Boundary distinctions among omitted BOQ items (BOQ errors), provisional prices, provisional sums, dayworks and site instruction records in contract price adjustment: required but not listed vs listed but unpriced vs confirmation evidence for unforeseen matters

Under GB/T 50500-2024: omission falls under 'BOQ errors' (clause 2.0.27, differences between the BOQ and the contract drawings in items, item descriptions and quantities), handled by re-determining the all-in unit rate under sections 8.2 and 8.9; a provisional price is an item already listed but with the price provisional - once the price is fixed only the price element is replaced: for items subject to mandatory tendering by law, the pre-tax tendered material price or the VAT-inclusive tendered specialist subcontract price replaces it (8.4.1); for items not subject to mandatory tendering, the pre-tax price confirmed by the employer from enquiry or the contractor's own quote replaces it, with the VAT change computed (8.4.5, 8.4.7); a material provisional price adjusts only the pre-tax material price within the all-in unit rate, leaving all other cost elements untouched. Provisional sums are controlled by the employer and used on instruction (8.3.1); when used for works not fully foreseen or specified, the price is adjusted as contract unit rates x quantities from the confirmed drawings (8.3.2); where no adjustment event has occurred, the whole amount is deducted at final account (8.3.5). Dayworks are a pricing method for work not suitably priced under the contract and the pricing standards (8.6.1); at settlement they are counted as actually incurred, but the daywork items already included in the contract price are deducted (8.6.5). Site instruction records are certification of process facts (GB/T 50875-2013 clause 3.4.8, GB/T 50500-2024 clause 12.2.1) and are not an independent price adjustment matter in themselves. The same matter must not be priced twice - once as a new BOQ item for omission and again under dayworks or provisional sums.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.27、7.2.1、8.2、8.3.1、8.3.2、8.3.5、8.4.1、8.4.5、8.4.7、8.6.1、8.6.5、8.9、10.3.2、12.2.1条
  • GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.9、5.9.1、5.9.2条
  • GB/T 50875-2013 · Standard glossary of project costs 第3.4.8条

Topic positioning

Answers what each of the five easily confused price adjustment matters at final account - omitted BOQ items, provisional prices, provisional sums, dayworks and site instruction records - is, how each is priced, and where their boundaries lie, for qualitative judgement in final account review and contract price adjustment.

Core conclusion

1. Omitted BOQ items = required but not listed (BOQ errors). GB/T 50500-2024 clause 2.0.27 defines: 'differences between the items listed in the work item lists of the BOQ and the items required by the contract drawings and contract specifications, in terms of listing, item description and quantities, including surplus items, omissions and errors, mismatched item descriptions, quantity deviations and other like cases.' The qualitative benchmark is clause 7.2.1: differences between the contract BOQ and the contract drawings are BOQ errors (adjusted under section 8.2); differences between the contract drawings and the actual construction drawings are variations (adjusted under the variation rules). The handling path is 're-determining the all-in unit rate': where the change is within 15% (15% inclusive) of the quantity in the contract BOQ, clause 8.9.1 applies with five rate-setting tiers; beyond 15%, clause 8.9.2 adjusts up or down in light of bulk purchase concessions. For unit-rate contracts the BOQ error risk sits with the employer; for lump-sum contracts with the contractor (except items priced on provisional quantities).

2. Provisional price = listed but unpriced. Clause 8.4.1: 'Where materials and/or specialist works given provisional prices in the BOQ are subject to mandatory tendering by law, the pre-tax material price and/or the VAT-inclusive specialist subcontract price determined by tendering shall replace the provisional price to adjust the contract price. A material provisional price is a pre-tax unit price (excluding VAT), while a specialist works provisional price is a VAT-inclusive price (including VAT).' Substitution rules: for materials, the tendered pre-tax price replaces the provisional pre-tax price; for specialist subcontracts, the tendered VAT-inclusive price replaces the provisional VAT-inclusive price. Clause 8.4.5 (materials not subject to mandatory tendering): the contractor may procure by market enquiry or its own quote, and after confirmation by the employer the pre-tax price replaces the provisional price, or both parties jointly enquire and confirm the replacement pre-tax price, computing the VAT change caused by the price adjustment. Clause 8.4.7 (specialist works not subject to mandatory tendering): the VAT-inclusive specialist works price may be determined under section 8.10 to replace the provisional price, or determined by joint tendering of both parties. Key point: a material provisional price adjustment 'adjusts only the provisional material price (pre-tax) within the all-in unit rate; the other costs included in the all-in unit rate shall not be adjusted' - no re-rating of the build-up, no overheads or profit added.

3. Provisional sums = a reserve amount under the employer's control. Clause 8.3.1: 'Provisional sums within the contract price shall be under the employer's control and used in accordance with the instructions issued by the employer.' Although included in the contract price, provisional sums belong neither to the contractor nor necessarily to incurred work; only when actually incurred as agreed in the contract do they become payment due to the contractor, and unused provisional sums revert to the employer at final account. Clause 8.3.2: where provisional sums are used for works not fully foreseen or specified, the parties compute the work item quantities from the confirmed construction drawings and adjust the price at contract unit rates; changes to preliminaries are computed under section 8.9; the contract price is adjusted by the difference between the determined adjustment price and the provisional sums, and the contract price adjustment for the provisional sum difference shall include the VAT adjustment. Clause 8.3.5: where no provisional-sum adjustment event has occurred during performance, the provisional sums included in the contract price are deducted in full at settlement; where events occurred, they are declared, verified and determined under Chapter 8 and paid under Chapters 9 and 10. Provisional sums are thus a funding pool: once drawn they are still measured and priced on BOQ terms, and cannot be turned into a fresh price adjustment basis.

