provisional sum for specified materials / nominated works
Concept Guide
Concept
In Chinese practice, a provisional sum for specified materials / nominated works denotes an item that will certainly be executed but whose price cannot be fixed at tender — typically specified materials, equipment or nominated specialist subcontract works. The Employer states the amount in the bill of quantities; bidders carry that amount without competing and it forms part of the Contract Price. The actual price is fixed during construction and the Contract Price is adjusted accordingly (adjustment of provisional prices after procurement): price only, quantity unchanged.
Mechanism:
- Initiation and pricing: the Employer lists the item and states the amount; the Contractor organises procurement.
- Fixing the price: where tendering is legally mandatory, Employer and Contractor tender jointly to select the supplier or specialist subcontractor; where it is not, the Contractor proposes a supplier and the Employer approves and signs off.
- Risk: price-uncertainty risk rests with the Employer; organisation, programme and coordination risk with the Contractor.
- Related mechanisms: the item interacts with provisional sums, dayworks, subcontract administration and specialist subcontract tendering. The key difference from provisional sums is that these items will definitely occur, whereas provisional sums cover costs whose occurrence is still uncertain.
FIDIC Mapping
FIDIC has no single equivalent. The Chinese concept is approximated by a combination of provisional sums (Sub-Clause 13.4) and nominated Subcontractors: provisional sums for payment, and nominated Subcontractors (Sub-Clause 4.5 in the Yellow Book; 5.2 in the Red Book) for nominated works. Older FIDIC forms and British-practice bills once used prime cost (PC) items for materials of deferred price, but the 2017 suite absorbs them into Provisional Sums.
| Chinese term | FIDIC term | Relation | Key point |
|---|---|---|---|
| 暂估价 | provisional sum for specified materials / nominated works | distinct | no single FIDIC equivalent |
| 材料暂估价 | prime cost (PC) sum for materials | adjacent | reimbursed at actual cost |
| 专业工程暂估价 | provisional sum for nominated specialist subcontract works | adjacent | linked to nominated subcontracts |
| 暂列金额 | provisional sums | adjacent | single purpose, 13.4 |
| 计日工 | dayworks | adjacent | measured and paid on actuals |
| 暂估价调整 | adjustment of provisional prices after procurement | adjacent | price set after procurement |
Differences: under FIDIC, provisional sums may vary in both occurrence and quantity, are used only as instructed by the Engineer under Sub-Clause 13.4, and are paid on the basis of what is actually done; nominated Subcontractors are instructed by the Engineer and the Contractor has a right of reasonable objection (Sub-Clause 4.5 in the Yellow Book, 5.2 in the Red Book). In Chinese practice the scope is already defined and only the price is deferred, and the fixing of that price is embedded in a statutory tendering procedure or in the Employer's approval — joint pricing by the Parties rather than a unilateral instruction by the Engineer.
Caution: when reading an FIDIC contract, do not treat provisional sums as the Chinese provisional-price item and carry them as non-competitive amounts — the Engineer may increase, reduce or omit them, and the adjustment and risk routes are entirely different.
| Chinese Term | English Term | FIDIC Term | Relation | Notes |
|---|---|---|---|---|
| 暂估价 | provisional sum for specified materials / nominated works | Provisional Sums (Sub-Clause 13.4) + Nominated Subcontractors (黄皮书 Sub-Clause 4.5;红皮书 5.2) | distinct | FIDIC 无单一对应物,以暂列金额与指定分包组合近似;旧版 prime cost items 已并入 Provisional Sums,2017 版无独立 PC 机制。 |
| 材料暂估价 | prime cost (PC) sum for materials | Provisional Sums (Sub-Clause 13.4) | adjacent | FIDIC 无直接对应,最接近的是暂列金额项下按工程师指示采购指定材料、按指示金额支付。 |
| 专业工程暂估价 | provisional sum for nominated specialist subcontract works | Nominated Subcontractors (黄皮书 Sub-Clause 4.5;红皮书 5.2) | adjacent | FIDIC 由工程师指示聘用指定分包、承包商有合理反对权;中国由发承包双方共同招标或发包人签认。 |
| 暂列金额 | provisional sums | Provisional Sums (Sub-Clause 13.4) | adjacent | 中国暂列金额用于是否发生尚不确定的费用,FIDIC 建议雇主在合同中专列清单界定每笔暂列金额的用途。 |
Updated 2026-09-13
- 01
Who bears the costs of organising tendering and of cooperation for provisionally priced materials and provisionally priced specialist works, in three scenarios (employer as tenderer / contractor as tenderer / joint tendering) (GB/T 50500-2024, 8.4.2-8.4.4 + GF-2020-0216, 13.4.1)
Under GB/T 50500-2024, 8.4.2-8.4.4: where the employer acts as tenderer…
GB/T 50500-2024 建设工程工程量清单计价标准 第8.4.2条、第8.4.3条、第8.4.4条、第8.4.7条建设项目工程总承包合同(示范文本)GF-2020-0216 通用合同条件第13.4.1项、第13.4.2项及专用合同条件第13.4条中华人民共和国招标投标法实施条例 第二十九条2026-10-29 - 02
