The unit-price / total-price preliminaries divide and its migration in the BOQ system: the 2013 'unit-price items / total-price items' split of GB 50500-2013 clauses 4.3.1-4.3.2 against the three pricing methods of GB/T 50500-2024 clauses 2.0.10~2.0.12 and 3.2.1
GB 50500-2013 clause 4.3.2 split preliminaries by 'whether quantities can be computed': those that cannot (site discipline, safety, temporary facilities) price 'per item' as total-price items; those that can (scaffolds, dewatering) price 'per quantity' as unit-price items, with clause 4.3.1 mandatory (preliminaries lists compiled per the current national measurement codes). GB/T 50500-2024 drops the split: pricing now runs by unit, total or rate (2.0.10~2.0.12); work items and dayworks suit unit pricing, preliminaries preferably total or rate (3.2.1 - total, per item); quantifiable specialist preliminaries such as concrete formwork have moved into the work-item list of GB/T 50854-2024 (Appendix E Table E.5.1, code 010505), and expert-reviewed specialist schemes may price by unit within the work-item list.
Applicable Codes
- GB/T 50500-2024 第2.0.10条、第2.0.11条、第2.0.12条
- GB/T 50500-2024 第3.1.5条
- GB/T 50500-2024 第3.2.1条
- GB/T 50854-2024 App. R Table R.1.1(措施项目,code 011601)
- GB/T 50854-2024 App. E Table E.5.1(混凝土模板,code 010505)
- GB 50500-2013 第4.3.1条(强制性条文)、第4.3.2条(已被 GB/T 50500-2024 替代)
Positioning
The frequent dispute 'how do unit-price and total-price preliminaries divide': the 2013 two-class text, the current three-method basis of 2024, and where quantifiable preliminaries (concrete formwork) now sit - landing the divide on BOQ codes.
Core conclusions
1. 2013: split by measurability (4.3.2 verbatim) 'The preliminaries list is itemised per the actual works... the measurement codes divide preliminaries into two classes: items whose quantities cannot be computed - site discipline and safety protection, temporary facilities etc. - price "per item", called total-price items; items whose quantities can be computed - scaffolds, dewatering etc. - price "per quantity", better for fixing and adjusting the cost, called unit-price items. Where the appendices list no item matching the works, supplement per the actual case.' Clause 4.3.1: 'the preliminaries list must be compiled per the current national measurement codes' - a mandatory provision.
2. 2024: the split dropped; three pricing methods; preliminaries preferably total
- 2.0.10 unit pricing: quantity x all-in rate.
- 2.0.11 total pricing: per item at a total price.
- 2.0.12 rate pricing: charging base x rate.
- Shared application: work-item and daywork items suit unit pricing; preliminaries lists suit total or rate pricing; provisional sums and specialist provisional sums suit totals; attendance suits rate or total.
- 3.1.5 fallback: items price by unit or total; otherwise rate or the like, with requirements and adjustment rules stated in the tender and contract.
- 3.2.1: unit-priced items = quantity x rate; total-priced = per item; work-item lists preferably unit-priced, preliminaries preferably total; total-priced lists may price per item; the rate carries reasonable risk. Specialist preliminaries schemes passed by expert review may price by unit and list within the work-item list at quantity x rate.
3. The divide lands on codes: formwork-type preliminaries moved into work items
- The preliminaries list keeps only the non-physical items of GB/T 50854-2024 Appendix R Table R.1.1 (011601): scaffolds, vertical transport, large-plant mobilisation, drainage, dewatering, temporary facilities, site discipline, environment, safety, winter / rainy additions, night work, special-region additions, double handling etc.
- Quantifiable 'quantity x rate' concrete formwork sits in Appendix E Table E.5.1 'concrete formwork (010505)' - a work item, not a preliminaries item.
- So the right question is no longer 'unit-price or total-price preliminaries' but which list the content sits in (011601 versus work items) and on which pricing method - work-item listed: unit-priced, quantity-variable; 011601 listed: preferably total (or rate), lumped per item.
Applicable boundaries
- Building and decoration (GB/T 50854-2024); railway, highway and water codes still hold measurable preliminaries items - the code conclusions never carry; railway terms are 'construction-measures costs' and 'work safety funds'.
- 2013 is superseded - legacy and comparison only; new contracts run 2024.
- This card fixes division and pricing attribution; whether preliminaries adjust (7.3.1's five exceptions, variation and BOQ-error channels) is another topic.
- Tender / contract pricing agreements prevail (3.1.5 allows other methods, stated).
Further reading
GB/T 50500-2024 clauses 2.0.10~2.0.12 (definitions and shared text), 3.1.5, 3.2.1, 7.3.1; GB/T 50854-2024 Appendix R Table R.1.1 (011601) and Appendix E Table E.5.1 (010505); GB 50500-2013 clauses 4.3.1 (mandatory) and 4.3.2 (superseded).