4. Dayworks = a pricing method, not a category of matter. Clause 8.6.1: 'Where contract work is not suitably priced under the contract and the national and industry BOQ pricing standards, the employer and the contractor may adopt dayworks pricing.' Clause 8.6.5: at settlement, the daywork items calculable under the contract are all counted into the settlement total, but the daywork items in the contract BOQ included in the contract price are deducted from the settlement total; the VAT on daywork items is adjusted on the difference between the confirmed total of actually incurred daywork payments and the daywork total in the contract price, multiplied by the applicable VAT rate - count the actual, deduct the listed, avoiding double counting between the original daywork list and actual occurrences.

5. Site instruction records = evidence certifying facts, not an independent price adjustment matter. GB/T 50875-2013 clause 3.4.8: 'Site instruction: certification signed by the employer's site representative (or the supervising engineer or cost consultant authorised by it) and the contractor's site representative regarding liability events arising during construction.' GB/T 50500-2024 clause 12.2.1: 'The parties shall agree in the contract the scope of duties of their respective site management personnel; written documents signed and confirmed by such personnel within their scope of duties are valid evidence for pricing, except where other valid evidence or verification proves them false.' GB/T 51262-2017 section 5.9 lists the site record situations: employer verbal instructions to be converted into written records; employer written notices involving implementation of the works requiring certification of labour, materials and plant; items listed in the BOQ but found on site to differ (for example running sand in soil classification); suspension attributable to the employer requiring records to support claim costs; material price market movements requiring certification of purchase quantities and unit prices. Assessment rules: clause 5.9.1 grades by the completeness of the record - where labour/material/machine-shift quantities and prices are stated, price by the recorded quantities and prices; where only labour quantities are stated without rates, refer to the assessed labour rates of the project with an appropriate uplift (an experience-based practice of about 20%); where only material and machine-shift quantities are stated without prices, price at the corresponding prices of the assessed project; where only a lump sum is stated without breakdown, price by that lump sum; where the quantities of minor works differ from actual completion, price by actual completion. Clause 5.9.2 deals with defective records - where a party only signed receipt without signifying agreement, and the contractor has evidence the work was done, the expert assessor may issue an assessment opinion listed separately for the commissioning party to judge; where there is neither quantity nor price, only a statement of the work, the parties first negotiate; failing agreement, the assessor analyses professionally under the principles and methods agreed in the contract and issues an inferential opinion.

6. Boundary tests. (1) Is the item in the BOQ? No item but required by the drawings = omission (BOQ error); item present but price pending = provisional price; item present and priced but site facts inconsistent with the BOQ = a variation or site record matter. (2) Where does the money come from? Omission adjustments are listed separately as final account item 2 'BOQ error adjustment price'; provisional price differences go to item 4; provisional sum drawdowns go to item 3 measured at contract unit rates; dayworks go to item 6 net of the listed daywork amount; variation increases and decreases and claims are each listed separately. (3) Prevent double counting: the same physical work must not be priced both as a new BOQ item for omission and again under provisional sums, or priced for omission and again taken in full as dayworks; records settle only 'facts and quantities' - the price must still return to the contract rates, analogous rate conversion or negotiated rate build-up rules.

Applicability boundaries

Applies to contract price adjustment and final account review on BOQ-priced works. Limits: (1) the 'adjust the price difference only, no re-rating' treatment applies to material (and permanent equipment) provisional prices only - specialist works provisional prices are VAT-inclusive and wholly replaced by the tendered VAT-inclusive subcontract price under different rules; (2) a provisional sum drawdown requires an employer instruction; the contractor may not use it on its own; (3) dayworks presuppose a contractual daywork list and certification of actual occurrence; absent agreement, they should not be created after the event; (4) the evidentiary force of site records is limited to the scope of duties of the site management personnel and may be overturned by other valid evidence; (5) GB/T 50500-2024 is a recommended national standard; express contractual agreements prevail. This card does not settle the rate-setting tiers for omitted items (see the section 8.9 rules) and does not cover price fluctuation adjustment or changes in laws and regulations.

Further reading

GB/T 50500-2024 'Standard for BOQ Pricing of Construction Works': clause 2.0.27 (BOQ errors), clause 7.2.1 (the dividing benchmark between errors and variations), section 8.2 (BOQ error adjustment), clauses 8.3.1, 8.3.2, 8.3.5 (control, use and settlement deduction of provisional sums), clauses 8.4.1, 8.4.5, 8.4.7 (provisional price substitution rules and the material/specialist works difference), clauses 8.6.1, 8.6.5 (dayworks pricing and settlement deduction), section 8.9 (setting of all-in unit rates), clause 10.3.2 (order of final account price line items), clause 12.2.1 (evidentiary force of documents signed by site management personnel); GB/T 51262-2017 'Code for Construction Cost Expert Assessment' section 5.9 (classification of site record situations), clause 5.9.1 (five grades for assessing record costs), clause 5.9.2 (assessment of defective records); GB/T 50875-2013 'Standard for Construction Cost Terminology' clause 3.4.8 (site instruction term).