 Clause 10.1.2 — the 10%–30% band and changed deduction bases
The 10%–30% payment band is retained in GB/T 50500-2024 but the deductio…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 9.2.2 条、第 9.2.3 条GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第 10.1.2 条(已废止)2026-09-25 - 13
Provisional sums at final account: settlement line item, replacement paths, VAT basis and review essentials (GB/T 50500-2024)
At final account, provisional sums are dealt with as "the actually deter…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准T/ZBD 100.5-2023 建设工程结算审核作业指引2026-09-25