Provisional prices (materials / specialist works): the settlement adjustment procedure of replacing the provisional price with the actual confirmed price - legal position, the submission-checking-review-re-examination-confirmation chain and deemed approval on expiry, the two confirmation routes (compulsory tendering and otherwise), adjusting only the pre-tax material price, the deduction direction when the confirmed price is lower, the boundary against material price adjustment, and the clause mapping of GB/T 50500-2024 against GB 50500-2013
The final account replaces the provisional price with the 'confirmed pri…
GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.14、3.2.3、3.3.5、6.2.5、8.1.2~8.1.6、8.4.1~8.4.8、8.5.3、8.7.2~8.7.5、8.10、9.4.6、10.3.2条及App. A、App. G.2GB 50500-2013 建设工程工程量清单计价规范 第5.2.5、6.2.5、9.9.1~9.9.4条中华人民共和国招标投标法实施条例(2018修订)第二十九条2026-10-25 - 03
Boundary distinctions among omitted BOQ items (BOQ errors), provisional prices, provisional sums, dayworks and site instruction records in contract price adjustment: required but not listed vs listed but unpriced vs confirmation evidence for unforeseen matters
Under GB/T 50500-2024: omission falls under 'BOQ errors' (clause 2.0.27…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.27、7.2.1、8.2、8.3.1、8.3.2、8.3.5、8.4.1、8.4.5、8.4.7、8.6.1、8.6.5、8.9、10.3.2、12.2.1条GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.9、5.9.1、5.9.2条GB/T 50875-2013 · Standard glossary of project costs 第3.4.8条2026-10-25 - 04
Settlement pricing when the confirmed price of a provisionally priced material differs from published price information: the procedurally formed confirmed price (net award price, or employer-confirmed enquiry price) replaces the provisional sum, published prices serving only as the contractually agreed base or a provisional fallback in disputes
Settlement follows the confirmed price formed under the contractual proc…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.14、3.3.5、8.4.1~8.4.6、10.3.2条及App. A 第A.2.2、A.2.5条GB/T 50875-2013 · Standard glossary of project costs 第2.2.60、2.1.16条T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第3.1.7条2026-10-18 - 05
Organizing the certification of material quality and price for installation materials and equipment: four applicable situations, a six-step implementation process, situation-based rules for employer approval of material prices, and dispute fallbacks
Certification of material quality and price is organized as 'lock qualit…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.4-2023 建设工程造价鉴定作业指引T/ZBD 100.5-2023 建设工程结算审核作业指引2026-09-25 - 06
Adjustment of the contract price (GB/T 50500-2024 Chapter 8): eleven triggering events, mechanism by section, and FIDIC mapping
Adjustment of the contract price is the mechanism for changing the contr…
GB/T 50500-2024 建设工程工程量清单计价标准(第8.1.1/8.1.2条、第8.2~8.11节、第7.5节、App. A、App. G)FIDIC Red/Yellow Book 2017(第13.3、13.4、13.6、13.7、20.2.1 条〔对照〕)GB/T 50875-2013 工程造价术语标准2026-09-25 - 07
Pricing rules for prime-sum estimates (provisional sums) of specialist works: GB/T 50500-2024 VAT-inclusive, lump-sum per item, deduction from the VAT base, and substitution on adjustment (compared with GB 50500-2013)
GB/T 50500-2024 defines the prime-sum estimate of specialist works as "s…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works (第2.0.15、3.1.6、3.2.7、3.2.11、8.4.1、8.4.7条)GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works (第4.4、5.2.5、9.9节,已废止)住房城乡建设部公告2024年第212号2026-09-25 - 08
Identifying duplicate measurement in subcontract final accounts: a four-layer investigation method — contract interfaces, stage settlements during construction, measurement rules, and cost composition
Identify duplicate measurement in subcontract final accounts by investig…
T/ZBD 100.5-2023 工程结算审核作业指引GB/T 50500-2024 建设工程工程量清单计价标准DB37/T 5130-2018 建设工程造价咨询服务规范2026-09-25 - 09
Tender pricing strategy: market price enquiry as the primary basis with published price information as auxiliary cross-validation — bidders price independently and are not compelled to use published price information
Tender pricing takes market price enquiry as primary and published price…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准T/ZBD 100.1-2022 建设工程造价数据建设通用标准2026-09-25 - 10
Determining re-tendering of provisional-sum specialty works, organization modes, and tax-inclusive price confirmation rules (Implementation Regulations Article 29 + GB/T 50500-2024 Section 8.4)
Specialty works included in the general-contract scope as provisional su…
招标投标法实施条例(2018修订)第二十九条GB/T 50500-2024 建设工程工程量清单计价标准 第8.4节必须招标的工程项目规定(发改委16号令)第五条2026-09-25 - 11
Provisional sums at final account: settlement line item, replacement paths, VAT basis and review essentials (GB/T 50500-2024)
At final account, provisional sums are dealt with as "the actually deter…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准T/ZBD 100.5-2023 建设工程结算审核作业指引2026-09-25 - 12
Price adjustment rules for brand changes of decoration materials: three situations, adjusting the material cost only, and the certification of material quality and price procedure
Brand-change price adjustment = replace the original price with the conf…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范T/ZBD 100.4-2023 建设工程造价鉴定作业指引2026-09-25