GB/T 50500-2024: definitions of the three pricing methods (unit rate / lump sum / rate-based) and their applicability to each BOQ category

GB/T 50500-2024 provides: work-section BOQ items and day-work items should use unit-rate pricing (quantity x comprehensive rate); measures items should use lump-sum or rate-based pricing; provisional sums and specialist-work provisional amounts should use lump-sum pricing; main-contract services should use rate-based or lump-sum pricing (shared passage of Clauses 2.0.10-2.0.12). Clause 3.1.5 is the catch-all: where unit-rate or lump-sum pricing is unsuitable, rate-based or other methods may be used, with pricing requirements and price-adjustment rules stated in the tender and contract documents.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.10~2.0.12、3.1.5、3.2.1、3.2.7条

Topic Positioning

This card answers the standard definitions of unit-rate, lump-sum, and percentage-rate based pricing under GB/T 50500-2024 "Standard for BOQ pricing of construction works", and which method suits each BOQ category (work sections, preliminary items, dayworks, provisional sums, provisional sums for nominated specialist subcontract works, main contractor's attendance and coordination provisions) — for BOQ tendering, contract pricing, and settlement.

Core Conclusions

Definitions (Clauses 2.0.10-2.0.12):

  • Unit-rate pricing: computing payment as quantity x all-in unit rate in the BOQ.
  • Lump-sum pricing: computing payment as a total price per item in the BOQ.
  • Percentage-rate based pricing: computing payment as the base to which percentage rates are applied x the rate in the BOQ.

Applicability (shared passage of the three term clauses): "The BOQ pricing methods are mainly unit-rate, lump-sum, and percentage-rate based. Work-section items and dayworks should use unit-rate pricing; preliminary items should use lump-sum or percentage-rate based pricing; provisional sums and provisional sums for nominated specialist subcontract works should use lump-sum pricing; main contractor's attendance and coordination provisions should use percentage-rate based or lump-sum pricing."

Refined clauses:

  • Clause 3.2.1: work-section items should use unit-rate pricing and preliminary items lump-sum pricing; unit-rate items are priced as quantity x all-in unit rate; lump-sum items as a total per item. The all-in unit rate of work-section items shall allow for reasonable risk costs. Special case: special-case preliminary items whose construction method statement the employer has required, as agreed in the contract, to pass expert panel review may be priced on a unit-rate basis and listed in the work-section BOQ, priced as quantity x all-in unit rate.
  • Clause 3.2.7 (other items): provisional sums for nominated specialist subcontract works may be lump-sum priced, priced per item; provisional sums and main contractor's attendance and coordination provisions may be percentage-rate based or lump-sum priced, priced as the base to which the percentage rate is applied x rate or per item; dayworks may use the unit-rate method of Clause 3.2.1.
  • Clause 3.1.5 (catch-all): item payments may use unit-rate or lump-sum pricing; where unsuitable given the nature of the project, percentage-rate based or other methods may be used, with pricing requirements and price-adjustment rules stated in the tender and contract documents.

Applicable Boundaries

Applies to employer-contractor projects priced on a BOQ basis under GB/T 50500-2024. The standard is recommended (GB/T) and the clauses use "should" (recommendatory): parties may adjust via tender/contract documents, but per 3.1.5 the pricing requirements and adjustment rules must be stated. Railway and other specialty works follow their industry pricing rules; local cost-data standards may divide bills differently, but the pricing-method rules are substantially the same.

Further Reading

See GB/T 50500-2024: Clauses 2.0.10 (unit-rate), 2.0.11 (lump-sum), 2.0.12 (percentage-rate based), 3.1.5 (catch-all), 3.2.1 (work-section/preliminary item rules and the special-case exception), 3.2.7 (other items). All-in unit rate composition in 2.0.9; preliminary-item change adjustments in 7.3.1, 8.9.1, 8.9.4-8.9.7.