Provisional sums - ownership and use, two editions compared: GB 50500-2013 Section 9.15 vs GB/T 50500-2024 Clauses 2.0.13/8.3.1/8.3.5 - held by the employer, used per instruction, balance to the employer
Both editions share the core logic: the provisional sum is included in the contract price but is held by the employer and used per the employer's instructions; only amounts actually incurred go to the contractor; the unused balance (fully deducted at settlement) belongs to the employer. Three substantive 2024 changes: (1) "used per instructions issued by the employer" is promoted from the 2013 commentary into the body text 8.3.1; (2) new 8.3.5 with dual settlement paths (no adjustment event - fully deducted at settlement; event occurred - declared and verified per Chapter 8, paid per Chapters 9/10); (3) new 9.4.6 concurrent payment with progress payments and 7.2.3 measurement-basis clauses. Peripheral change: 2013 was a mandatory GB (repealed); 2024 is a recommended GB/T.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准(第2.0.13、7.2.3、8.3.1、8.3.5、9.4.6条)
- GB 50500-2013 建设工程工程量清单计价规范(第9.15节,已废止)
Topic Positioning
Comparing the repealed GB 50500-2013 Section 9.15 with the current GB/T 50500-2024 Clauses 2.0.13, 8.3.1, and 8.3.5: who holds the provisional sum, how it is used, and who gets the balance at settlement - plus the substantive 2024 changes.
Core Conclusions
Identical allocation logic across editions: held by the employer -> used per the employer's instructions -> only actual occurrence transfers to the contractor -> unused balance/portion to the employer. Original texts (paired):
- GB 50500-2013 9.15.1: "The provisional sum in the signed contract price shall be held and used by the employer." 9.15.2: "After the employer has paid per Sections 9.1-9.14 of this code, the balance of the provisional sum shall belong to the employer." Commentary: "The provisional sum in the signed contract price may only be used per the employer's instructions. Though included in the contract price, it is not owned by the contractor and does not necessarily occur; only upon actual occurrence per the contract does it become the contractor's due, incorporated into the settlement price."
- GB/T 50500-2024 8.3.1: "The provisional sum within the total contract price shall be held by the employer and used per instructions issued by the employer. Though included in the total contract price, it is not owned by the contractor and does not necessarily occur; only upon actual occurrence per the contract does it become the contractor's due payment, incorporated into the settlement price; unused provisional sums at final settlement belong to the employer."
- GB/T 50500-2024 term 2.0.13: the provisional sum is "an amount provisionally set by the employer in the BOQ and included in the total contract price, reserved for works, services, and price adjustments that cannot be determined or detailed at tendering", "may be used partly or wholly per the employer's instructions; if not needed, it shall be deducted from the total contract price".
Three substantive 2024 changes:
- "Use per instruction" promoted from commentary to body text: 2013's body said only "held and used by the employer", with the instruction rule in the commentary; 2024 writes it into 8.3.1 itself.
- New 8.3.5 refines settlement into two paths: with no adjustment event, "the provisional sum included in the total contract price shall be fully deducted at settlement"; with an event, both parties declare, verify, and determine the adjusted price per Chapter 8 and pay per Chapters 9 and 10. It also distinguishes two uses: sums for not-yet-specified works/services are computed from the actual work performed at the employer's request; parts not requested "shall be deducted from the total contract price at final settlement".
- New interim-payment and measurement clauses: 9.4.6 - sums for unforeseen works, services, and adjustments are computed from actual cumulative completion and paid concurrently with progress payments at the value confirmed by both parties; 7.2.3 - work-item-list items for provisional-sum projects completed at the employer's request are measured per 7.2.1 as the basis for adjusting the provisional sum.
Peripheral: GB 50500-2013 (mandatory GB) is repealed; GB/T 50500-2024 is recommended (GB/T). Provisional sums preferably use lump-sum pricing (2.0.10-2.0.12).
Applicable Boundaries
- For building, municipal, and similar works priced under the GB 50500 series; sectors with their own standards (highways, railways) follow those.
- GB 50500-2013 is repealed - cite GB/T 50500-2024 in practice; contractual terms prevail.
- "Balance to the employer" covers only the unused portion; amounts actually incurred per instruction and confirmed are paid to the contractor - not a forfeiture clause.
- Provisional sum is not prime sum: material/specialist prime sums follow Section 8.4 - do not conflate.
Further Reading
- GB/T 50500-2024: 2.0.13 (term), 8.3.1, 8.3.5 (adjustment), 9.4.6 (interim payment), 7.2.3 (measurement).
- GB 50500-2013: 9.15.1-9.15.2 and commentary (repealed; comparison only).
- Companion: provisional-sum settlement treatment and prime-sum rules in Section 8.4 - see cited cards.
Keywords
- provisional sums
- provisional sum
- GB/T 50500-2024
- GB 50500-2013
- 发包人掌握
- 余额归发包人
- adjustment of the contract price
- final account